Monthly State Let Construction Report For Dallas District As Of Aug 12, 2014 Page 2 Of 8

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDENTON
Highway US 377
From AT HICKORY CREEK AND RELIEF
To .
CSJ 0081-03-051
Proj ID BR 2013(177)
Work Type REHAB AND WIDEN BRIDGE AND APPROACH
 
0.739 4078318.50 407515.44 3077684.98 75.4
Work Order 10-30-13
Work Began 01-07-14
Work Completed  
Time Computed 12-29-13
Contract Working Days 157
Addl Days Granted 0
Working Days Charged 145
Percent Time Used 92
Contractor(s)
REBCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0081-03-051
ACU CONSTRUCTION LLC (0.42%)
C.T. AND S. METALWORKS, INC. (1.69%)
COWTOWN TRAFFIC CONTROL, INC.(0.18%)
JAGOE-PUBLIC COMPANY (4.76%)
LAYFIELD CONSTRUCTION, INC (2.00%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (2.51%)
S & S BRIDGE PAINTING, INC.( 10.86%)
SOUTHEAST GRINDING & GROOVING, LLC (0.11%)
STRIPING TECHNOLOGY, L.P.(1.08%)
WEST TEXAS REBAR PLACERS INC.(1.34%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.89%)
W.O.E. CONSTRUCTION(0.14%)
Contract # 08133029
Totals 4078318.50 407515.44 3077684.98 75.4

CountyDENTON
Highway US 377
From TARRANT COUNTY LINE
To HICKORY CREEK
CSJ 0081-03-052
Proj ID STP 2013(180)
Work Type BASE REP, OV
 
15.648 4479766.95 17722.12 4300084.08 96.7
Work Order 01-03-13
Work Began 03-25-13
Work Completed  
Time Computed 03-04-13
Contract Working Days 222
Addl Days Granted 4
Working Days Charged 262
Percent Time Used 115
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0081-03-052
HIGHWAY TECHNOLOGIES, INC. (0.36%)
STRIPING TECHNOLOGY, L.P.(3.33%)
TEX OP CONSTRUCTION, LP(2.63%)
BUYERS BARRICADES, INC.(0.17%)
Contract # 11123009
Totals 4479766.95 17722.12 4300084.08 96.7

CountyDENTON
Highway US 377
From SOUTH OF BUS 377E
To BUS 377E NORTH OF PILOT POINT
CSJ 0081-06-029
Proj ID C 81-6-29
Work Type REHAB ROADWAY
 
3.702 7501346.55 466658.62 1651579.45 22.0
Work Order 03-07-14
Work Began 05-19-14
Work Completed  
Time Computed 03-23-14
Contract Working Days 264
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 22
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0081-06-029
CRAIG OLDEN, INC.(1.15%)
DUSTROL, INC.(1.24%)
IOWA BRIDGE & CULVERT, LC(3.94%)
K & S UTILITY CONTRACTORS, INC.( 28.85%)
MARCOM"S MOWING SERVICE, LLC (1.70%)
MEL"S ELECTRIC SERVICE, INC. (0.51%)
STORM WATER MANAGEMENT, INC. (0.37%)
STRIPING TECHNOLOGY, L.P.(2.42%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.73%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.56%)
RAMBO CONTRACTING, INC.( 10.99%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.87%)
Contract # 01143003
Totals 7501346.55 466658.62 1651579.45 22.0

CountyCOLLIN
Highway SH 289
From FM 455
To N BUS 289C, NORTH OF CELINA
CSJ 0091-03-021
Proj ID C 91-3-21
Work Type GRD, STR, PVMT, SIGNS
 
3.448 15996401.11 79450.00 4611875.28 28.8
Work Order 08-22-12
Work Began 02-14-13
Work Completed  
Time Computed 02-14-13
Contract Working Days 520
Addl Days Granted 30
Working Days Charged 157
Percent Time Used 28
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0091-03-021
ALLIANCE GEOTECHNICAL GROUP(0.21%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(0.11%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.14%)
FORTSON CONTRACTING, INC.(0.10%)
HIGHWAY TECHNOLOGIES, INC. (0.93%)
INDUS CONSTRUCTION, L.P. (0.90%)
JAGOE-PUBLIC COMPANY ( 13.49%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.97%)
LONE STAR BARRIER SERVICES, LLC(0.24%)
LONE STAR MANHOLE & STRUCTURES, LLC(4.63%)
TEX OP CONSTRUCTION, LP(0.74%)
MIKE ALBERT, INC.(1.33%)
W.O.E. CONSTRUCTION(0.29%)
EROSION CONTROL MANAGEMENT SERVICES(0.55%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.08%)
STRIPING TECHNOLOGY, L.P.(1.20%)
IRON CONCRETE CONSTRUCTION COMPANY, INC. (2.39%)
TEXAS INLETS, INC. (2.24%)
Contract # 06123003
Totals 15996401.11 79450.00 4611875.28 28.8

CountyCOLLIN
Highway SH 289
From US 380 INTERCHANGE
To NORTH OF FM 1461 / BS 289D
CSJ 0091-04-050
Proj ID C 91-4-50
Work Type GRD, STR, PVMT, SIGNS, RAMPS
 
3.144 17270901.44 415686.43 17102642.35 99.2
Work Order 10-13-11
Work Began 03-23-12
Work Completed  
Time Computed 03-23-12
Contract Working Days 619
Addl Days Granted 56
Working Days Charged 697
Percent Time Used 103
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0091-04-050
ALLIANCE GEOTECHNICAL GROUP(0.20%)
ARLINGTON PAVERS, INC. (0.03%)
CONCRETE CUTTING BY BOND (0.36%)
DUSTROL, INC.(0.64%)
HIGHWAY TECHNOLOGIES, INC. (1.44%)
INDUS CONSTRUCTION, L.P. (1.13%)
MIKE ALBERT, INC.(1.20%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 14.69%)
ROADWAY SOLUTIONS, INC.(4.41%)
TEXAS INLETS, INC. (4.43%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.10%)
STORM WATER MANAGEMENT, INC. (0.45%)
SKAGGS ROAD BORING INC.(0.12%)
SYNERGY SIGNS & SERVICES, LLC(0.15%)
ANCHOR FENCE GROUP, LLC(0.08%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.06%)
STRIPING TECHNOLOGY, L.P.(0.96%)
JET UNDERGROUND UTILITIES, INC.(0.19%)
NORTH TEXAS BOMANITE, INC. (0.59%)
W.O.E. CONSTRUCTION(0.08%)
Contract # 07113202
Totals 17270901.44 415686.43 17102642.35 99.2

CountyCOLLIN
Highway SH 289
From NORTH OF FM 1461 / BS 289D
To FM 455 IN CELINA
CSJ 0091-04-055
Proj ID C 91-4-55
Work Type GR, STR, PVMT, SIGNS, PVMT MKGS
 
4.090 18214018.09 1107009.70 16041530.43 88.0
Work Order 10-18-11
Work Began 06-22-12
Work Completed  
Time Computed 04-15-12
Contract Working Days 519
Addl Days Granted 187
Working Days Charged 664
Percent Time Used 94
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0091-04-055
ALLIANCE GEOTECHNICAL GROUP(0.18%)
ARLINGTON PAVERS, INC. (0.02%)
CONCRETE CUTTING BY BOND (0.32%)
DUSTROL, INC.(0.73%)
FORTSON CONTRACTING, INC.(0.15%)
HIGHWAY TECHNOLOGIES, INC. (0.88%)
INDUS CONSTRUCTION, L.P. (0.90%)
LONE STAR MANHOLE & STRUCTURES, LLC(6.25%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 15.14%)
STORM WATER MANAGEMENT, INC. (0.29%)
ROADWAY SOLUTIONS, INC.(1.97%)
FARR FOUNDATION, INC.(0.02%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.73%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.07%)
STRIPING TECHNOLOGY, L.P.(0.88%)
MIKE ALBERT, INC.(0.36%)
SYNERGY SIGNS & SERVICES, LLC(0.10%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.17%)
EROSION CONTROL MANAGEMENT SERVICES(0.02%)
IRON CONCRETE CONSTRUCTION COMPANY, INC. (0.60%)
Contract # 07113203
Totals 18214018.09 1107009.70 16041530.43 88.0

CountyCOLLIN
Highway SH 289
From PANTHER CREEK
To SOUTH OF US 380
CSJ 0091-04-058
Proj ID STP 2014(569)
Work Type LANDSCAPE DEVELOPMENT
 
4.457 376485.00 0.00 0.00 0.0
Work Order 04-15-14
Work Began 00-00-00
Work Completed  
Time Computed 05-01-14
Contract Working Days 53
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LANDSCAPE CONTRACTING AND IRRIGATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0091-04-058
MCBRIDE ELECTRIC, INC. (0.42%)
AQUA BORE(3.71%)
ALTUS TRAFFIC MANAGEMENT LLC (0.86%)
Contract # 03143034
Totals 376485.00 0.00 0.00 0.0

CountyCOLLIN
Highway SH 289
From NORTH OF US 380
To FM 455
CSJ 0091-04-059
Proj ID STP 2014(761)
Work Type LANDSCAPE DEVELOPMENT
 
7.234 649411.81 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-29-14
Work Began 00-00-00
Work Completed  
Time Computed 08-14-14
Contract Working Days 139
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0091-04-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143012
Totals 649411.81 0.00 0.00 0.0

CountyDALLAS
Highway SH 289
From ON SH 289 (PRESTON)
To AT ROYAL
CSJ 0091-06-049
Proj ID STP 2013(727)MM
Work Type INTERSECTION IMPROVEMENT
 
0.166 674540.86 0.00 14666.00 2.1
CountyDALLAS
Highway SH 289
From ON SH 289
To AT ROYAL LANE
CSJ 0091-06-055
Proj ID STP 2012(375)MM
Work Type ROW ACQ & UTIL ADJ
 
0.010 44707.50 0.00 0.00 0.0
Work Order 07-31-13
Work Began 00-00-00
Work Completed  
Time Computed 09-29-13
Contract Working Days 118
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REBCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0091-06-049
DURABLE SPECIALTIES, INC.( 15.16%)
M & M STRIPING & POWER WASHING, LLC(3.23%)
NORTH TEXAS CONTRACTING, INC.( 11.02%)
PREMIER PAVING, LTD. (3.55%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.76%)
Contract # 05133228
Totals 719248.36 0.00 14666.00 2.0

CountyELLIS
Highway IH 45
From SH 34
To FM 879
CSJ 0092-04-070
Proj ID IM 0453(132)
Work Type INSTALL GUIDE SIGNS
 
17.893 376016.55 51875.70 379051.89 99.9
CountyELLIS
Highway IH 45
From FM 1182
To FM 1181
CSJ 0092-05-049
Proj ID STP 2013(530)MM
Work Type TRUCK LANE RESTRICTIONS
 
6.780 63617.45 8563.40 62159.40 99.5
Work Order 07-19-13
Work Began 02-13-04
Work Completed  
Time Computed 01-15-14
Contract Working Days 96
Addl Days Granted 1
Working Days Charged 99
Percent Time Used 102
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0092-05-049
JND CONSTRUCTION CONSULTANTS, LLC(6.36%)
AAA DRILLING FOUNDATION CO., INC.( 11.82%)
BUYERS BARRICADES, INC.(3.11%)
TEAM CONSULTANTS INC.(0.69%)
LAYFIELD CONSTRUCTION, INC (6.36%)
Contract # 04133011
Totals 439634.00 60439.10 441211.29 99.9

CountyNAVARRO
Highway IH 45
From NORTH OF US 287
To ELLIS/NAVARRO COUNTY LINE
CSJ 0092-06-100
Proj ID IM 0453(136)
Work Type INSTALL GUIDE SIGNS
 
30.787 227139.90 23418.00 23418.00 10.3
Work Order 03-03-14
Work Began 07-01-14
Work Completed  
Time Computed 05-02-14
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 23
Contractor(s)
SOUTH RANGER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0092-06-100
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01143224
Totals 227139.90 23418.00 23418.00 10.3

CountyELLIS
Highway LP 561
From IH 45 SOUTH OF TRUMBULL
To IH 45 NORTH OF TRUMBULL
CSJ 0092-11-003
Proj ID STP 2014(350)
Work Type MILL, REP, RESURF
 
0.936 681039.82 18000.00 743421.62 99.9
Work Order 02-14-14
Work Began 04-14-14
Work Completed  
Time Computed 04-14-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 97
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0092-11-003
TOTAL HIGHWAY MAINTENANCE, LLC (0.99%)
GJ SEEDING, LLC(3.22%)
O. TREVINO CONSTRUCTION, LLC ( 31.89%)
DUSTROL, INC.(7.37%)
ALTUS TRAFFIC MANAGEMENT LLC (0.36%)
Contract # 01143022
Totals 681039.82 18000.00 743421.62 99.9

CountyDALLAS
Highway IH 345
From SOUTH OF IH 30, NB AND SB
To US 75 IN CITY OF DALLAS
CSJ 0092-14-083
Proj ID NH 1402(023)
Work Type REPAIR BENT CAPS AND GIRDERS
 
2.434 666025.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 126
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0092-14-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143023
Totals 666025.00 0.00 0.00 0.0

CountyNAVARRO
Highway SH 14
From AT UP RR
To SOUTH OF RICHLAND
CSJ 0093-02-015
Proj ID C 93-2-15
Work Type REPLACE EXISTING RAILROAD UNDERPASS
 
0.862 6571060.16 231694.26 3563065.97 54.2
Work Order 11-13-13
Work Began 12-02-13
Work Completed  
Time Computed 12-02-13
Contract Working Days 378
Addl Days Granted 0
Working Days Charged 142
Percent Time Used 37
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0093-02-015
SAN-ANN-CO., INC.(0.19%)
W.O.E. CONSTRUCTION(0.03%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.06%)
STRIPING TECHNOLOGY, L.P.(0.82%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.20%)
FORTSON CONTRACTING, INC.(0.66%)
NE-TEX CONSTRUCTION, LTD.( 44.04%)
APAC-TEXAS, INC. (7.62%)
TEX OP CONSTRUCTION, LP(0.93%)
MESA ROD BUSTERS, INC. (0.17%)
Contract # 08133246
Totals 6571060.16 231694.26 3563065.97 54.2

CountyDALLAS
Highway SH 183
From E. ABUTMENT OF TRINITY RIVER BRIDGE
To IH 35E
CSJ 0094-07-041
Proj ID NH 2013(651)
Work Type MILL, INLAY, FDRCP, PAV MRKS
 
1.535 2164097.25 383081.02 2211445.49 100.0
Work Order 06-20-13
Work Began 07-22-13
Work Completed 08-08-14
Time Computed 07-06-13
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 102
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0094-07-041
CROSSROADS, L.P. (0.48%)
HALL BROTHERS, INC.( 13.41%)
STRIPING TECHNOLOGY, L.P.(1.34%)
O. TREVINO CONSTRUCTION, LLC ( 11.99%)
BRENDA PRICE TRUCKING(0.14%)
W.O.E. CONSTRUCTION(0.52%)
USA EROSION, INC.(0.12%)
Contract # 04133030
Totals 2164097.25 383081.02 2211445.49 100.0

CountyDALLAS
Highway US 80
From CULVERT 0.3 MI E OF E FORK RD
To .
CSJ 0095-02-109
Proj ID NH 2013(381)
Work Type REPAIR SLOPE WITH HEADWALL
 
0.024 256468.00 12563.05 207450.72 99.9
Work Order 04-10-13
Work Began 06-13-13
Work Completed  
Time Computed 06-09-13
Contract Working Days 50
Addl Days Granted 15
Working Days Charged 210
Percent Time Used 323
Contractor(s)
WEST GENERAL CONTRACTORS CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0095-02-109
DALLAS LITE AND BARRICADE INC. (8.04%)
IOWA BRIDGE & CULVERT, LC( 11.40%)
CONSTRUCTION COMPANIES GROUP, LLC( 38.57%)
FARR FOUNDATION, INC.( 11.96%)
STRAIGHT LINE PAVEMENT MARKINGS(3.76%)
Contract # 02133218
Totals 256468.00 12563.05 207450.72 99.9

CountyDALLAS
Highway US 80 ETC
From TOWN EAST
To IH 635
CSJ 0095-02-113
Proj ID CM 1402(024)
Work Type INSTALLATION OF WIRELESS ITS SYSTEM
 
25.893 1949706.73 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0095-02-113
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143211
Totals 1949706.73 0.00 0.00 0.0

CountyKAUFMAN
Highway US 80
From 0.4 MI WEST OF FM 460
To EAST OF FM 548
CSJ 0095-03-088
Proj ID NH 2014(870)
Work Type BS, CMT TR, FLX BS, STR, HMAC, WDN, MRKS
 
8.162 9634025.22 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 281
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0095-03-088
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143007
Totals 9634025.22 0.00 0.00 0.0

CountyKAUFMAN
Highway US 80
From AT PROPOSED FORNEY PARKWAY
To .
CSJ 0095-04-064
Proj ID C 95-4-64
Work Type GR, STR, DRAINAGE, PVMT, SIGNS
 
1.030 17050215.03 32425.61 19007219.73 99.9
Work Order 03-06-12
Work Began 04-09-12
Work Completed  
Time Computed 03-22-12
Contract Working Days 473
Addl Days Granted 82
Working Days Charged 555
Percent Time Used 100
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0095-04-064
BEAIRD DRILLING(2.99%)
BUYERS BARRICADES, INC.(0.19%)
DUSTROL, INC.(0.14%)
FORTSON CONTRACTING, INC.(0.57%)
PEACHTREE CONSTRUCTION, LTD. (3.69%)
STAR OPERATIONS, INC.(1.93%)
STORM WATER MANAGEMENT, INC. (0.08%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.32%)
SOUTH TEXAS PAINTING COMPANY (1.00%)
CONCRETE CUTTING BY BOND (0.07%)
USA SWPPP INSPECTIONS, INC.(0.66%)
W. W. FOUNDATION DRILLING, LTD.(2.82%)
J.L. STEEL REINFORCING, LLC(1.20%)
COWBOY TRUCKING(0.00%)
CHRISTINE"S CONCERTE SAWING & SEALING LLC(0.06%)
SUNNYVALE FENCE COMPANY(0.10%)
Contract # 01123202
Totals 17050215.03 32425.61 19007219.73 99.9

CountyDALLAS
Highway IH 20
From I.H. 635
To SEAGOVILLE ROAD.
CSJ 0095-13-025
Proj ID IM 0205(146)
Work Type GRADING, PAVING, SIGNING, LANDSCAPING
 
0.841 4972861.19 0.00 4847267.72 97.4
Work Order 06-21-12
Work Began 10-01-12
Work Completed  
Time Computed 10-01-12
Contract Working Days 147
Addl Days Granted 70
Working Days Charged 217
Percent Time Used 100
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0095-13-025
NORTH TEXAS REBAR, LLC (0.68%)
FORTSON CONTRACTING, INC.(1.00%)
INTEGRATED ROADWAY SERVICES, INC.(1.49%)
S & S PAINTING (0.25%)
W.O.E. CONSTRUCTION(0.21%)
AXIS CONTRACTING, INC. (8.00%)
HOUSTON SAWING & DRILLING(0.05%)
USA SWPPP INSPECTIONS, INC.(0.47%)
DUSTROL, INC.(0.54%)
DALLAS LITE AND BARRICADE INC. (0.28%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.23%)
THELIN RECYCLING COMPANY, L.P. (0.24%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(9.28%)
W. W. FOUNDATION DRILLING, LTD.(2.12%)
THE ANCHOR GROUP, INC. (0.78%)
NORTH TEXAS REBAR, LLC (0.09%)
COWBOY TRUCKING(0.40%)
MCALLISTER"S LANDSCAPE MANAGEMENT(3.25%)
S & S BRIDGE PAINTING, INC.(0.25%)
STAR OPERATIONS, INC.(0.24%)
Contract # 05123247
Totals 4972861.19 0.00 4847267.72 97.4

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8