Monthly State Let Construction Report For Dallas District As Of Apr 10, 2015 Page 2 Of 9

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyELLIS
Highway US 77 ETC
From NORTH OF US 287 IN WAXAHACHIE
To SH 342
CSJ 0048-03-084
Proj ID STP 2014(343)HESG
Work Type PROFILE PAVEMENT MARKINGS
 
35.046 569367.05 10.00 405025.42 100.0
Work Order 02-14-14
Work Began 07-07-14
Work Completed 12-29-14
Time Computed 04-15-14
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 115
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0048-03-084
BRYDL CONTRACTING, INC.(2.18%)
BUYERS BARRICADES, INC.(1.41%)
Contract # 01143219
Totals 569367.05 10.00 405025.42 100.0

CountyELLIS
Highway US 77
From AT SH 342
To .
CSJ 0048-03-087
Proj ID NH 2015(390)
Work Type REHABILITATION OF TRAFFIC SIGNALS
 
0.002 268750.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-16-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0048-03-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143212
Totals 268750.00 0.00 0.00 0.0

CountyELLIS
Highway IH 35E
From SOUTH OF BILL LEWIS RD
To SOUTH OF WAXAHACHIE LAKE
CSJ 0048-08-048
Proj ID IM 0356(445)
Work Type REHAB FRTG RD PV
 
7.000 1574118.58 296213.33 1482557.86 94.2
Work Order 03-14-14
Work Began 10-20-14
Work Completed  
Time Computed 05-13-14
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 106
Percent Time Used 100
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0048-08-048
ALTUS TRAFFIC MANAGEMENT LLC (0.53%)
TEX OP CONSTRUCTION, LP(0.27%)
O. TREVINO CONSTRUCTION, LLC (9.38%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(3.36%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.64%)
BRENDA PRICE TRUCKING(0.22%)
W.O.E. CONSTRUCTION(0.63%)
Contract # 01143009
Totals 1574118.58 296213.33 1482557.86 94.2

CountyDENTON
Highway US 377
From AT HICKORY CREEK AND RELIEF
To .
CSJ 0081-03-051
Proj ID BR 2013(177)
Work Type REHAB AND WIDEN BRIDGE AND APPROACH
 
0.739 4078318.50 0.00 4143250.01 99.9
Work Order 10-30-13
Work Began 01-07-14
Work Completed  
Time Computed 12-29-13
Contract Working Days 157
Addl Days Granted 37
Working Days Charged 194
Percent Time Used 100
Contractor(s)
REBCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0081-03-051
ACU CONSTRUCTION LLC (0.42%)
C.T. AND S. METALWORKS, INC. (1.69%)
COWTOWN TRAFFIC CONTROL, INC.(0.18%)
JAGOE-PUBLIC COMPANY (4.76%)
LAYFIELD CONSTRUCTION, INC (2.00%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (2.51%)
S & S BRIDGE PAINTING, INC.( 10.86%)
SOUTHEAST GRINDING & GROOVING, LLC (0.11%)
STRIPING TECHNOLOGY, L.P.(1.08%)
WEST TEXAS REBAR PLACERS INC.(1.34%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.89%)
W.O.E. CONSTRUCTION(0.14%)
BONE CONSTRUCTION SOLUTIONS, LLC (0.74%)
Contract # 08133029
Totals 4078318.50 0.00 4143250.01 99.9

CountyDENTON
Highway US 377
From SOUTH OF BUS 377E
To BUS 377E NORTH OF PILOT POINT
CSJ 0081-06-029
Proj ID C 81-6-29
Work Type REHAB ROADWAY
 
3.702 7501346.55 318173.90 3795084.01 50.5
Work Order 03-07-14
Work Began 05-19-14
Work Completed  
Time Computed 03-23-14
Contract Working Days 264
Addl Days Granted 0
Working Days Charged 226
Percent Time Used 85
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0081-06-029
CRAIG OLDEN, INC.(1.15%)
DUSTROL, INC.(1.24%)
IOWA BRIDGE & CULVERT, LC(3.94%)
K & S UTILITY CONTRACTORS, INC.( 28.85%)
MARCOM"S MOWING SERVICE, LLC (1.70%)
MEL"S ELECTRIC SERVICE, INC. (0.51%)
STORM WATER MANAGEMENT, INC. (0.37%)
STRIPING TECHNOLOGY, L.P.(2.42%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.73%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.56%)
RAMBO CONTRACTING, INC.( 10.99%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.87%)
Contract # 01143003
Totals 7501346.55 318173.90 3795084.01 50.5

CountyDENTON
Highway IH 35W
From DENTON/TARRANT COUNTY LINE
To IH 35
CSJ 0081-13-051
Proj ID NH 2015(348)
Work Type INSTALL GUIDE SIGNS
 
32.304 375630.65 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-09-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIME STRIPING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0081-13-051
BUYERS BARRICADES, INC.(2.52%)
Contract # 11143222
Totals 375630.65 0.00 0.00 0.0

CountyCOLLIN
Highway SH 289
From FM 455
To N BUS 289C, NORTH OF CELINA
CSJ 0091-03-021
Proj ID C 91-3-21
Work Type GRD, STR, PVMT, SIGNS
 
3.448 15996401.11 183912.03 9288861.02 58.0
Work Order 08-22-12
Work Began 02-14-13
Work Completed  
Time Computed 02-14-13
Contract Working Days 520
Addl Days Granted 30
Working Days Charged 350
Percent Time Used 63
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0091-03-021
ALLIANCE GEOTECHNICAL GROUP(0.21%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(0.11%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.14%)
FORTSON CONTRACTING, INC.(0.10%)
HIGHWAY TECHNOLOGIES, INC. (0.93%)
INDUS CONSTRUCTION, L.P. (0.90%)
JAGOE-PUBLIC COMPANY ( 13.49%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.97%)
LONE STAR BARRIER SERVICES, LLC(0.24%)
LONE STAR MANHOLE & STRUCTURES, LLC(4.63%)
TEX OP CONSTRUCTION, LP(0.74%)
MIKE ALBERT, INC.(1.33%)
W.O.E. CONSTRUCTION(0.29%)
EROSION CONTROL MANAGEMENT SERVICES(0.55%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.08%)
STRIPING TECHNOLOGY, L.P.(1.20%)
IRON CONCRETE CONSTRUCTION COMPANY, INC. (2.39%)
TEXAS INLETS, INC. (2.24%)
Contract # 06123003
Totals 15996401.11 183912.03 9288861.02 58.0

CountyCOLLIN
Highway SH 289
From US 380 INTERCHANGE
To NORTH OF FM 1461 / BS 289D
CSJ 0091-04-050
Proj ID C 91-4-50
Work Type GRD, STR, PVMT, SIGNS, RAMPS
 
3.144 17270901.44 176093.20 17292374.82 100.0
Work Order 10-13-11
Work Began 03-23-12
Work Completed 03-26-15
Time Computed 03-23-12
Contract Working Days 619
Addl Days Granted 81
Working Days Charged 708
Percent Time Used 101
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0091-04-050
ALLIANCE GEOTECHNICAL GROUP(0.20%)
ARLINGTON PAVERS, INC. (0.03%)
CONCRETE CUTTING BY BOND (0.36%)
DUSTROL, INC.(0.64%)
HIGHWAY TECHNOLOGIES, INC. (1.44%)
INDUS CONSTRUCTION, L.P. (1.13%)
MIKE ALBERT, INC.(1.20%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 14.69%)
ROADWAY SOLUTIONS, INC.(4.41%)
TEXAS INLETS, INC. (4.43%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.10%)
STORM WATER MANAGEMENT, INC. (0.45%)
SKAGGS ROAD BORING INC.(0.12%)
SYNERGY SIGNS & SERVICES, LLC(0.15%)
ANCHOR FENCE GROUP, LLC(0.08%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.06%)
STRIPING TECHNOLOGY, L.P.(0.96%)
JET UNDERGROUND UTILITIES, INC.(0.19%)
NORTH TEXAS BOMANITE, INC. (0.59%)
W.O.E. CONSTRUCTION(0.08%)
Contract # 07113202
Totals 17270901.44 176093.20 17292374.82 100.0

CountyCOLLIN
Highway SH 289
From NORTH OF FM 1461 / BS 289D
To FM 455 IN CELINA
CSJ 0091-04-055
Proj ID C 91-4-55
Work Type GR, STR, PVMT, SIGNS, PVMT MKGS
 
4.090 18214018.09 23557.29 17498190.44 96.5
Work Order 10-18-11
Work Began 06-22-12
Work Completed  
Time Computed 04-15-12
Contract Working Days 519
Addl Days Granted 199
Working Days Charged 779
Percent Time Used 108
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0091-04-055
ALLIANCE GEOTECHNICAL GROUP(0.18%)
ARLINGTON PAVERS, INC. (0.02%)
CONCRETE CUTTING BY BOND (0.32%)
DUSTROL, INC.(0.73%)
FORTSON CONTRACTING, INC.(0.15%)
HIGHWAY TECHNOLOGIES, INC. (0.88%)
INDUS CONSTRUCTION, L.P. (0.90%)
LONE STAR MANHOLE & STRUCTURES, LLC(6.25%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 15.14%)
STORM WATER MANAGEMENT, INC. (0.29%)
ROADWAY SOLUTIONS, INC.(1.97%)
FARR FOUNDATION, INC.(0.02%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.73%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.07%)
STRIPING TECHNOLOGY, L.P.(0.88%)
MIKE ALBERT, INC.(0.36%)
SYNERGY SIGNS & SERVICES, LLC(0.10%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.17%)
EROSION CONTROL MANAGEMENT SERVICES(0.02%)
IRON CONCRETE CONSTRUCTION COMPANY, INC. (0.60%)
JET UNDERGROUND UTILITIES, INC.(0.18%)
Contract # 07113203
Totals 18214018.09 23557.29 17498190.44 96.5

CountyCOLLIN
Highway SH 289
From PANTHER CREEK
To SOUTH OF US 380
CSJ 0091-04-058
Proj ID STP 2014(569)
Work Type LANDSCAPE DEVELOPMENT
 
4.457 376485.00 6858.00 368869.74 97.9
Work Order 04-15-14
Work Began 10-14-14
Work Completed  
Time Computed 05-01-14
Contract Working Days 53
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 66
Contractor(s)
LANDSCAPE CONTRACTING AND IRRIGATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0091-04-058
MCBRIDE ELECTRIC, INC. (0.42%)
AQUA BORE(3.71%)
ALTUS TRAFFIC MANAGEMENT LLC (0.86%)
Contract # 03143034
Totals 376485.00 6858.00 368869.74 97.9

CountyCOLLIN
Highway SH 289
From NORTH OF US 380
To FM 455
CSJ 0091-04-059
Proj ID STP 2014(761)
Work Type LANDSCAPE DEVELOPMENT
 
7.234 649411.81 81474.86 386929.05 59.5
Work Order 07-29-14
Work Began 10-07-14
Work Completed  
Time Computed 08-14-14
Contract Working Days 139
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 22
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0091-04-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143012
Totals 649411.81 81474.86 386929.05 59.5

CountyDALLAS
Highway SH 289
From ON SH 289 (PRESTON)
To AT ROYAL
CSJ 0091-06-049
Proj ID STP 2013(727)MM
Work Type INTERSECTION IMPROVEMENT
 
0.166 674540.86 101906.90 524688.35 77.7
CountyDALLAS
Highway SH 289
From ON SH 289
To AT ROYAL LANE
CSJ 0091-06-055
Proj ID STP 2012(375)MM
Work Type ROW ACQ & UTIL ADJ
 
0.010 44707.50 449.96 10705.56 23.9
Work Order 07-31-13
Work Began 10-15-14
Work Completed  
Time Computed 09-29-13
Contract Working Days 118
Addl Days Granted 0
Working Days Charged 108
Percent Time Used 91
Contractor(s)
REBCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0091-06-049
DURABLE SPECIALTIES, INC.( 15.16%)
M & M STRIPING & POWER WASHING, LLC(3.23%)
NORTH TEXAS CONTRACTING, INC.( 11.02%)
PREMIER PAVING, LTD. (3.55%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.76%)
W.O.E. CONSTRUCTION(1.33%)
CHRISTINE"S CONCERTE SAWING & SEALING LLC(0.97%)
Contract # 05133228
Totals 719248.36 102356.86 535393.91 74.4

CountyDALLAS
Highway SH 289
From LOOP 12
To ELDERWOOD DRIVE
CSJ 0091-06-058
Proj ID NH 2015(839)
Work Type MILL, CONC REPAIR & OVERLAY
 
2.397 2360163.24 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SILVER CREEK CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0091-06-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153212
Totals 2360163.24 0.00 0.00 0.0

CountyNAVARRO
Highway IH 45
From NORTH OF US 287
To ELLIS/NAVARRO COUNTY LINE
CSJ 0092-06-100
Proj ID IM 0453(136)
Work Type INSTALL GUIDE SIGNS
 
30.787 227139.90 0.00 226669.28 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-03-14
Work Began 07-01-14
Work Completed 02-12-15
Time Computed 05-02-14
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 77
Percent Time Used 113
Contractor(s)
SOUTH RANGER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0092-06-100
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01143224
Totals 227139.90 0.00 226669.28 100.0

CountyDALLAS
Highway IH 345
From SOUTH OF IH 30, NB AND SB
To US 75 IN CITY OF DALLAS
CSJ 0092-14-083
Proj ID NH 1402(023)
Work Type REPAIR BENT CAPS AND GIRDERS
 
2.434 666025.00 7500.00 719897.28 99.9
Work Order 09-22-14
Work Began 12-08-14
Work Completed  
Time Computed 10-08-14
Contract Working Days 126
Addl Days Granted 0
Working Days Charged 69
Percent Time Used 54
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0092-14-083
TOTAL HIGHWAY MAINTENANCE, LLC (3.23%)
BROCK ENVIRONMENTAL, LLC (0.06%)
Contract # 08143023
Totals 666025.00 7500.00 719897.28 99.9

CountyNAVARRO
Highway SH 14
From AT UP RR
To SOUTH OF RICHLAND
CSJ 0093-02-015
Proj ID C 93-2-15
Work Type REPLACE EXISTING RAILROAD UNDERPASS
 
0.862 6571060.16 750.00 4626938.80 70.4
Work Order 11-13-13
Work Began 12-02-13
Work Completed  
Time Computed 12-02-13
Contract Working Days 378
Addl Days Granted 0
Working Days Charged 307
Percent Time Used 81
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0093-02-015
SAN-ANN-CO., INC.(0.19%)
W.O.E. CONSTRUCTION(0.03%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.06%)
STRIPING TECHNOLOGY, L.P.(0.82%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.20%)
FORTSON CONTRACTING, INC.(0.66%)
NE-TEX CONSTRUCTION, LTD.( 44.04%)
APAC-TEXAS, INC. (7.62%)
TEX OP CONSTRUCTION, LP(0.93%)
MESA ROD BUSTERS, INC. (0.17%)
Contract # 08133246
Totals 6571060.16 750.00 4626938.80 70.4

CountyDALLAS
Highway US 80
From CULVERT 0.3 MI E OF E FORK RD
To .
CSJ 0095-02-109
Proj ID NH 2013(381)
Work Type REPAIR SLOPE WITH HEADWALL
 
0.024 256468.00 0.00 208791.72 99.9
Work Order 04-10-13
Work Began 06-13-13
Work Completed  
Time Computed 06-09-13
Contract Working Days 50
Addl Days Granted 15
Working Days Charged 210
Percent Time Used 323
Contractor(s)
WEST GENERAL CONTRACTORS CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0095-02-109
DALLAS LITE AND BARRICADE INC. (8.04%)
IOWA BRIDGE & CULVERT, LC( 11.40%)
CONSTRUCTION COMPANIES GROUP, LLC( 38.57%)
FARR FOUNDATION, INC.( 11.96%)
STRAIGHT LINE PAVEMENT MARKINGS(3.76%)
Contract # 02133218
Totals 256468.00 0.00 208791.72 99.9

CountyDALLAS
Highway US 80 ETC
From TOWN EAST
To IH 635
CSJ 0095-02-113
Proj ID CM 1402(024)
Work Type INSTALLATION OF WIRELESS ITS SYSTEM
 
25.893 1949706.73 332251.38 499563.38 25.6
Work Order 11-04-14
Work Began 00-00-00
Work Completed  
Time Computed 03-04-15
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 1
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0095-02-113
ODUM SERVICES, L.P.(6.10%)
PEAK COMMUNICATIONS LLC(1.32%)
BIG DOG DRILLING, LLC(0.71%)
Contract # 08143211
Totals 1949706.73 332251.38 499563.38 25.6

CountyDALLAS
Highway US 80
From EAST OF TOWN EAST BLVD
To KAUFMAN COUNTY LINE
CSJ 0095-02-114
Proj ID STP 2015(840)HES
Work Type INSTALL PROTECTION
 
23.645 936969.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 127
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ODUM SERVICES, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0095-02-114
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153033
Totals 936969.50 0.00 0.00 0.0

CountyKAUFMAN
Highway US 80
From 0.4 MI WEST OF FM 460
To EAST OF FM 548
CSJ 0095-03-088
Proj ID NH 2014(870)
Work Type BS, CMT TR, FLX BS, STR, HMAC, WDN, MRKS
 
8.162 9634025.22 254101.67 3089080.67 32.0
Work Order 09-30-14
Work Began 01-14-15
Work Completed  
Time Computed 11-29-14
Contract Working Days 281
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 21
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0095-03-088
VIKING CONSTRUCTION, INC.(0.55%)
SAMMY G. SMALLWOOD (0.83%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.16%)
STRIPING TECHNOLOGY, L.P.(0.76%)
O. TREVINO CONSTRUCTION, LLC (0.86%)
CROSSROADS, L.P. (0.00%)
FORTSON CONTRACTING, INC.(1.86%)
CLLA GROUP, LLC(1.84%)
HIGHWAY 19 CONSTRUCTION, LLC (4.20%)
DUSTROL, INC.(4.75%)
W.O.E. CONSTRUCTION(0.01%)
Contract # 07143007
Totals 9634025.22 254101.67 3089080.67 32.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9