Monthly State Let Construction Report For Dallas District As Of Sep 15, 2016 Page 2 Of 8

Last Update: Thursday, September 15, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyELLIS
Highway IH 35E
From 2 MILES SOUTH OF FM 566 (HILL C/L)
To US 77 SOUTH OF WAXAHACHIE
CSJ 0048-08-049
Proj ID NH 2016(091)
Work Type CONC, PAV MRKS
 
18.481 35775602.93 1016718.28 8643645.90 24.1
Work Order 12-15-15
Work Began 02-01-16
Work Completed  
Time Computed 02-01-16
Contract Working Days 453
Addl Days Granted 0
Working Days Charged 145
Percent Time Used 32
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0048-08-049
ALTUS TRAFFIC MANAGEMENT LLC (0.06%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(3.17%)
PREMIER PAVING, LTD. ( 14.36%)
TEXOP CONSTRUCTION (1.55%)
AVANZA CONSTRUCTION & EARTHWORKS, LLC(1.89%)
INTEGRATED ROADWAY SERVICES, INC.( 12.47%)
BREDA COMPANY, INC.(5.14%)
ANCORTEX, INC. (0.43%)
STRIPING TECHNOLOGY, L.P.(1.81%)
UNDER CONSTRUCTION INC.(0.17%)
P G SERVICES (0.00%)
DBI SERVICES, LLC(0.00%)
Contract # 09153002
Totals 35775602.93 1016718.28 8643645.90 24.1

CountyDENTON
Highway US 377
From HENRIETTA CREEK RD IN ROANOAKE
To CRAWFORD RD IN ARGYLE
CSJ 0081-03-058
Proj ID STP 2016(982)HES
Work Type IMPROVE TRAFFIC SIGNALS
 
9.053 258524.00 0.00 0.00 0.0
CountyDALLAS
Highway US 67
From ELLIS COUNTY LINE
To BELTLINE RD
CSJ 0261-02-076
Proj ID STP 2016(981)HES
Work Type INSTALL SAFETY LIGHTING
 
3.430 821532.11 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 137
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0261-02-076
BUYERS BARRICADES, INC.(1.98%)
DYNAMIC VISION CO., INC. (0.24%)
USA SWPPP INSPECTIONS, INC.(1.41%)
KLP COMMERCIAL, LLC(0.72%)
Contract # 04163213
Totals 1080056.11 0.00 0.00 0.0

CountyDENTON
Highway US 377
From IH 35E
To W COLLINS STREET
CSJ 0081-04-040
Proj ID STP 1502(484)
Work Type LANDSCAPE DEVELOPMENT
 
3.013 323544.00 4000.00 282110.16 87.1
Work Order 08-24-15
Work Began 10-19-15
Work Completed  
Time Computed 10-19-15
Contract Working Days 95
Addl Days Granted 0
Working Days Charged 95
Percent Time Used 100
Contractor(s)
CARRUTH NURSERY IRRIGATION & LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0081-04-040
TOTAL HIGHWAY MAINTENANCE, LLC (1.35%)
TEXAS CABLE & BORING (0.82%)
Contract # 07153218
Totals 323544.00 4000.00 282110.16 87.1

CountyDENTON
Highway US 377 ETC
From AT FM 428 / SPRING HILL RD
To IN AUBREY
CSJ 0081-06-037
Proj ID STP 1502(084)HES
Work Type TRAFFIC SIGNAL IMPROVEMENTS
 
7.644 950000.00 9730.00 733680.58 77.2
Work Order 07-07-15
Work Began 10-08-15
Work Completed  
Time Computed 10-06-15
Contract Working Days 188
Addl Days Granted 0
Working Days Charged 147
Percent Time Used 78
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0081-06-037
DYNAMIC VISION CO., INC. (7.43%)
Contract # 05153218
Totals 950000.00 9730.00 733680.58 77.2

CountyDENTON
Highway IH 35W
From EAGLE PARKWAY
To SH 114
CSJ 0081-13-041
Proj ID STP 2016(093)MM
Work Type GR, STRS, CONC PAV
 
2.040 15427421.65 727705.40 7016853.83 45.4
Work Order 00-00-00
Work Began 02-01-16
Work Completed  
Time Computed 02-01-16
Contract Working Days 486
Addl Days Granted 0
Working Days Charged 165
Percent Time Used 33
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0081-13-041
OSCAR ORDUNO, INC. (1.03%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.71%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.94%)
MICA CORPORATION (0.94%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(8.31%)
W.O.E. CONSTRUCTION(0.19%)
TEXAS SHAFTS, INC. (0.78%)
ANTIGO CONSTRUCTION, INC.(0.10%)
TEXOP CONSTRUCTION (0.44%)
IRON CONCRETE CONSTRUCTION COMPANY, INC. (0.60%)
RG PAINTING(0.13%)
BRJ PAVING INCORPORATION (1.26%)
BREDA COMPANY, INC.(4.05%)
J.C. TRUCKING(0.11%)
LUZ TRUCKING, INC. (0.26%)
ORTIZ TRUCKING (EFERN) (0.11%)
MARCO A. TRUCKING(0.16%)
TX TINMAN ENTERPRISES, LLC.(0.30%)
Contract # 09153203
Totals 15427421.65 727705.40 7016853.83 45.4

CountyCOLLIN
Highway SH 289
From PGBT
To SH 121
CSJ 0091-05-073
Proj ID NH 1602(420)
Work Type LANDSCAPE ENHANCEMENT
 
5.950 474267.76 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 156
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0091-05-073
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163215
Totals 474267.76 0.00 0.00 0.0

CountyDALLAS
Highway SH 310
From IH 20
To 0.91 MI S OF SL 12
CSJ 0092-02-122
Proj ID STP 1602(159)HES
Work Type IMPROVE GUARDRAIL
 
2.162 564485.75 0.00 0.00 0.0
CountyDALLAS
Highway US 175
From MALLOY BRIDGE ROAD
To KAUFMAN COUNTY LINE
CSJ 0197-02-119
Proj ID NH 1602(160)
Work Type EARTHWORK, HMAC, FOUNDATION, & CTB
 
0.742 600671.00 0.00 0.00 0.0
CountyDALLAS
Highway FM 1382
From WEST OF S HAMPTON ROAD
To EAST OF S PARKS DRIVE
CSJ 1047-02-048
Proj ID NH 1602(160)
Work Type MILL & OVERLAY
 
0.898 155164.35 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-08-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 62
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0092-02-122
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163021
Totals 1320321.10 0.00 0.00 0.0

CountyDALLAS
Highway SH 310
From AT TRINITY RIVER
To .
CSJ 0092-02-123
Proj ID BR 1502(088)
Work Type BRIDGE MAINTENANCE
 
0.516 2145801.00 0.00 2072578.23 96.5
Work Order 06-16-15
Work Began 07-27-15
Work Completed  
Time Computed 09-15-15
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 138
Percent Time Used 55
Contractor(s)
CEKRA INC.
SUBCONTRACTOR(S) FOR CCSJ: 0092-02-123
SCR CONSTRUCTION CO., INC. ( 16.93%)
WOLFE CONSTRUCTION GROUP, INC. (0.99%)
Contract # 05153016
Totals 2145801.00 0.00 2072578.23 96.5

CountyELLIS
Highway IH 45
From BRUSHY CREEK
To DALLAS COUNTY LINE
CSJ 0092-03-049
Proj ID CM 1602(105)
Work Type INSTALLATION OF WIRELESS ITS
 
23.422 1185768.45 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-22-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0092-03-049
INTERSTATE BARRICADES & MARKINGS, INC. (1.61%)
INTEGRATED ROADWAY SERVICES, INC.( 24.37%)
Contract # 05163215
Totals 1185768.45 0.00 0.00 0.0

CountyNAVARRO
Highway IH 45
From NORTH OF BUS 287
To I-45 BUSINESS NORTH IN CORSICANA
CSJ 0092-06-101
Proj ID NH 1502(485)
Work Type GR; STR; PVMT; PVMT MKGS
 
24.743 58762184.65 636120.45 9495477.22 16.1
Work Order 03-18-16
Work Began 04-12-16
Work Completed  
Time Computed 04-12-16
Contract Working Days 772
Addl Days Granted 7
Working Days Charged 96
Percent Time Used 12
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0092-06-101
ACU CONSTRUCTION LLC (1.24%)
BREDA COMPANY, INC.(4.42%)
O. TREVINO CONSTRUCTION, LLC (0.29%)
TX TINMAN ENTERPRISES, LLC.(1.37%)
ANCORTEX, INC. (1.32%)
CB SERVICES, INC.(0.43%)
DIAMOND SURFACE, INC.(0.04%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.04%)
BIG CREEK CONSTRUCTION, LTD. ( 11.91%)
STRIPING TECHNOLOGY, L.P.(1.09%)
STRIPING SYSTEMS, INC. (0.00%)
GIBSON & ASSOCIATES, INC.(0.97%)
HYDRO TECHNOLOGIES, INC. (0.11%)
LINDAMOOD DEMOLITION, INC. (0.15%)
MICA CORPORATION (2.46%)
DALLAS LITE AND BARRICADE INC. (0.20%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.65%)
SCOTT DERR PAINTING CO, LLC(0.21%)
UNDER CONSTRUCTION INC.(0.69%)
MID-AMERICA MILLING CO., LLC (0.05%)
MCL CONTRACTING, LLC (0.08%)
Contract # 07153202
Totals 58762184.65 636120.45 9495477.22 16.1

CountyDALLAS
Highway IH 345
From IH 30 - NORTHBOUND & SOUTHBOUND
To SP 366 OVER IH 30, US 75, & DART RR
CSJ 0092-14-080
Proj ID NH 2016(094)
Work Type REHABILITATE BRIDGE
 
2.800 30450159.00 930279.35 7899296.70 25.9
Work Order 12-01-15
Work Began 02-01-16
Work Completed  
Time Computed 02-01-16
Contract Working Days 504
Addl Days Granted 0
Working Days Charged 159
Percent Time Used 31
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0092-14-080
ALLIANCE GEOTECHNICAL GROUP(3.00%)
SCR CONSTRUCTION CO., INC. ( 47.66%)
BUYERS BARRICADES, INC.(0.15%)
BKH INSPECTION SERVICES, LLC (0.12%)
STEEL INSPECTORS OF TEXAS, INC.(2.87%)
WELDCO INDUSTRIAL, INC.( 21.17%)
Contract # 09153201
Totals 30450159.00 930279.35 7899296.70 25.9

CountyNAVARRO
Highway IH 45
From SOUTH OF SH 14
To 2.1 MILES SOUTH OF BI 45F
CSJ 0093-01-098
Proj ID NH 1502(486)
Work Type GR; STR; PVMT; PVMT MKGS
 
28.820 71994840.25 2209728.11 30306503.87 42.0
Work Order 10-05-15
Work Began 10-28-15
Work Completed  
Time Computed 10-28-15
Contract Working Days 776
Addl Days Granted 0
Working Days Charged 208
Percent Time Used 26
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0093-01-098
STRIPING TECHNOLOGY, L.P.(1.06%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.38%)
W. W. FOUNDATION DRILLING, LTD.(0.64%)
RAMA ENTERPRISES, LLC(0.52%)
LINDAMOOD DEMOLITION, INC. (0.10%)
BIG CREEK CONSTRUCTION, LTD. (9.95%)
LAYFIELD CONSTRUCTION, INC (0.18%)
RENAISSANCE CONTRACTORS, INC.(2.61%)
BUYERS BARRICADES, INC.(0.22%)
ACU CONSTRUCTION LLC (0.49%)
STRAIGHT LINE SAWING & SEALING (0.49%)
BREDA COMPANY, INC.(3.94%)
A R DANIEL CONSTRUCTION SERVICES, INC. (0.28%)
TEX OP CONSTRUCTION, LP(0.83%)
MICA CORPORATION (1.11%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(0.08%)
W.O.E. CONSTRUCTION(0.47%)
URBAN INFRACONSTRUCTION, LLC.(0.13%)
Contract # 07153001
Totals 71994840.25 2209728.11 30306503.87 42.0

CountyNAVARRO
Highway SH 14
From AT UP RR
To SOUTH OF RICHLAND
CSJ 0093-02-015
Proj ID C 93-2-15
Work Type REPLACE EXISTING RAILROAD UNDERPASS
 
0.862 6571060.16 160980.46 6001114.20 96.4
Work Order 11-13-13
Work Began 12-02-13
Work Completed  
Time Computed 12-02-13
Contract Working Days 378
Addl Days Granted 13
Working Days Charged 690
Percent Time Used 176
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0093-02-015
SAN-ANN-CO., INC.(0.19%)
W.O.E. CONSTRUCTION(0.03%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.06%)
STRIPING TECHNOLOGY, L.P.(0.82%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.20%)
FORTSON CONTRACTING, INC.(0.66%)
NE-TEX CONSTRUCTION, LTD.( 44.04%)
APAC-TEXAS, INC. (7.62%)
TEX OP CONSTRUCTION, LP(0.93%)
MESA ROD BUSTERS, INC. (0.17%)
Contract # 08133246
Totals 6571060.16 160980.46 6001114.20 96.4

CountyDALLAS
Highway SS 482
From SH 114
To SPUR RD
CSJ 0094-03-118
Proj ID STP 2016(976)
Work Type FDCR, MBGR
 
0.831 414730.00 0.00 0.00 0.0
CountyDALLAS
Highway SL 12
From SHADY BROOK LANE
To ABRAMS AVE
CSJ 0353-05-116
Proj ID STP 2016(975)HES
Work Type INSTALL RAISED MEDIAN
 
1.017 739940.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-20-16
Work Began 09-12-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0094-03-118
ROCK SOLID, INC. (9.62%)
STRIPING TECHNOLOGY, L.P.(0.64%)
W.O.E. CONSTRUCTION(2.66%)
CROSS ROADS, L.P.(0.92%)
FORTSON CONTRACTING, INC.(1.17%)
BROCK ENVIRONMENTAL SERVICES, LLC(0.26%)
STRIPING SYSTEMS, INC. (0.07%)
O. TREVINO CONSTRUCTION, LLC ( 11.75%)
STRAIGHT LINE SAWING & SEALING (0.40%)
BRENDA PRICE TRUCKING(0.41%)
Contract # 04163010
Totals 1154670.50 0.00 0.00 0.0

CountyDALLAS
Highway US 80
From IH 635
To NORTH GALLOWAY AVENUE
CSJ 0095-02-102
Proj ID STP 1602(324)MM
Work Type RELOCATE OFF RAMP; SIGNS
 
1.601 10441947.51 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 335
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0095-02-102
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163226
Totals 10441947.51 0.00 0.00 0.0

CountyDALLAS
Highway US 80 ETC
From TOWN EAST
To IH 635
CSJ 0095-02-113
Proj ID CM 1402(024)
Work Type INSTALLATION OF WIRELESS ITS SYSTEM
 
25.893 1949706.73 70509.32 1861104.70 98.6
Work Order 11-04-14
Work Began 05-01-15
Work Completed  
Time Computed 03-04-15
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 239
Percent Time Used 149
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0095-02-113
ODUM SERVICES, L.P.(6.10%)
PEAK COMMUNICATIONS LLC(1.32%)
BIG DOG DRILLING, LLC(0.71%)
DOUBLE S CONSTRUCTION(1.71%)
ALTUS TRAFFIC MANAGEMENT LLC (0.62%)
UNION ELECTRICAL CONTRACTOR, INC.(2.17%)
DALLAS LITE AND BARRICADE INC. (0.94%)
C & B COMMUNICATIONS, INC. (1.56%)
Contract # 08143211
Totals 1949706.73 70509.32 1861104.70 98.6

CountyDALLAS
Highway US 80
From WEST OF GROSS RD
To EAST OF GROSS RD
CSJ 0095-02-119
Proj ID NH 2016(827)
Work Type GR, PVMT, ACP, BASE
 
0.852 3008042.49 422085.82 853683.40 28.3
Work Order 05-18-16
Work Began 07-19-16
Work Completed  
Time Computed 07-05-16
Contract Working Days 124
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 37
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0095-02-119
CROSS ROADS, L.P.(0.48%)
DUSTROL, INC.(8.61%)
FORTSON CONTRACTING, INC.(0.55%)
IOWA BRIDGE & CULVERT, LC( 22.64%)
ROADWAY SOLUTIONS, INC.(4.20%)
STRIPING TECHNOLOGY, L.P.(1.56%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.31%)
STRIPING SYSTEMS, INC. (0.02%)
BUYERS BARRICADES, INC.(0.29%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.05%)
Contract # 03163009
Totals 3008042.49 422085.82 853683.40 28.3

CountyKAUFMAN
Highway US 80
From FM 460
To FM 740
CSJ 0095-03-087
Proj ID NH 1602(162)
Work Type RELOC EX & ENTRANCE RAMPS
 
1.553 5049368.48 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-23-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 279
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0095-03-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163022
Totals 5049368.48 0.00 0.00 0.0

CountyKAUFMAN
Highway US 80
From 0.4 MI WEST OF FM 460
To EAST OF FM 548
CSJ 0095-03-088
Proj ID NH 2014(870)
Work Type BS, CMT TR, FLX BS, STR, HMAC, WDN, MRKS
 
8.162 9634025.22 362266.64 8820041.41 91.5
Work Order 09-30-14
Work Began 01-14-15
Work Completed  
Time Computed 11-29-14
Contract Working Days 281
Addl Days Granted 3
Working Days Charged 287
Percent Time Used 101
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0095-03-088
VIKING CONSTRUCTION, INC.(0.55%)
SAMMY G. SMALLWOOD (0.83%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.16%)
STRIPING TECHNOLOGY, L.P.(0.76%)
O. TREVINO CONSTRUCTION, LLC (0.86%)
CROSSROADS, L.P. (0.00%)
FORTSON CONTRACTING, INC.(1.86%)
CLLA GROUP, LLC(1.84%)
HIGHWAY 19 CONSTRUCTION, LLC (4.20%)
DUSTROL, INC.(4.75%)
W.O.E. CONSTRUCTION(0.01%)
FARR FOUNDATION, INC.(0.40%)
Contract # 07143007
Totals 9634025.22 362266.64 8820041.41 91.5

CountyNAVARRO
Highway SH 22 ETC
From AT CURVE IN BLOOMING GROVE
To .
CSJ 0121-04-026
Proj ID STP 2016(977)HES
Work Type HIGH FRICTION SURFACE TREATMENT
 
37.110 6426065.65 1016429.59 2599504.65 40.4
Work Order 05-18-16
Work Began 06-20-16
Work Completed  
Time Computed 06-17-16
Contract Working Days 115
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 44
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0121-04-026
N-LINE TRAFFIC MAINTENANCE, L.P. (0.57%)
TOTAL HIGHWAY MAINTENANCE, LLC ( 14.63%)
DIAMOND SURFACE, INC.(0.12%)
Contract # 04163013
Totals 6426065.65 1016429.59 2599504.65 40.4