Monthly State Let Construction Report For Dallas District As Of Apr 10, 2015 Page 5 Of 9

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDALLAS
Highway SS 348
From SH 114
To LOOP 12
CSJ 0353-04-098
Proj ID NH 2015(845)
Work Type FDR - CP
 
5.291 679176.65 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 63
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0353-04-098
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153010
Totals 679176.65 0.00 0.00 0.0

CountyDALLAS
Highway LP 12
From W. LAWTHER DRIVE
To EAST OF GOFORTH DRIVE
CSJ 0353-05-084
Proj ID NH 2008(361)
Work Type GRADING, STRS, ACP, SIGNING, PAVT M
 
0.785 28349251.84 0.00 30594902.99 100.0
CountyDALLAS
Highway LP 12
From W. LAWTHER DRIVE
To EAST OF GOFORTH DRIVE
CSJ 0353-05-110
Proj ID RW 353-5-110
Work Type ROW UTL. ADJ. IN CONSTRUCTION
 
0.785 3131109.30 0.00 3095232.21 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-22-08
Work Began 11-17-08
Work Completed 01-07-15
Time Computed 01-20-09
Contract Working Days 533
Addl Days Granted 85
Working Days Charged 618
Percent Time Used 100
Contractor(s)
REBCON, INC.
CONCHO CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0353-05-084
ARK CONTRACTING SERVICES, LLC(1.88%)
AUSTIN BRIDGE & ROAD, LP (1.88%)
FORTSON CONTRACTING, INC.(0.60%)
TEXAS SHAFTS, INC. (5.55%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.12%)
COWTOWN TRAFFIC CONTROL, INC.(0.00%)
DGI-MENARD, INC. (0.55%)
DUSTROL, INC. (ROANOKE)(0.38%)
MIKE ALBERT, INC.( 10.64%)
SOUTHWEST CONSTRUCTION SERVICES(0.05%)
WEIR BROS., INC. (5.05%)
ENVIRONMENTAL STANDARDS(1.85%)
STAR OPERATIONS, INC.(2.94%)
RG PAINTING(0.22%)
J.R. DAVIS AND ASSOCIATES, INC.(1.86%)
WEST TEXAS REBAR PLACERS INC.(0.00%)
EAGLE AGGREGATE TRANSPORTATION, LLC. (0.00%)
SALDANA'S TRUCKING COMPANY, INC. (0.22%)
CONCRETE CUTTING BY BOND (0.04%)
HOUSTON SAWING & DRILLING(0.07%)
TEXAS INLETS, INC. (0.29%)
SKAGGS ROAD BORING INC.(0.12%)
J.L. STEEL REINFORCING, LLC(0.17%)
Contract # 08083217
Totals 31480361.14 0.00 33690135.20 100.0

CountyDALLAS
Highway SL 12
From WEST OF MIDWAY
To US 75
CSJ 0353-05-088
Proj ID CM 1402(026)
Work Type INTERSECTION IMPROVEMENT
 
3.939 6564020.36 762399.40 866917.25 13.2
CountyDALLAS
Highway SL 12
From WEST OF MIDWAY
To US 75
CSJ 0353-05-107
Proj ID CM 2005(517)
Work Type ACQUISITION, UTILITIES AND RELOCATI
 
3.940 1087941.00 0.00 0.00 0.0
Work Order 11-19-14
Work Began 02-19-15
Work Completed  
Time Computed 02-19-15
Contract Working Days 457
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 5
Contractor(s)
REBCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0353-05-088
DURABLE SPECIALTIES, INC.( 16.58%)
BUYERS BARRICADES, INC.(1.31%)
INLET STRUCTURE SPECIALTIES LTD. (0.64%)
PREMIER PAVING, LTD. (3.01%)
W.O.E. CONSTRUCTION(0.08%)
USA SWPPP INSPECTIONS, INC.(1.16%)
NORTH TEXAS CONTRACTING, INC.( 14.83%)
STRIPING TECHNOLOGY, L.P.(1.00%)
TED ALVAREZ TRUCKING (1.64%)
Contract # 08143219
Totals 7651961.36 762399.40 866917.25 11.3

CountyDALLAS
Highway SH 121
From TARRANT/DALLAS COUNTY LINE
To BUSINESS 121H
CSJ 0364-02-017
Proj ID NH 2013(829)
Work Type GRADING, STRUCTURES AND SURFACE
 
2.567 58805233.66 1138104.18 25362696.01 43.1
Work Order 09-04-13
Work Began 03-04-14
Work Completed  
Time Computed 03-03-14
Contract Working Days 986
Addl Days Granted 1
Working Days Charged 309
Percent Time Used 31
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0364-02-017
ALTUS TRAFFIC MANAGEMENT LLC (0.12%)
USA SWPPP INSPECTIONS, INC.(1.33%)
FOWLER UNLIMITED, LLC(0.05%)
RAMBO CONTRACTING, INC.(1.72%)
RDI FOUNDATION DRILLING(1.93%)
VALLEY PLACERS, LLC(0.15%)
FORTSON CONTRACTING, INC.(0.32%)
HOUSTON SAWING & DRILLING(0.03%)
BORTUNCO (0.83%)
AUSTIN BRIDGE & ROAD, LP ( 12.65%)
TEX OP CONSTRUCTION, LP(0.61%)
RONE ENGINEERING SERVICES, LTD (0.07%)
SCOTT DERR PAINTING CO (0.15%)
W.O.E. CONSTRUCTION(3.18%)
STRIPING TECHNOLOGY, L.P.(0.89%)
MCL CONTRACTING, LLC (7.51%)
SOUTH TEXAS ILLUMINATION, LLC(3.83%)
LABOR READY CENTRAL III L.P. (0.00%)
Contract # 07133002
Totals 58805233.66 1138104.18 25362696.01 43.1

CountyDALLAS
Highway IH 35E
From ELLIS/DALLAS CL
To 8TH STREET
CSJ 0442-02-156
Proj ID IM 0356(446)
Work Type INSTALLATION OF SIGNS
 
18.212 328568.40 3851.98 284661.39 86.6
Work Order 06-02-14
Work Began 12-17-14
Work Completed  
Time Computed 11-29-14
Contract Working Days 56
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 66
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0442-02-156
ALTUS TRAFFIC MANAGEMENT LLC (2.53%)
FORTSON CONTRACTING, INC.( 11.80%)
Contract # 04143226
Totals 328568.40 3851.98 284661.39 86.6

CountyROCKWALL
Highway SH 205
From SOUTH OF WEST HEATH ST
To JOHN KING BLVD
CSJ 0451-04-020
Proj ID STP 2014(871)
Work Type MILL, REPAIR, OL, STR, MRKS, SIGNS
 
3.113 1740711.54 37876.10 1574396.23 100.0
Work Order 08-20-14
Work Began 09-23-14
Work Completed 04-01-15
Time Computed 09-05-14
Contract Working Days 112
Addl Days Granted 0
Working Days Charged 84
Percent Time Used 75
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0451-04-020
CROSSROADS, L.P. (0.81%)
DURABLE SPECIALTIES, INC.(0.28%)
SYNERGY SIGNS & SERVICES, LLC(2.16%)
TEX OP CONSTRUCTION, LP( 11.70%)
TOTAL HIGHWAY MAINTENANCE, LLC (3.41%)
WOLFE CONSTRUCTION GROUP, INC. (0.08%)
Contract # 07143035
Totals 1740711.54 37876.10 1574396.23 100.0

CountyCOLLIN
Highway SH 121
From SH 5
To 1.65 MILES WEST OF FM 455
CSJ 0549-03-018
Proj ID C 549-3-18
Work Type GRD, STR, BASE, PVMT, SIGNS
 
5.918 38276053.90 0.00 219691.60 0.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-12-14
Work Began 08-25-14
Work Completed  
Time Computed 02-28-14
Contract Working Days 671
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0549-03-018
FOWLER UNLIMITED, LLC(0.04%)
Contract # 11133202
Totals 38276053.90 0.00 219691.60 0.5

CountyELLIS
Highway SH 34
From FM 667
To US 287
CSJ 0568-01-046
Proj ID STP 2015(482)HES
Work Type TEXTURE SHDRS AND CTR LINE TEXTURIN
 
16.811 199164.27 0.00 0.00 0.0
Work Order 02-18-15
Work Began 00-00-00
Work Completed  
Time Computed 03-06-15
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0568-01-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153205
Totals 199164.27 0.00 0.00 0.0

CountyDALLAS
Highway SL 12
From IH 30
To FERGUSON RD
CSJ 0581-01-140
Proj ID NH 2014(268)
Work Type LANDSCAPE DEVELOPMENT
 
1.394 268951.00 25875.00 170421.67 63.3
Work Order 11-18-14
Work Began 12-15-14
Work Completed  
Time Computed 12-04-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 76
Contractor(s)
GREY CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0581-01-140
ALTUS TRAFFIC MANAGEMENT LLC (3.71%)
UNLIMITED UTILITY CONSTRUCTION (4.79%)
PAVEMENT SERVICES( 12.02%)
Contract # 10143228
Totals 268951.00 25875.00 170421.67 63.3

CountyDALLAS
Highway LP 12
From COCKRELL HILL ROAD
To ANDERSON ST
CSJ 0581-02-139
Proj ID NH 2014(581)
Work Type BRIDGE DECK AND JOINT REPAIRS
 
5.116 253575.50 14094.00 231135.73 100.0
Work Order 05-05-14
Work Began 10-27-14
Work Completed 02-09-15
Time Computed 09-02-14
Contract Working Days 94
Addl Days Granted 0
Working Days Charged 38
Percent Time Used 40
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0581-02-139
CROSSROADS, L.P. (2.85%)
Contract # 04143213
Totals 253575.50 14094.00 231135.73 100.0

CountyDALLAS
Highway LP 12
From SP 408
To WEST FORK OF TRINITY RIVER
CSJ 0581-02-140
Proj ID NH 2014(659)
Work Type FULL DEPTH REPAIR, MILL AND OVERLAY
 
4.413 2679703.82 0.00 2560786.42 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-22-14
Work Began 09-17-14
Work Completed 03-06-15
Time Computed 09-17-14
Contract Working Days 106
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 86
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0581-02-140
ALTUS TRAFFIC MANAGEMENT LLC (0.35%)
APAC-KANSAS( 10.81%)
BROCK ENVIRONMENTAL, LLC (0.60%)
DUSTROL, INC.(7.15%)
O. TREVINO CONSTRUCTION, LLC (7.23%)
W.O.E. CONSTRUCTION(1.29%)
BRENDA PRICE TRUCKING(0.15%)
COWBOY TRUCKING(1.05%)
STRIPING TECHNOLOGY, L.P.(5.39%)
MARCOM"S MOWING SERVICE, LLC (0.06%)
Contract # 05143025
Totals 2679703.82 0.00 2560786.42 100.0

CountyDALLAS
Highway SL 12
From ILLINOIS AVENUE
To NORTH OF SINGLETON BLVD
CSJ 0581-02-141
Proj ID STP 1502(042)
Work Type FDR - CP AND OVERLAY ON FRONTAGE RDS
 
8.760 2761594.56 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0581-02-141
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153219
Totals 2761594.56 0.00 0.00 0.0

CountyELLIS
Highway FM 66
From AT OAK BRANCH
To .
CSJ 0596-02-038
Proj ID BR 2015(066)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.206 1798061.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-01-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 343
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0596-02-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143226
Totals 1798061.60 0.00 0.00 0.0

CountyDENTON
Highway FM 544
From FM 2281
To 0.17 MILE WEST OF JOSEY LANE
CSJ 0619-05-034
Proj ID STP 1402(111)MM
Work Type GR, STR, BASE, PVMT, SIGNS, MKGS
 
2.311 21406881.99 0.00 0.00 0.0
CountyDENTON
Highway FM 544
From AT KCS RR, E OF FM 2281
To .
CSJ 0619-05-036
Proj ID BR 2014(763)
Work Type REPL BR & APPR
 
0.060 5316292.06 0.00 0.00 0.0
CountyDENTON
Highway FM 544
From 0.17 MILES WEST OF JOSEY LN
To PARKER/DOZIER RD.
CSJ 0619-05-037
Proj ID HP 2008(733)
Work Type RECONSTRUCT EXISTING ROADWAY
 
1.136 8667784.26 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-23-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 755
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MCM
SUBCONTRACTOR(S) FOR CCSJ: 0619-05-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143001
Totals 35390958.31 0.00 0.00 0.0

CountyKAUFMAN
Highway FM 986
From TOWN NORTH DR IN TERRELL
To CR 2326 (NEAR HUNT C/L)
CSJ 0642-05-023
Proj ID STP 2013(768)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
6.560 3869442.70 209286.88 3480724.91 89.9
Work Order 08-19-13
Work Began 10-07-13
Work Completed  
Time Computed 10-07-13
Contract Working Days 207
Addl Days Granted 0
Working Days Charged 207
Percent Time Used 100
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0642-05-023
BAHENA CONSTRUCTION CO.,INC. ( 17.30%)
CATOCON, INC.(0.94%)
DUSTROL, INC.(1.97%)
EROSION CONTROL MANAGEMENT SERVICES(2.13%)
FARR FOUNDATION, INC.(1.26%)
PEACHTREE CONSTRUCTION, LTD. ( 23.73%)
STRIPING TECHNOLOGY, L.P.(1.34%)
ALTUS TRAFFIC MANAGEMENT LLC (0.72%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.10%)
Contract # 06133017
Totals 3869442.70 209286.88 3480724.91 89.9

CountyKAUFMAN
Highway FM 429
From SH 243
To US 80
CSJ 0697-03-027
Proj ID STP 2015(393)HES
Work Type TEXTURE SHOULDERS AND CENTERLINE
 
21.758 207202.70 116429.97 167234.57 80.7
Work Order 01-07-15
Work Began 02-09-15
Work Completed  
Time Computed 01-23-15
Contract Working Days 104
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 23
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0697-03-027
FLEX SUPPLY, LLC (5.30%)
COWBELL TRAFFIC SERVICES, INC. ( 29.14%)
Contract # 12143221
Totals 207202.70 116429.97 167234.57 80.7

CountyDENTON
Highway FM 156 ETC
From SOUTH HICKORY CREEK
To 0.1 MI NORTH OF FM 2450
CSJ 0718-01-051
Proj ID STP 2007(014)
Work Type ADD 10' SHOULDERS AND REHAB
 
10.779 7732000.00 484198.56 6537844.99 85.4
Work Order 09-26-13
Work Began 11-11-13
Work Completed  
Time Computed 10-12-13
Contract Working Days 288
Addl Days Granted 0
Working Days Charged 347
Percent Time Used 120
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0718-01-051
W.O.E. CONSTRUCTION(4.24%)
J & M CONTRACTING, COMPANY (4.78%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.95%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.52%)
TEXAS SHAFTS, INC. (1.79%)
MASTERPIECE GRINDING & GROOVING, LLC (0.05%)
HJC FARMS, INC.(0.49%)
FORTSON CONTRACTING, INC.(2.68%)
BREDA COMPANY, INC.(0.42%)
ALTUS TRAFFIC MANAGEMENT LLC (0.50%)
MCL CONTRACTING, LLC (0.09%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.11%)
Contract # 07133229
Totals 7732000.00 484198.56 6537844.99 85.4

CountyKAUFMAN
Highway FM 148
From FM 1390 SOUTH
To US 175 SOUTH
CSJ 0751-02-023
Proj ID STP 2014(660)
Work Type MILL, REPAIR, OL, STR, MRKS, SIGN
 
7.475 10805279.10 71225.21 1622612.85 15.0
Work Order 07-08-14
Work Began 10-01-14
Work Completed  
Time Computed 09-06-14
Contract Working Days 246
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 10
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0751-02-023
TRP CONSTRUCTION GROUP, LLC(0.94%)
ALTUS TRAFFIC MANAGEMENT LLC (0.21%)
SAMMY G. SMALLWOOD (0.54%)
FORTSON CONTRACTING, INC.(2.15%)
K & S UTILITY CONTRACTORS, INC.(6.70%)
USA SWPPP INSPECTIONS, INC.(1.95%)
W.O.E. CONSTRUCTION(2.93%)
PEACHTREE CONSTRUCTION, LTD. (4.30%)
HORIZON SIGNAL TECHNOLOGIES, INC.(0.04%)
Contract # 05143221
Totals 10805279.10 71225.21 1622612.85 15.0

CountyELLIS
Highway FM 663
From SOUTH OF US 287
To NORTH OF US 287
CSJ 0815-08-027
Proj ID PTF 2013(451)
Work Type STR, PVMT, PVMT MKGS
 
0.568 4728943.55 336242.52 3310975.97 70.0
Work Order 05-16-13
Work Began 06-30-14
Work Completed  
Time Computed 06-01-13
Contract Working Days 161
Addl Days Granted 0
Working Days Charged 130
Percent Time Used 80
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0815-08-027
TOTAL HIGHWAY MAINTENANCE, LLC (0.26%)
WYLIE DRILLING & DRAINAGE, INC.(0.75%)
USA SWPPP INSPECTIONS, INC.(1.93%)
STRIPING TECHNOLOGY, L.P.(1.20%)
SOUTHEAST GRINDING & GROOVING, LLC (0.05%)
SCOTT DERR PAINTING CO, LLC(0.20%)
MCL CONTRACTING, LLC (0.48%)
LONE STAR BARRIER SERVICES, LLC(0.83%)
INLET STRUCTURE SPECIALTIES LTD. (1.27%)
DUSTROL, INC.(0.51%)
DURABLE SPECIALTIES, INC.(5.94%)
PREMIER PAVING, LTD. ( 10.88%)
CHRISTINE"S CONCERTE SAWING & SEALING LLC(0.17%)
Contract # 03133216
Totals 4728943.55 336242.52 3310975.97 70.0

CountyDENTON
Highway FM 455
From AT BOOM CREEK
To .
CSJ 0816-02-053
Proj ID BR 2014(764)
Work Type REPLACE EXISTING BRIDGE AND APPROAC
 
1.646 3335495.22 12711.66 47292.30 1.4
Work Order 09-09-14
Work Began 00-00-00
Work Completed  
Time Computed 09-25-14
Contract Working Days 193
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0816-02-053
ALTUS TRAFFIC MANAGEMENT LLC (0.39%)
FOUNDATION DRILLERS, INC.(1.63%)
HJC FARMS, INC.(0.21%)
LAYFIELD CONSTRUCTION, INC (1.66%)
LINDAMOOD DEMOLITION, INC. (0.41%)
MCL CONTRACTING, LLC (1.58%)
PENHALL COMPANY(0.08%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.40%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.98%)
Contract # 06143238
Totals 3335495.22 12711.66 47292.30 1.4

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9