Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCOLLIN
Highway SH 78
From BUSINESS 78
To FM 6
CSJ 0281-01-030
Proj ID C 281-1-030
Work Type GRADING, DRAINAGE, AND PAVEMENT
 
2.563 24832811.20 69683.55 19645048.14 79.1
Work Order 06-15-12
Work Began 12-13-12
Work Completed  
Time Computed 12-12-12
Contract Working Days 630
Addl Days Granted 70
Working Days Charged 650
Percent Time Used 92
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0281-01-030
STORM WATER MANAGEMENT, INC. (0.35%)
INTEGRATED ROADWAY SERVICES, INC.(1.79%)
TEX OP CONSTRUCTION, LP(0.61%)
FOUNDATION DRILLERS, INC.(1.05%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 12.22%)
FORTSON CONTRACTING, INC.(0.03%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.05%)
J.L. STEEL REINFORCING, LLC(1.02%)
W.O.E. CONSTRUCTION(0.36%)
ALLIANCE GEOTECHNICAL GROUP(0.09%)
SCOTT DERR PAINTING CO (0.14%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.76%)
GREAT WESTERN ERECTORS (0.06%)
LONE STAR MANHOLE & STRUCTURES, LLC(3.52%)
AMERICAN INTERLOCK & MODULAR CONSTRUCTION, INC.(0.03%)
USA SWPPP INSPECTIONS, INC.(0.19%)
JET UNDERGROUND UTILITIES, INC.(1.23%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(0.54%)
SOUTHEAST GRINDING & GROOVING, LLC (0.02%)
ODUM SERVICES, L.P.(0.00%)
J. E. GUZMAN CONSTRUCTION, INC.(0.53%)
IRON CONCRETE CONSTRUCTION COMPANY, INC. (1.35%)
Contract # 04123201
Totals 24832811.20 69683.55 19645048.14 79.1

CountyCOLLIN
Highway SH 78
From SPRING CREEK PKWY
To SH 205
CSJ 0281-02-039
Proj ID C 281-2-39
Work Type WDN GR STRS & SURF
 
3.349 21337007.60 66650.07 6583014.59 30.8
Work Order 08-28-12
Work Began 09-12-13
Work Completed  
Time Computed 05-25-13
Contract Working Days 630
Addl Days Granted 0
Working Days Charged 253
Percent Time Used 40
Contractor(s)
GLENN THURMAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0281-02-039
CONCRETE CUTTING BY BOND (0.33%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 15.66%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.92%)
BUYERS BARRICADES, INC.(0.25%)
DT CONSTRUCTION SERVICES (2.63%)
LARRETT, INC.( 11.16%)
INTEGRATED ROADWAY SERVICES, INC.(2.02%)
INDUS CONSTRUCTION, L.P. (0.68%)
DUSTROL, INC.(1.51%)
ENVIRONMENTAL STANDARDS, INC.(2.51%)
COPPELL CONSTRUCTION CO., INC. ( 12.43%)
TEXAS SHAFTS, INC. (1.32%)
MCL CONTRACTING, LLC (0.07%)
IOWA BRIDGE & CULVERT, LC(0.77%)
MEADE SERVICING GROUP, INC.(2.52%)
W.O.E. CONSTRUCTION(0.29%)
Contract # 06123202
Totals 21337007.60 66650.07 6583014.59 30.8

CountyCOLLIN
Highway SH 78 ETC
From N. OF WILLIFORD RD IN SACHSE
To SPRING CREEK IN WYLIE
CSJ 0281-02-069
Proj ID STP 2013(657)
Work Type FULL DEPTH REPAIR
 
50.849 595393.36 0.00 570875.77 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-31-13
Work Began 09-17-13
Work Completed 11-20-14
Time Computed 08-16-13
Contract Working Days 157
Addl Days Granted 0
Working Days Charged 157
Percent Time Used 100
Contractor(s)
TEXAS HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0281-02-069
XTREEME SAWING & SEALING, INC. (5.50%)
BUYERS BARRICADES, INC.(3.02%)
Contract # 04133007
Totals 595393.36 0.00 570875.77 100.0

CountyDENTON
Highway FM 51
From AT BLOCKER CREEK
To .
CSJ 0312-02-016
Proj ID BR 2013(603)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.303 2575804.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-10-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 316
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
IOWA BRIDGE & CULVERT, LC
SUBCONTRACTOR(S) FOR CCSJ: 0312-02-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153023
Totals 2575804.40 0.00 0.00 0.0

CountyDENTON
Highway SH 114
From WEST OF COUNTY LINE ROAD
To WEST OF FM 156
CSJ 0353-02-029
Proj ID C 353-2-29
Work Type GR STRS & SURF
 
4.638 28612477.14 43688.91 26239489.63 91.7
Work Order 08-28-12
Work Began 04-22-13
Work Completed  
Time Computed 02-25-13
Contract Working Days 569
Addl Days Granted 0
Working Days Charged 514
Percent Time Used 90
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0353-02-029
FOUNDATION DRILLERS, INC.(0.31%)
HIGHWAY TECHNOLOGIES, INC. (0.19%)
INTEGRATED ROADWAY SERVICES, INC.(2.34%)
THE LANE CONSTRUCTION CORPORATION( 35.42%)
NORTH TEXAS CONTRACTING, INC.(8.47%)
TRP CONSTRUCTION GROUP, LLC(0.85%)
W.O.E. CONSTRUCTION(4.17%)
FOWLER UNLIMITED, LLC(0.17%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.04%)
J.L. STEEL REINFORCING, LLC(0.00%)
K.L. DURHAM CONSTRUCTION, LLC(1.57%)
FARR FOUNDATION, INC.(0.69%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(0.46%)
INDUS CONSTRUCTION, L.P. (0.87%)
WEBBER BARRIER SERVICES, LLC.(0.27%)
SLATON BROTHERS, INC.(0.52%)
Contract # 06123201
Totals 28612477.14 43688.91 26239489.63 91.7

CountyDENTON
Highway SH 114
From NORTH OF BUS 114
To WEST OF TROPHY CLUB DR
CSJ 0353-02-060
Proj ID C 353-2-60
Work Type GR, STRS, BASE & SURF
 
1.649 33333333.33 17855.92 33721259.51 99.9
Work Order 02-15-11
Work Began 03-14-11
Work Completed  
Time Computed 03-14-11
Contract Working Days 650
Addl Days Granted 112
Working Days Charged 758
Percent Time Used 99
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0353-02-060
COWTOWN TRAFFIC CONTROL, INC.(0.09%)
INDUS CONSTRUCTION, L.P. (1.12%)
INTERSTATE FOUNDATION, LLC (0.87%)
J.L. STEEL REINFORCING, LLC(0.06%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.73%)
WRIGHT CONSTRUCTION CO., INC.( 11.11%)
DALLAS LITE AND BARRICADE INC. (0.20%)
J. E. GUZMAN CONSTRUCTION, INC.(0.82%)
INTEGRATED ROADWAY SERVICES, INC.(1.69%)
THE LANE CONSTRUCTION CORPORATION(7.26%)
CRAIG OLDEN, INC.(0.95%)
DUSTROL, INC. (ROANOKE)(0.02%)
S & V CONSTRUCTION LLC (1.33%)
STRIPING TECHNOLOGY, L.P.(0.24%)
TEX OP CONSTRUCTION, LP(0.02%)
W.O.E. CONSTRUCTION(0.65%)
CHOCTAW ERECTORS, INC. (1.30%)
GLENN THURMAN, INC.( 15.64%)
VSTRUCTURAL LLC(0.08%)
CONCRETE CUTTING BY BOND (0.14%)
HOUSTON SAWING & DRILLING(0.07%)
WEBBER BARRIER SERVICES, INC.(1.27%)
SOUTH TEXAS PAINTING COMPANY (0.58%)
SCOTT DERR PAINTING CO, LLC(0.14%)
SLATON BROTHERS, INC.(0.12%)
Contract # 01113205
Totals 33333333.33 17855.92 33721259.51 99.9

CountyDENTON
Highway SH 114
From EAST OF FM 156
To WEST OF IH 35W
CSJ 0353-02-062
Proj ID C 353-2-62
Work Type GR, STR, PAV, STRM SEWER, PAV MRK, SIG
 
1.830 15384182.11 59300.49 20678896.71 99.9
Work Order 11-16-10
Work Began 04-22-11
Work Completed  
Time Computed 05-15-11
Contract Working Days 562
Addl Days Granted 167
Working Days Charged 692
Percent Time Used 94
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0353-02-062
ARLINGTON PAVERS, INC. (0.03%)
DUSTROL, INC. (ROANOKE)(0.24%)
FORTSON CONTRACTING, INC.(0.04%)
HIGHWAY TECHNOLOGIES, INC. (0.41%)
INDUS CONSTRUCTION, L.P. (0.93%)
JAGOE-PUBLIC COMPANY ( 11.50%)
MUSTANG TURF & LANDSCAPE, LLC(2.47%)
RMI WORLDWIDE, LLC (0.19%)
SOUTHWEST CONSTRUCTION SERVICES(0.36%)
SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.12%)
STORM WATER MANAGEMENT, INC. (0.17%)
S & V CONSTRUCTION LLC (0.35%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (4.68%)
TEXAS SHAFTS, INC. (0.18%)
PENHALL COMPANY(0.01%)
MARKSMAN CONTRACTING, LLC(0.52%)
RAMBO CONTRACTING, INC.(1.30%)
TEXAS INLETS, INC. (2.55%)
STOMPER DEMOLITION COMPANY, INC. (0.04%)
LLANO UTILITY SERVICES, INC. (0.10%)
J.L. STEEL REINFORCING, LLC(0.01%)
MELS ELECTRIC, L.P.(0.05%)
STRIPING TECHNOLOGY, L.P.(0.46%)
RICE ENVIRONMENTAL SERVICES(0.34%)
MICA CORPORATION (1.29%)
EPCS ENVIRONMENTAL, LLC(0.13%)
Contract # 10103001
Totals 15384182.11 59300.49 20678896.71 99.9

CountyDENTON
Highway SH 114
From AT FM 156
To .
CSJ 0353-02-063
Proj ID C 353-2-63
Work Type GR, STRS & PAVT
 
1.269 30580029.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-03-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 651
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0353-02-063
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153001
Totals 30580029.40 0.00 0.00 0.0

CountyDALLAS
Highway SS 348
From SH 114
To LOOP 12
CSJ 0353-04-098
Proj ID NH 2015(845)
Work Type FDR - CP
 
5.291 679176.65 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-21-15
Work Began 00-00-00
Work Completed  
Time Computed 06-21-15
Contract Working Days 63
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0353-04-098
BRENDA PRICE TRUCKING(0.98%)
ALTUS TRAFFIC MANAGEMENT LLC (0.85%)
DUSTROL, INC.(9.50%)
PREMIER PAVING, LTD. ( 24.77%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.24%)
DURABLE SPECIALTIES, INC.(2.35%)
W.O.E. CONSTRUCTION(1.67%)
Contract # 04153010
Totals 679176.65 0.00 0.00 0.0

CountyDALLAS
Highway SL 12
From WEST OF HARRY HINES
To WEST OF MIDWAY
CSJ 0353-05-082
Proj ID CM 1502(091)
Work Type RECONSTRUCT, GRADING, BASE, PAVEMEN
 
2.746 5165037.00 0.00 0.00 0.0
CountyDALLAS
Highway SL 12
From WEST OF HARRY HINES
To WEST OF MIDWAY
CSJ 0353-05-105
Proj ID CM 2005(220)
Work Type ROW ACQ., UTIL. ADJ., RELOC ASSIST.
 
3.201 1151839.50 0.00 0.00 0.0
CountyDALLAS
Highway SL 12
From AT WEBB CHAPEL EXTENSION
To .
CSJ 0353-05-114
Proj ID STP 1502(092)HES
Work Type IMPROVE TRAFFIC SIGNALS
 
0.001 235159.80 0.00 0.00 0.0
CountyDALLAS
Highway SL 12
From AT WEBB CHAPEL
To .
CSJ 0353-05-115
Proj ID STP 1502(093)HES
Work Type IMPROVE TRAFFIC SIGNALS
 
0.001 184815.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 335
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0353-05-082
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153215
Totals 6736851.50 0.00 0.00 0.0

CountyDALLAS
Highway LP 12
From W. LAWTHER DRIVE
To EAST OF GOFORTH DRIVE
CSJ 0353-05-084
Proj ID NH 2008(361)
Work Type GRADING, STRS, ACP, SIGNING, PAVT M
 
0.785 28349251.84 154337.08 30749240.07 100.0
CountyDALLAS
Highway LP 12
From W. LAWTHER DRIVE
To EAST OF GOFORTH DRIVE
CSJ 0353-05-110
Proj ID RW 353-5-110
Work Type ROW UTL. ADJ. IN CONSTRUCTION
 
0.785 3131109.30 0.00 3095232.21 100.0
Work Order 10-22-08
Work Began 11-17-08
Work Completed 01-07-15
Time Computed 01-20-09
Contract Working Days 533
Addl Days Granted 85
Working Days Charged 618
Percent Time Used 100
Contractor(s)
REBCON, INC.
CONCHO CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0353-05-084
ARK CONTRACTING SERVICES, LLC(1.88%)
AUSTIN BRIDGE & ROAD, LP (1.88%)
FORTSON CONTRACTING, INC.(0.60%)
TEXAS SHAFTS, INC. (5.55%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.12%)
COWTOWN TRAFFIC CONTROL, INC.(0.00%)
DGI-MENARD, INC. (0.55%)
DUSTROL, INC. (ROANOKE)(0.38%)
MIKE ALBERT, INC.( 10.64%)
SOUTHWEST CONSTRUCTION SERVICES(0.05%)
WEIR BROS., INC. (5.05%)
ENVIRONMENTAL STANDARDS(1.85%)
STAR OPERATIONS, INC.(2.94%)
RG PAINTING(0.22%)
J.R. DAVIS AND ASSOCIATES, INC.(1.86%)
WEST TEXAS REBAR PLACERS INC.(0.00%)
EAGLE AGGREGATE TRANSPORTATION, LLC. (0.00%)
SALDANA'S TRUCKING COMPANY, INC. (0.22%)
CONCRETE CUTTING BY BOND (0.04%)
HOUSTON SAWING & DRILLING(0.07%)
TEXAS INLETS, INC. (0.29%)
SKAGGS ROAD BORING INC.(0.12%)
J.L. STEEL REINFORCING, LLC(0.17%)
Contract # 08083217
Totals 31480361.14 154337.08 33844472.28 100.0

CountyDALLAS
Highway SL 12
From WEST OF MIDWAY
To US 75
CSJ 0353-05-088
Proj ID CM 1402(026)
Work Type INTERSECTION IMPROVEMENT
 
3.939 6564020.36 102828.61 1022766.31 15.5
CountyDALLAS
Highway SL 12
From WEST OF MIDWAY
To US 75
CSJ 0353-05-107
Proj ID CM 2005(517)
Work Type ACQUISITION, UTILITIES AND RELOCATI
 
3.940 1087941.00 0.00 0.00 0.0
Work Order 11-19-14
Work Began 02-19-15
Work Completed  
Time Computed 02-19-15
Contract Working Days 457
Addl Days Granted 6
Working Days Charged 66
Percent Time Used 14
Contractor(s)
REBCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0353-05-088
DURABLE SPECIALTIES, INC.( 16.58%)
BUYERS BARRICADES, INC.(1.31%)
INLET STRUCTURE SPECIALTIES LTD. (0.64%)
PREMIER PAVING, LTD. (3.01%)
W.O.E. CONSTRUCTION(0.08%)
USA SWPPP INSPECTIONS, INC.(1.16%)
NORTH TEXAS CONTRACTING, INC.( 14.83%)
STRIPING TECHNOLOGY, L.P.(1.00%)
TED ALVAREZ TRUCKING (1.64%)
SKAGGS ROAD BORING INC.(0.84%)
J. E. GUZMAN CONSTRUCTION, INC.(0.05%)
Contract # 08143219
Totals 7651961.36 102828.61 1022766.31 13.3

CountyDALLAS
Highway SH 121
From TARRANT/DALLAS COUNTY LINE
To BUSINESS 121H
CSJ 0364-02-017
Proj ID NH 2013(829)
Work Type GRADING, STRUCTURES AND SURFACE
 
2.567 58805233.66 679484.35 27341540.49 46.4
Work Order 09-04-13
Work Began 03-04-14
Work Completed  
Time Computed 03-03-14
Contract Working Days 986
Addl Days Granted 1
Working Days Charged 357
Percent Time Used 36
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0364-02-017
ALTUS TRAFFIC MANAGEMENT LLC (0.12%)
USA SWPPP INSPECTIONS, INC.(1.33%)
FOWLER UNLIMITED, LLC(0.05%)
RAMBO CONTRACTING, INC.(1.72%)
RDI FOUNDATION DRILLING(1.93%)
VALLEY PLACERS, LLC(0.15%)
FORTSON CONTRACTING, INC.(0.32%)
HOUSTON SAWING & DRILLING(0.03%)
BORTUNCO (0.83%)
AUSTIN BRIDGE & ROAD, LP ( 12.65%)
TEX OP CONSTRUCTION, LP(0.61%)
RONE ENGINEERING SERVICES, LTD (0.07%)
SCOTT DERR PAINTING CO (0.15%)
W.O.E. CONSTRUCTION(3.18%)
STRIPING TECHNOLOGY, L.P.(0.89%)
MCL CONTRACTING, LLC (7.51%)
SOUTH TEXAS ILLUMINATION, LLC(3.83%)
LABOR READY CENTRAL III L.P. (0.00%)
Contract # 07133002
Totals 58805233.66 679484.35 27341540.49 46.4

CountyDALLAS
Highway IH 35E
From ELLIS/DALLAS CL
To 8TH STREET
CSJ 0442-02-156
Proj ID IM 0356(446)
Work Type INSTALLATION OF SIGNS
 
18.212 328568.40 7855.54 325052.58 100.0
Work Order 06-02-14
Work Began 12-17-14
Work Completed 06-04-15
Time Computed 11-29-14
Contract Working Days 56
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 103
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0442-02-156
ALTUS TRAFFIC MANAGEMENT LLC (2.53%)
FORTSON CONTRACTING, INC.( 11.80%)
Contract # 04143226
Totals 328568.40 7855.54 325052.58 100.0

CountyROCKWALL
Highway SH 205
From AT FM 549
To .
CSJ 0451-01-051
Proj ID STP 1502(326)HES
Work Type ADD LEFT AND RIGHT TURN LANES
 
0.559 801819.95 0.00 0.00 0.0
CountyROCKWALL
Highway FM 549
From SH 205
To SH 276
CSJ 1015-01-025
Proj ID STP 1502(325)
Work Type GR, BASE, ACP OVERLAY, PVMT MKGS
 
4.866 6648602.81 0.00 0.00 0.0
CountyROCKWALL
Highway SH 276
From AT FM 548
To .
CSJ 1290-03-026
Proj ID STP 1502(327)HES
Work Type ADD LEFT TURN LANE
 
0.306 299049.77 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 410
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1015-01-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153249
Totals 7749472.53 0.00 0.00 0.0

CountyROCKWALL
Highway SH 205
From SOUTH OF WEST HEATH ST
To JOHN KING BLVD
CSJ 0451-04-020
Proj ID STP 2014(871)
Work Type MILL, REPAIR, OL, STR, MRKS, SIGNS
 
3.113 1740711.54 30795.39 1605191.62 100.0
Work Order 08-20-14
Work Began 09-23-14
Work Completed 04-01-15
Time Computed 09-05-14
Contract Working Days 112
Addl Days Granted 0
Working Days Charged 84
Percent Time Used 75
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0451-04-020
CROSSROADS, L.P. (0.81%)
DURABLE SPECIALTIES, INC.(0.28%)
SYNERGY SIGNS & SERVICES, LLC(2.16%)
TEX OP CONSTRUCTION, LP( 11.70%)
TOTAL HIGHWAY MAINTENANCE, LLC (3.41%)
WOLFE CONSTRUCTION GROUP, INC. (0.08%)
Contract # 07143035
Totals 1740711.54 30795.39 1605191.62 100.0

CountyCOLLIN
Highway SH 121
From SH 5
To 1.65 MILES WEST OF FM 455
CSJ 0549-03-018
Proj ID C 549-3-18
Work Type GRD, STR, BASE, PVMT, SIGNS
 
5.918 38276053.90 0.00 219691.60 0.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-12-14
Work Began 08-25-14
Work Completed  
Time Computed 02-28-14
Contract Working Days 671
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0549-03-018
FOWLER UNLIMITED, LLC(0.04%)
Contract # 11133202
Totals 38276053.90 0.00 219691.60 0.5

CountyCOLLIN
Highway SH 121
From SH 5
To 1.65 MILES WEST OF FM 455
CSJ 0549-03-027
Proj ID C 549-3-27
Work Type GRD, STR, BASE, PVMT, SIGNS
 
5.918 43893899.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 768
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0549-03-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153202
Totals 43893899.25 0.00 0.00 0.0

CountyELLIS
Highway SH 34
From FM 667
To US 287
CSJ 0568-01-046
Proj ID STP 2015(482)HES
Work Type TEXTURE SHDRS AND CTR LINE TEXTURIN
 
16.811 199164.27 0.00 0.00 0.0
Work Order 02-18-15
Work Began 00-00-00
Work Completed  
Time Computed 03-06-15
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0568-01-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153205
Totals 199164.27 0.00 0.00 0.0

CountyDALLAS
Highway SL 12
From IH 30
To FERGUSON RD
CSJ 0581-01-140
Proj ID NH 2014(268)
Work Type LANDSCAPE DEVELOPMENT
 
1.394 268951.00 16399.20 237116.49 88.3
Work Order 11-18-14
Work Began 12-15-14
Work Completed  
Time Computed 12-04-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 101
Contractor(s)
GREY CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0581-01-140
ALTUS TRAFFIC MANAGEMENT LLC (3.71%)
UNLIMITED UTILITY CONSTRUCTION (4.79%)
PAVEMENT SERVICES( 12.02%)
Contract # 10143228
Totals 268951.00 16399.20 237116.49 88.3