Monthly State Let Construction Report For Dallas District As Of Aug 16, 2016 Page 7 Of 8

Last Update: Tuesday, August 16, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDALLAS
Highway IH 30
From NW 7TH STREET
To BELTLINE ROAD
CSJ 1068-04-148
Proj ID STP 2016(740)MM
Work Type GR, DRN, RET WLS, CONC PAV, SIG, PV MRKS
 
1.011 7991673.30 370585.33 661118.57 8.2
Work Order 04-01-16
Work Began 05-18-16
Work Completed  
Time Computed 05-18-16
Contract Working Days 380
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 12
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-148
ALTUS TRAFFIC MANAGEMENT LLC (0.17%)
W.O.E. CONSTRUCTION(2.42%)
C.T. AND S. METALWORKS, INC. (0.37%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.22%)
FORTSON CONTRACTING, INC.(0.31%)
K & S UTILITY CONTRACTORS, INC.( 12.19%)
MICA CORPORATION (3.52%)
STORM WATER MANAGEMENT, INC. (0.23%)
STRIPE-A-ZONE, INC.(1.02%)
SYNERGY SIGNS & SERVICES (0.36%)
TEXAS BOMANITE (0.05%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.32%)
TEXAS SHAFTS, INC. (0.67%)
BOWMAN ENGINEERING & CONSTRUCTION, INC.(1.25%)
SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.01%)
Contract # 02163225
Totals 7991673.30 370585.33 661118.57 8.2

CountyDALLAS
Highway IH 30
From COCKRELL HILL ROAD
To WESTMORELAND RD IN DALLAS
CSJ 1068-04-154
Proj ID C 1068-4-154
Work Type GRADING, PAVEMENT, SIGNS, PVMT MKGS
 
2.704 9814841.51 340085.35 8200359.18 84.9
Work Order 09-09-14
Work Began 11-11-14
Work Completed  
Time Computed 09-25-14
Contract Working Days 321
Addl Days Granted 5
Working Days Charged 449
Percent Time Used 137
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-154
K & S UTILITY CONTRACTORS, INC.(9.08%)
OSCAR ORDUNO, INC. (4.26%)
STORM WATER MANAGEMENT, INC. (0.29%)
SLATON BROTHERS, INC.(4.57%)
W.O.E. CONSTRUCTION(7.63%)
MICA CORPORATION (1.31%)
DURABLE SPECIALTIES, INC.(1.31%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.44%)
J.H. PAINTING COMPANY(0.16%)
Contract # 07143214
Totals 9814841.51 340085.35 8200359.18 84.9

CountyKAUFMAN
Highway FM 741
From US 175
To EAST OF FM 548
CSJ 1092-01-017
Proj ID STP 2015(778)
Work Type GR, BASE, ACP OVERLAY, PVMT MKGS
 
7.726 4550316.19 93578.75 4492231.50 99.9
Work Order 03-23-15
Work Began 06-03-15
Work Completed  
Time Computed 04-23-15
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 275
Percent Time Used 147
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1092-01-017
ALTUS TRAFFIC MANAGEMENT LLC (0.26%)
TEXAS ENVIRONMENTAL MANAGEMENT SA, INC.(4.68%)
DUSTROL, INC.(4.57%)
MARCOM"S MOWING SERVICE, LLC (1.16%)
J & M CONTRACTING, COMPANY (7.65%)
STRIPING TECHNOLOGY, L.P.(1.43%)
FORTSON CONTRACTING, INC.(0.60%)
C & J TREE SERVICE (0.03%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (4.68%)
Contract # 02153235
Totals 4550316.19 93578.75 4492231.50 99.9

CountyELLIS
Highway FM 875
From AT WAXAHACHIE CREEK
To .
CSJ 1159-01-022
Proj ID BR 2013(604)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.471 3724841.00 0.00 26660.86 0.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-13-15
Work Began 00-00-00
Work Completed  
Time Computed 12-11-15
Contract Working Days 467
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 1159-01-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153025
Totals 3724841.00 0.00 26660.86 0.7

CountyELLIS
Highway FM 879
From 2.1 MILES WEST OF IKE RD
To 0.3 MILE WEST OF FM 1722
CSJ 1159-02-032
Proj ID STP 1502(328)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
6.667 9549753.04 715273.73 4119828.66 43.1
Work Order 07-31-15
Work Began 09-03-15
Work Completed  
Time Computed 07-31-15
Contract Working Days 315
Addl Days Granted 12
Working Days Charged 245
Percent Time Used 74
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1159-02-032
CROSS ROADS, L.P.(0.38%)
BROCK ENVIRONMENTAL SERVICES, LLC(0.19%)
ACU CONSTRUCTION LLC (1.24%)
STRIPING TECHNOLOGY, L.P.(0.61%)
SYNERGY SIGNS & SERVICES (0.28%)
FORTSON CONTRACTING, INC.(1.62%)
NORTH EASTERN PAVERS (4.90%)
PEACHTREE CONSTRUCTION, LTD. ( 13.21%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (4.95%)
HAYWARD BAKER, INC.(0.67%)
BRENDA PRICE TRUCKING(6.89%)
Contract # 06153225
Totals 9549753.04 715273.73 4119828.66 43.1

CountyELLIS
Highway FM 984
From AT DRAW, 1.7 MI SOUTH OF SH 34
To .
CSJ 1211-01-018
Proj ID BR 2015(483)
Work Type REPL BR AND APPR
 
0.117 879623.40 256085.35 309603.06 35.1
CountyELLIS
Highway FM 984
From AT ONION CREEK RELIEF #1 AND #2
To .
CSJ 1211-01-019
Proj ID BR 2015(484)
Work Type REPL BR
 
0.156 1453823.50 59180.00 363254.80 24.9
Work Order 03-02-15
Work Began 02-25-16
Work Completed  
Time Computed 02-25-16
Contract Working Days 379
Addl Days Granted 0
Working Days Charged 109
Percent Time Used 28
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 1211-01-018
FORTSON CONTRACTING, INC.(2.16%)
USA EROSION, INC.(3.94%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.48%)
STRIPING TECHNOLOGY, L.P.(1.23%)
TEX OP CONSTRUCTION, LP(1.11%)
W. W. FOUNDATION DRILLING, LTD.(5.36%)
Contract # 01153012
Totals 2333446.90 315265.35 672857.86 28.8

CountyKAUFMAN
Highway FM 1388
From FM 148
To US 175
CSJ 1217-03-019
Proj ID STP 2016(360)
Work Type GR, BASE, ACP OVERLAY, PVMT MKGS
 
12.030 17608683.44 304019.50 2247374.01 12.7
CountyKAUFMAN
Highway FM 1388
From AT KINGS CREEK RELIEF #2
To .
CSJ 1217-03-020
Proj ID BR 2016(361)
Work Type REPLACE BRIDGE
 
0.495 4432389.14 0.00 2630.00 0.0
Work Order 01-29-16
Work Began 04-11-16
Work Completed  
Time Computed 04-11-16
Contract Working Days 580
Addl Days Granted 0
Working Days Charged 89
Percent Time Used 15
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1217-03-019
ALTUS TRAFFIC MANAGEMENT LLC (0.13%)
SOUTHWEST CONSTRUCTION SERVICES(0.39%)
K & S UTILITY CONTRACTORS, INC.(9.31%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.72%)
A-CORE, INC. (0.02%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(0.05%)
PEACHTREE CONSTRUCTION, LTD. (4.40%)
INDUS CONSTRUCTION, L.P. (0.07%)
SOUTHERN CROSS CONTRACTORS, LLC(0.08%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(5.40%)
SYNERGY SIGNS & SERVICES, LLC(0.39%)
FARR FOUNDATION, INC.(0.56%)
FORTSON CONTRACTING, INC.(0.74%)
TRP CONSTRUCTION GROUP, LLC(0.60%)
HERDEZ TRUCKING, INC.(2.17%)
RAMBO CONTRACTING, INC.(4.73%)
TEXOP CONSTRUCTION (0.07%)
Contract # 12153205
Totals 22041072.58 304019.50 2250004.01 10.2

CountyNAVARRO
Highway FM 1126
From AT CHAMBERS CREEK, SW OF IH 45
To .
CSJ 1289-01-029
Proj ID BR 1602(046)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.890 6714487.74 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-02-16
Work Began 08-09-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 386
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1289-01-029
A. L. HELMCAMP, INC. ( 22.43%)
IOWA BRIDGE & CULVERT, LC(1.25%)
AARON CONCRETE CONTRACTORS, L.P. (3.51%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.82%)
FORTSON CONTRACTING, INC.(0.29%)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(0.29%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.26%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.42%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.37%)
Contract # 04163237
Totals 6714487.74 0.00 0.00 0.0

CountyDENTON
Highway FM 1171
From WEST OF US 377
To WEST OF SHILOH RD
CSJ 1311-01-034
Proj ID C 1311-1-34
Work Type GR, STRS, BASE, CRCP, PVMT MKGS, SIGNS
 
7.011 45721253.16 1359648.85 43427136.76 94.9
Work Order 06-05-13
Work Began 06-02-14
Work Completed  
Time Computed 03-02-14
Contract Working Days 693
Addl Days Granted 0
Working Days Charged 542
Percent Time Used 78
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1311-01-034
BREDA COMPANY, INC.(0.96%)
BUYERS BARRICADES, INC.(0.20%)
CINTEREX US, INC.(2.10%)
CLLA GROUP, LLC(9.39%)
DUSTROL, INC.(0.30%)
INTEGRATED ROADWAY SERVICES, INC.(2.34%)
JAGOE-PUBLIC COMPANY ( 14.10%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.74%)
THELIN RECYCLING COMPANY, L.P. (0.16%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.10%)
W.O.E. CONSTRUCTION(0.28%)
WYLIE DRILLING & DRAINAGE, INC.(0.83%)
VENUS CONSTRUCTION (7.23%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.35%)
SLATON BROTHERS, INC.(0.58%)
CB SERVICES, INC.(0.10%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.07%)
LLOYD D. NABORS DEMOLITION LLC (0.12%)
STORM WATER MANAGEMENT, INC. (0.07%)
THE LANE CONSTRUCTION CORPORATION(0.93%)
SCOTT DERR PAINTING CO, LLC(0.06%)
Contract # 03133002
Totals 45721253.16 1359648.85 43427136.76 94.9

CountyDENTON
Highway FM 1171
From ON CORPS OF ENGINEERS PROPERTY
To NEAR WHITE'S BRANCH
CSJ 1311-01-053
Proj ID C 1311-1-53
Work Type TREES AND PLANTS
 
0.001 148908.50 0.00 61596.76 41.3
CountyDENTON
Highway FM 2499
From FM 2181
To HICKORY CREEK
CSJ 2681-01-022
Proj ID NH 1502(094)
Work Type LANDSCAPE DEVELOPMENT
 
1.112 299148.05 0.00 277336.91 92.7
Work Order 07-20-15
Work Began 08-04-15
Work Completed  
Time Computed 08-04-15
Contract Working Days 60
Addl Days Granted 2
Working Days Charged 34
Percent Time Used 54
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2681-01-022
ALTUS TRAFFIC MANAGEMENT LLC (0.85%)
AMAYA UTILITY(0.56%)
QUICK SET CONCRETE, INC. (5.50%)
Contract # 05153018
Totals 448056.55 0.00 338933.67 75.6

CountyDENTON
Highway FM 1385
From US 380
To APPROX. 2 MILES NORTH OF FM 428
CSJ 1315-01-025
Proj ID STP 1402(028)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
7.588 9063184.19 609293.73 7296849.65 80.5
Work Order 12-10-14
Work Began 07-10-15
Work Completed  
Time Computed 06-08-15
Contract Working Days 378
Addl Days Granted 0
Working Days Charged 271
Percent Time Used 71
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1315-01-025
ALTUS TRAFFIC MANAGEMENT LLC (0.54%)
ASHLAR CONTRACTING COMPANY (8.41%)
SAMMY SMALLWOOD COMPANY(0.61%)
STRIPING TECHNOLOGY, L.P.(1.77%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(7.84%)
W.S. CONSTRUCTION COMPANY(6.71%)
JM YANEZ CONSTRUCTION(8.03%)
BRADLEY DOUGLAS CONSTRUCTION SERVICES, LLC.(0.79%)
Contract # 09143208
Totals 9063184.19 609293.73 7296849.65 80.5

CountyDENTON
Highway FM 423
From US 380
To 0.8 MI SOUTH OF FM 2934
CSJ 1315-02-009
Proj ID C 1315-2-9
Work Type WIDEN TO 6 LANE DIVIDED URBAN
 
3.488 29826069.73 1037035.26 19426324.98 65.1
Work Order 12-12-13
Work Began 10-08-14
Work Completed  
Time Computed 09-08-14
Contract Working Days 603
Addl Days Granted 0
Working Days Charged 461
Percent Time Used 76
Contractor(s)
MCM
SUBCONTRACTOR(S) FOR CCSJ: 1315-02-009
TOTAL HIGHWAY MAINTENANCE, LLC (0.96%)
STORM WATER MANAGEMENT, INC. (0.28%)
BOWMAN ENGINEERING & CONSULTING, INC.(0.84%)
FORTSON CONTRACTING, INC.(0.09%)
IEA, INC (9.39%)
JAGOE-PUBLIC COMPANY ( 10.82%)
OSCAR ORDUNO, INC. (0.23%)
ROADWAY SOLUTIONS, INC.(4.78%)
ROBERTS TRUCKING (1.98%)
RUSSO CORPORATION(0.55%)
DUSTROL, INC.(0.49%)
W.O.E. CONSTRUCTION(4.50%)
TRANSPORT TRUST(0.96%)
RICHMOND HYDROMULCH AND SEEDING, LLC (0.27%)
Contract # 09133204
Totals 29826069.73 1037035.26 19426324.98 65.1

CountyCOLLIN
Highway FM 1378
From 585 SOUTH OF WHITE ROCK CREEK
To NORTH OF WHITE ROCK CREEK
CSJ 1392-01-035
Proj ID BR 2014(872)
Work Type REPL BRIDGE
 
0.526 1788995.75 137040.07 1137474.08 63.5
Work Order 10-09-14
Work Began 08-10-15
Work Completed  
Time Computed 04-07-15
Contract Working Days 300
Addl Days Granted 10
Working Days Charged 240
Percent Time Used 77
Contractor(s)
ACCELERATED CRITICAL PATH, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1392-01-035
BREDA COMPANY, INC.(0.40%)
CROSSROADS, L.P. (0.90%)
D & S ENGINEERING LABS (0.45%)
DUSTROL, INC.(2.56%)
FOUNDATION DRILLERS, INC.(0.91%)
CRAIG OLDEN, INC.(1.77%)
LINDAMOOD DEMOLITION, INC. (1.39%)
MCRYAN HAULING, INC. (1.87%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.32%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.08%)
LONE STAR BARRIER SERVICES, LLC(0.90%)
MARCOM"S MOWING SERVICE, LLC (0.70%)
HOUSTON SAWING & DRILLING(0.17%)
Contract # 07143231
Totals 1788995.75 137040.07 1137474.08 63.5

CountyKAUFMAN
Highway FM 1836
From FM 2515
To FM 90
CSJ 1397-01-030
Proj ID STP 2016(289)
Work Type SHLDR WDN, STR EXT, REMX, SC, PAV MRKS
 
6.905 6141935.93 380942.45 426257.45 6.9
Work Order 01-29-16
Work Began 04-19-16
Work Completed  
Time Computed 04-18-16
Contract Working Days 218
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 28
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 1397-01-030
PEACHTREE CONSTRUCTION, LTD. (1.77%)
S & S BRIDGE PAINTING, INC.(4.51%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.11%)
TRP CONSTRUCTION GROUP, LLC(1.23%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.55%)
DUSTIN ALLEN, INC. (1.46%)
FARR FOUNDATION, INC.(1.51%)
K & S UTILITY CONTRACTORS, INC.(6.21%)
WITHERS CONSTRUCTION, LLC(0.63%)
ALTUS TRAFFIC MANAGEMENT LLC (0.20%)
CAMBRIDGEMOEN LLC(2.28%)
GIBSON & ASSOCIATES, INC.(1.87%)
Contract # 11153024
Totals 6141935.93 380942.45 426257.45 6.9

CountyKAUFMAN
Highway FM 1836
From SH 34
To 0.28 MI EAST OF CR 146
CSJ 1397-01-031
Proj ID C 1397-1-31
Work Type PROVIDE ADDITIONAL PAVED SURFACE
 
4.269 5943147.30 449152.56 451792.56 7.6
Work Order 03-01-16
Work Began 07-18-16
Work Completed  
Time Computed 07-18-16
Contract Working Days 166
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 3
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1397-01-031
ALTUS TRAFFIC MANAGEMENT LLC (0.17%)
ODUM SERVICES, L.P.(1.02%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.55%)
J & M CONTRACTING, COMPANY ( 20.60%)
Contract # 01163240
Totals 5943147.30 449152.56 451792.56 7.6

CountyELLIS
Highway FM 55
From AT LITTLE ONION CREEK
To .
CSJ 1451-01-020
Proj ID BR 2005(274)
Work Type REPLACE BRIDGES AND APPROACHES
 
0.312 2010620.16 74232.96 425790.19 21.1
Work Order 07-24-15
Work Began 02-18-16
Work Completed  
Time Computed 11-21-15
Contract Working Days 340
Addl Days Granted 0
Working Days Charged 113
Percent Time Used 33
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-020
TEXOP CONSTRUCTION (1.10%)
FORTSON CONTRACTING, INC.(2.27%)
SAN-ANN-CO., INC.(0.96%)
USA EROSION, INC.(4.31%)
STRIPING TECHNOLOGY, L.P.(1.50%)
W. W. FOUNDATION DRILLING, LTD.(2.35%)
Contract # 05153220
Totals 2010620.16 74232.96 425790.19 21.1

CountyELLIS
Highway FM 55
From 0.14 MILE SOUTH OF NASH HOWARD RD
To US 77
CSJ 1451-01-023
Proj ID STP 2015(655)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
5.500 4975101.65 246785.66 4553503.82 92.2
Work Order 05-15-15
Work Began 06-29-15
Work Completed  
Time Computed 06-15-15
Contract Working Days 215
Addl Days Granted 25
Working Days Charged 278
Percent Time Used 115
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-023
ALTUS TRAFFIC MANAGEMENT LLC (0.31%)
RAMBO CONTRACTING, INC.(4.29%)
BEAR CREEK CONSTRUCTION, LLC ( 14.22%)
TEXAS ALTERNATIVE GRASSER, INC.(0.62%)
STRIPING TECHNOLOGY, L.P.(0.91%)
SAN-ANN-CO., INC.(0.99%)
FORTSON CONTRACTING, INC.(1.01%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.65%)
SOUTHWEST MAINTENANCE, LTD (0.01%)
Contract # 03153011
Totals 4975101.65 246785.66 4553503.82 92.2

CountyELLIS
Highway FM 55
From SH 34
To 0.14 MI S OF NASH HOWARD RD
CSJ 1451-01-024
Proj ID STP 2014(874)
Work Type GR, BASE, PVMT MKGS, SIGNS
 
5.052 5538628.87 0.00 4805135.22 89.0
Work Order 10-02-14
Work Began 12-01-14
Work Completed  
Time Computed 10-18-14
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 378
Percent Time Used 143
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-024
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(3.86%)
STRIPING TECHNOLOGY, L.P.(0.83%)
SAN-ANN-CO., INC.(1.01%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(0.25%)
FORTSON CONTRACTING, INC.(3.25%)
OLDEN, INC.(5.14%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.49%)
Contract # 07143018
Totals 5538628.87 0.00 4805135.22 89.0

CountyELLIS
Highway FM 55
From AT BIG ONION CREEK
To .
CSJ 1451-01-025
Proj ID BR 1502(533)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.135 1530409.40 0.00 107778.59 7.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-28-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 183
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153020
Totals 1530409.40 0.00 107778.59 7.0

CountyKAUFMAN
Highway FM 1565
From FM 986
To HUNT COUNTY LINE
CSJ 1494-02-008
Proj ID STP 2015(485)
Work Type GR, BASE, ACP OVERLAY, PVMT MKGS
 
1.623 1652146.23 554254.36 1456862.50 88.9
Work Order 03-02-15
Work Began 04-09-15
Work Completed  
Time Computed 03-18-15
Contract Working Days 159
Addl Days Granted 6
Working Days Charged 182
Percent Time Used 110
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1494-02-008
J & M CONTRACTING, COMPANY ( 15.62%)
STRIPING TECHNOLOGY, L.P.(1.25%)
GJ SEEDING, LLC(4.19%)
LONE STAR BARRIER SERVICES, LLC(1.14%)
ALTUS TRAFFIC MANAGEMENT LLC (0.56%)
C & J TREE SERVICE (0.18%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.63%)
Contract # 01153215
Totals 1652146.23 554254.36 1456862.50 88.9