Monthly State Let Construction Report For Dallas District As Of May 10, 2016 Page 7 Of 9

Last Update: Tuesday, May 10, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyROCKWALL
Highway FM 3549
From SH 66
To FM 552
CSJ 1015-01-022
Proj ID STP 2015(590)
Work Type BASE REPAIR, LEVEL UP, OVERLAY
 
2.319 2576274.62 446977.14 2695243.39 99.9
Work Order 03-30-15
Work Began 08-05-15
Work Completed  
Time Computed 04-15-15
Contract Working Days 165
Addl Days Granted 31
Working Days Charged 183
Percent Time Used 93
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 1015-01-022
PEACHTREE CONSTRUCTION, LTD. ( 14.69%)
K & S UTILITY CONTRACTORS, INC.(9.85%)
ALTUS TRAFFIC MANAGEMENT LLC (0.36%)
USA SWPPP INSPECTIONS, INC.(2.61%)
STRIPING TECHNOLOGY, L.P.(1.47%)
BAHENA CONSTRUCTION CO.,INC. (0.28%)
RAMBO CONTRACTING, INC.(2.41%)
Contract # 02153221
Totals 2576274.62 446977.14 2695243.39 99.9

CountyROCKWALL
Highway FM 551
From NORTH OF IH 30
To SH 66
CSJ 1016-01-027
Proj ID STP 2014(766)
Work Type BASE REPAIR, LEVEL UP, OVERLAY
 
2.479 5349450.72 558959.64 2827663.54 52.8
Work Order 08-07-14
Work Began 06-15-15
Work Completed  
Time Computed 02-03-15
Contract Working Days 126
Addl Days Granted 62
Working Days Charged 138
Percent Time Used 73
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1016-01-027
DUSTROL, INC.(4.85%)
PREMIER PAVING, LTD. ( 29.61%)
USA SWPPP INSPECTIONS, INC.(1.91%)
FORTSON CONTRACTING, INC.(1.26%)
STRIPING TECHNOLOGY, L.P.(0.71%)
HAYWOOD BAKER(1.24%)
SYNERGY SIGNS & SERVICES, LLC(0.86%)
BRENDA PRICE TRUCKING(1.08%)
FANNIN TREE FARM, LTD(0.13%)
Contract # 06143232
Totals 5349450.72 558959.64 2827663.54 52.8

CountyROCKWALL
Highway FM 1138
From SH 66
To COLLIN COUNTY LINE
CSJ 1016-03-013
Proj ID STP 1602(216)
Work Type BASE REPAIR, LEVEL UP, OVERLAY
 
1.065 1329420.20 0.00 0.00 0.0
CountyROCKWALL
Highway FM 35
From IH 30
To HUNT COUNTY LINE
CSJ 1017-02-012
Proj ID STP 1602(216)
Work Type MILL, BS REP, OV
 
1.539 627099.96 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1016-03-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163033
Totals 1956520.16 0.00 0.00 0.0

CountyELLIS
Highway FM 85
From IH 45
To FM 1182
CSJ 1050-01-017
Proj ID STP 2016(146)
Work Type ACP OVERLAY, GR, STR, PVMT MKGS
 
8.401 12874396.21 1010692.80 1055537.50 8.1
Work Order 12-21-15
Work Began 03-14-16
Work Completed  
Time Computed 03-14-16
Contract Working Days 490
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 6
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1050-01-017
FARR FOUNDATION, INC.(0.78%)
LONE STAR BARRIER SERVICES, LLC(0.82%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.18%)
SHALOM SERVICES CORPORATION(1.22%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.24%)
WOLFE CONSTRUCTION GROUP, INC. (0.30%)
STRIPING TECHNOLOGY, L.P.(0.81%)
PROJECT 2015, LLC(3.53%)
UNDER CONSTRUCTION INC.(0.00%)
GLL CORPORATION DBA MG TRUCKING(0.01%)
NIXON ENGINEERING(0.00%)
Contract # 10153212
Totals 12874396.21 1010692.80 1055537.50 8.1

CountyELLIS
Highway FM 664
From NORTH OF US 287
To SOUTH OF RED OAK CREEK IN OVILLA
CSJ 1051-01-042
Proj ID STP 2015(654)
Work Type ADD 3 - FOOT PAVED SHOULDERS
 
7.303 11142221.20 446756.13 4368484.31 39.2
Work Order 04-20-15
Work Began 06-22-15
Work Completed  
Time Computed 12-23-15
Contract Working Days 293
Addl Days Granted 0
Working Days Charged 210
Percent Time Used 71
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1051-01-042
BROCK ENVIRONMENTAL SERVICES, LLC(0.31%)
CROSSROADS, L.P. (0.48%)
DUSTROL, INC.(1.95%)
STRIPING TECHNOLOGY, L.P.(0.63%)
PEACHTREE CONSTRUCTION, LTD. ( 33.79%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.89%)
JE CASEY, LLC(1.56%)
SYNERGY SIGNS & SERVICES (0.72%)
OSCAR ORDUNO, INC. (2.36%)
BRENDA PRICE TRUCKING(1.09%)
AAA DRILLING FOUNDATION CO., INC.(0.32%)
FORTSON CONTRACTING, INC.(0.58%)
LONE STAR BARRIER SERVICES, LLC(0.53%)
Contract # 03153213
Totals 11142221.20 446756.13 4368484.31 39.2

CountyELLIS
Highway FM 876
From AT BIG ONION CREEK
To .
CSJ 1051-02-017
Proj ID BR 2015(591)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.255 1721378.55 41740.45 687742.42 39.9
Work Order 04-03-15
Work Began 09-15-15
Work Completed  
Time Computed 09-15-15
Contract Working Days 360
Addl Days Granted 0
Working Days Charged 159
Percent Time Used 44
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 1051-02-017
N-LINE TRAFFIC MAINTENANCE, L.P. (0.93%)
IOWA BRIDGE & CULVERT, LC(3.59%)
STRIPING TECHNOLOGY, L.P.(1.60%)
GJ SEEDING, LLC(5.27%)
FOUNDATION DRILLERS, INC.(3.17%)
FRAIRE"S REBAR, INC(4.42%)
F & K BUILDERS (2.81%)
PEACHTREE CONSTRUCTION, LTD. (6.81%)
CLEMONS TRUCKING (2.17%)
JANEK & WHITTEN CONSTRUCTION INC.(0.43%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(5.70%)
FORTSON CONTRACTING, INC.(1.45%)
Contract # 02153207
Totals 1721378.55 41740.45 687742.42 39.9

CountyTARRANT
Highway IH 30
From 0.5 MILES WEST OF N. FIELDER ROAD
To DALLAS/TARRANT COUNTY LINE
CSJ 1068-02-135
Proj ID C 1068-2-135
Work Type ITS, ETC, SIGNS
 
6.091 6960302.24 63182.02 6429220.59 92.3
CountyDALLAS
Highway IH 30
From TARRANT/DALLAS COUNTY LINE
To SYLVAN AVE.
CSJ 1068-04-147
Proj ID IM 0305(082)
Work Type STR, GR, PVMT, PVMT MKGS, SIGNS, ITS
 
12.664 56121468.07 868079.58 57066415.45 99.9
Work Order 02-28-13
Work Began 03-25-13
Work Completed  
Time Computed 03-16-13
Contract Working Days 728
Addl Days Granted 72
Working Days Charged 905
Percent Time Used 113
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-147
COWTOWN TRAFFIC CONTROL, INC.(0.04%)
THE ANCHOR GROUP, INC. (0.02%)
ANTIGO CONSTRUCTION, INC.(0.02%)
DUSTROL, INC.(0.33%)
DUSTIN ALLEN, INC. (0.41%)
HOUSTON SAWING & DRILLING(0.02%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.09%)
PENHALL COMPANY(0.06%)
STORM WATER MANAGEMENT, INC. (0.13%)
VSTRUCTURAL LLC(0.42%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.12%)
W.O.E. CONSTRUCTION(0.64%)
STRIPING TECHNOLOGY, L.P.(2.08%)
MICA CORPORATION ( 19.67%)
W. W. FOUNDATION DRILLING, LTD.(2.65%)
K & S UTILITY CONTRACTORS, INC.(4.66%)
INDUS CONSTRUCTION, L.P. (0.56%)
PRESSURE CLEANING SERVICE, INC. DBA WATERBLASTING.COM(0.06%)
RAMBO CONTRACTING, INC.(1.19%)
NORTH TEXAS REBAR, LLC (0.00%)
HERDEZ TRUCKING, INC.(0.09%)
J.H. PAINTING COMPANY(0.41%)
MCL CONTRACTING, LLC (0.09%)
CB SERVICES, INC.(0.06%)
VFC, INC (0.11%)
STRIPE-A-ZONE, INC.(1.00%)
Contract # 12123201
Totals 63081770.31 931261.60 63495636.04 99.9

CountyDALLAS
Highway IH 30
From BELTLINE ROAD
To MAC ARTHUR BLVD.
CSJ 1068-04-122
Proj ID C 1068-4-122
Work Type GR, STRS & PAV
 
1.522 24620668.27 0.00 0.00 0.0
CountyDALLAS
Highway IH 30
From BELT LINE RD
To MACARTHUR RD
CSJ 1068-04-137
Proj ID ROW 1068-4-137
Work Type ROW ACQ, UTIL & RELOC
 
0.760 565255.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-16-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 538
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAYDON CENTRAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-122
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153004
Totals 25185923.27 0.00 0.00 0.0

CountyDALLAS
Highway IH 30
From NW 7TH STREET
To BELTLINE ROAD
CSJ 1068-04-148
Proj ID STP 2016(740)MM
Work Type GR, DRN, RET WLS, CONC PAV, SIG, PV MRKS
 
1.011 7991673.30 0.00 51141.28 0.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 380
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-148
ALTUS TRAFFIC MANAGEMENT LLC (0.17%)
W.O.E. CONSTRUCTION(2.42%)
C.T. AND S. METALWORKS, INC. (0.37%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.22%)
FORTSON CONTRACTING, INC.(0.31%)
K & S UTILITY CONTRACTORS, INC.( 12.19%)
MICA CORPORATION (3.52%)
STORM WATER MANAGEMENT, INC. (0.23%)
STRIPE-A-ZONE, INC.(1.02%)
SYNERGY SIGNS & SERVICES (0.36%)
TEXAS BOMANITE (0.05%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.32%)
Contract # 02163225
Totals 7991673.30 0.00 51141.28 0.6

CountyDALLAS
Highway IH 30
From COCKRELL HILL ROAD
To WESTMORELAND RD IN DALLAS
CSJ 1068-04-154
Proj ID C 1068-4-154
Work Type GRADING, PAVEMENT, SIGNS, PVMT MKGS
 
2.704 9814841.51 1193918.22 7035310.67 72.4
Work Order 09-09-14
Work Began 11-11-14
Work Completed  
Time Computed 09-25-14
Contract Working Days 321
Addl Days Granted 0
Working Days Charged 386
Percent Time Used 120
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-154
K & S UTILITY CONTRACTORS, INC.(9.08%)
OSCAR ORDUNO, INC. (4.26%)
STORM WATER MANAGEMENT, INC. (0.29%)
SLATON BROTHERS, INC.(4.57%)
Contract # 07143214
Totals 9814841.51 1193918.22 7035310.67 72.4

CountyKAUFMAN
Highway FM 741
From US 175
To EAST OF FM 548
CSJ 1092-01-017
Proj ID STP 2015(778)
Work Type GR, BASE, ACP OVERLAY, PVMT MKGS
 
7.726 4550316.19 576831.70 4161501.27 91.9
Work Order 03-23-15
Work Began 06-03-15
Work Completed  
Time Computed 04-23-15
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 113
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1092-01-017
ALTUS TRAFFIC MANAGEMENT LLC (0.26%)
TEXAS ENVIRONMENTAL MANAGEMENT SA, INC.(4.68%)
DUSTROL, INC.(4.57%)
MARCOM"S MOWING SERVICE, LLC (1.16%)
J & M CONTRACTING, COMPANY (7.65%)
STRIPING TECHNOLOGY, L.P.(1.43%)
FORTSON CONTRACTING, INC.(0.60%)
C & J TREE SERVICE (0.03%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (4.68%)
Contract # 02153235
Totals 4550316.19 576831.70 4161501.27 91.9

CountyELLIS
Highway FM 875
From AT WAXAHACHIE CREEK
To .
CSJ 1159-01-022
Proj ID BR 2013(604)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.471 3724841.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-13-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 467
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 1159-01-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153025
Totals 3724841.00 0.00 0.00 0.0

CountyELLIS
Highway FM 879
From AT BRANCH OF MUSTANG CREEK
To .
CSJ 1159-02-031
Proj ID BR 2013(832)
Work Type REPLACE BR & APPRS
 
0.134 889807.76 0.00 935140.21 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-24-13
Work Began 01-15-14
Work Completed 04-11-16
Time Computed 12-23-13
Contract Working Days 245
Addl Days Granted 181
Working Days Charged 426
Percent Time Used 100
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1159-02-031
FORTSON CONTRACTING, INC.(2.52%)
HOUSTON SAWING & DRILLING(0.33%)
MCL CONTRACTING, LLC (1.05%)
ALTUS TRAFFIC MANAGEMENT LLC (1.05%)
PEACHTREE CONSTRUCTION, LTD. (5.55%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.38%)
STORM WATER MANAGEMENT, INC. (1.03%)
STRIPING TECHNOLOGY, L.P.(1.46%)
W.O.E. CONSTRUCTION(0.13%)
MCL CONTRACTING, LLC (0.23%)
WOLFE CONSTRUCTION GROUP, INC. (1.18%)
SOUTHEAST GRINDING & GROOVING, LLC (0.56%)
Contract # 07133013
Totals 889807.76 0.00 935140.21 100.0

CountyELLIS
Highway FM 879
From 2.1 MILES WEST OF IKE RD
To 0.3 MILE WEST OF FM 1722
CSJ 1159-02-032
Proj ID STP 1502(328)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
6.667 9549753.04 321978.36 2123214.63 22.2
Work Order 07-31-15
Work Began 09-03-15
Work Completed  
Time Computed 07-31-15
Contract Working Days 315
Addl Days Granted 0
Working Days Charged 176
Percent Time Used 55
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1159-02-032
CROSS ROADS, L.P.(0.38%)
BROCK ENVIRONMENTAL SERVICES, LLC(0.19%)
ACU CONSTRUCTION LLC (1.24%)
STRIPING TECHNOLOGY, L.P.(0.61%)
SYNERGY SIGNS & SERVICES (0.28%)
FORTSON CONTRACTING, INC.(1.62%)
NORTH EASTERN PAVERS (4.90%)
PEACHTREE CONSTRUCTION, LTD. ( 13.21%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (4.95%)
HAYWARD BAKER, INC.(0.67%)
BRENDA PRICE TRUCKING(1.44%)
Contract # 06153225
Totals 9549753.04 321978.36 2123214.63 22.2

CountyELLIS
Highway FM 984
From AT DRAW, 1.7 MI SOUTH OF SH 34
To .
CSJ 1211-01-018
Proj ID BR 2015(483)
Work Type REPL BR AND APPR
 
0.117 879623.40 1500.00 28251.71 3.2
CountyELLIS
Highway FM 984
From AT ONION CREEK RELIEF #1 AND #2
To .
CSJ 1211-01-019
Proj ID BR 2015(484)
Work Type REPL BR
 
0.156 1453823.50 74437.30 263358.80 18.1
Work Order 03-02-15
Work Began 02-25-16
Work Completed  
Time Computed 02-25-16
Contract Working Days 379
Addl Days Granted 0
Working Days Charged 44
Percent Time Used 11
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 1211-01-018
FORTSON CONTRACTING, INC.(2.16%)
USA EROSION, INC.(3.94%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.48%)
STRIPING TECHNOLOGY, L.P.(1.23%)
Contract # 01153012
Totals 2333446.90 75937.30 291610.51 12.4

CountyKAUFMAN
Highway FM 1388
From FM 148
To US 175
CSJ 1217-03-019
Proj ID STP 2016(360)
Work Type GR, BASE, ACP OVERLAY, PVMT MKGS
 
12.030 17608683.44 1443638.20 1444443.20 8.2
CountyKAUFMAN
Highway FM 1388
From AT KINGS CREEK RELIEF #2
To .
CSJ 1217-03-020
Proj ID BR 2016(361)
Work Type REPLACE BRIDGE
 
0.495 4432389.14 0.00 0.00 0.0
Work Order 01-29-16
Work Began 04-11-16
Work Completed  
Time Computed 04-11-16
Contract Working Days 580
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 4
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1217-03-019
ALTUS TRAFFIC MANAGEMENT LLC (0.13%)
SOUTHWEST CONSTRUCTION SERVICES(0.39%)
K & S UTILITY CONTRACTORS, INC.(9.31%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.72%)
A-CORE, INC. (0.02%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(0.05%)
PEACHTREE CONSTRUCTION, LTD. (4.40%)
INDUS CONSTRUCTION, L.P. (0.07%)
SOUTHERN CROSS CONTRACTORS, LLC(0.08%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(5.40%)
SYNERGY SIGNS & SERVICES, LLC(0.39%)
FARR FOUNDATION, INC.(0.56%)
FORTSON CONTRACTING, INC.(0.74%)
TRP CONSTRUCTION GROUP, LLC(0.60%)
HERDEZ TRUCKING, INC.(2.17%)
RAMBO CONTRACTING, INC.(4.73%)
Contract # 12153205
Totals 22041072.58 1443638.20 1444443.20 6.5

CountyNAVARRO
Highway FM 1126
From AT CHAMBERS CREEK, SW OF IH 45
To .
CSJ 1289-01-029
Proj ID BR 1602(046)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.890 6714487.74 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 386
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1289-01-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163237
Totals 6714487.74 0.00 0.00 0.0

CountyDENTON
Highway FM 1171
From WEST OF US 377
To WEST OF SHILOH RD
CSJ 1311-01-034
Proj ID C 1311-1-34
Work Type GR, STRS, BASE, CRCP, PVMT MKGS, SIGNS
 
7.011 45721253.16 1908195.61 38872195.02 85.0
Work Order 06-05-13
Work Began 06-02-14
Work Completed  
Time Computed 03-02-14
Contract Working Days 693
Addl Days Granted 0
Working Days Charged 475
Percent Time Used 68
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1311-01-034
BREDA COMPANY, INC.(0.96%)
BUYERS BARRICADES, INC.(0.20%)
CINTEREX US, INC.(1.17%)
CLLA GROUP, LLC(9.39%)
DUSTROL, INC.(0.30%)
INTEGRATED ROADWAY SERVICES, INC.(2.34%)
JAGOE-PUBLIC COMPANY ( 14.10%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.74%)
THELIN RECYCLING COMPANY, L.P. (0.16%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.10%)
W.O.E. CONSTRUCTION(0.28%)
WYLIE DRILLING & DRAINAGE, INC.(0.83%)
VENUS CONSTRUCTION (7.23%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.35%)
SLATON BROTHERS, INC.(0.58%)
CB SERVICES, INC.(0.10%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.07%)
LLOYD D. NABORS DEMOLITION LLC (0.12%)
STORM WATER MANAGEMENT, INC. (0.07%)
THE LANE CONSTRUCTION CORPORATION(0.93%)
Contract # 03133002
Totals 45721253.16 1908195.61 38872195.02 85.0

CountyDENTON
Highway FM 1171
From ON CORPS OF ENGINEERS PROPERTY
To NEAR WHITE'S BRANCH
CSJ 1311-01-053
Proj ID C 1311-1-53
Work Type TREES AND PLANTS
 
0.001 148908.50 0.00 61596.76 41.3
CountyDENTON
Highway FM 2499
From FM 2181
To HICKORY CREEK
CSJ 2681-01-022
Proj ID NH 1502(094)
Work Type LANDSCAPE DEVELOPMENT
 
1.112 299148.05 0.00 277336.91 92.7
Work Order 07-20-15
Work Began 08-04-15
Work Completed  
Time Computed 08-04-15
Contract Working Days 60
Addl Days Granted 2
Working Days Charged 34
Percent Time Used 54
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2681-01-022
ALTUS TRAFFIC MANAGEMENT LLC (0.85%)
AMAYA UTILITY(0.56%)
QUICK SET CONCRETE, INC. (5.50%)
Contract # 05153018
Totals 448056.55 0.00 338933.67 75.6

CountyDENTON
Highway FM 1385
From US 380
To APPROX. 2 MILES NORTH OF FM 428
CSJ 1315-01-025
Proj ID STP 1402(028)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
7.588 9063184.19 472702.37 6137179.39 67.7
Work Order 12-10-14
Work Began 07-10-15
Work Completed  
Time Computed 06-08-15
Contract Working Days 378
Addl Days Granted 0
Working Days Charged 207
Percent Time Used 54
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1315-01-025
ALTUS TRAFFIC MANAGEMENT LLC (0.54%)
ASHLAR CONTRACTING COMPANY (8.41%)
SAMMY SMALLWOOD COMPANY(0.61%)
STRIPING TECHNOLOGY, L.P.(1.77%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(7.84%)
W.S. CONSTRUCTION COMPANY(6.71%)
JM YANEZ CONSTRUCTION(8.03%)
Contract # 09143208
Totals 9063184.19 472702.37 6137179.39 67.7

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9