Monthly State Let Construction Report For Dallas District As Of Mar 10, 2015 Page 7 Of 10

Last Update: Wednesday, March 11, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDALLAS
Highway CS
From S MARSALIS AVE AT FIVEMILE CREEK
To .
CSJ 0918-45-761
Proj ID BR 2007(306)
Work Type REPL BR & APPRS
 
0.077 2688948.21 6036.66 10264.66 0.3
CountyDALLAS
Highway CS
From S MARSALIS AVE AT FIVEMILE CREEK
To .
CSJ 0918-47-085
Proj ID RW 918-47-85
Work Type ADJUSTMENT OF UTILITIES
 
0.090 255486.60 0.00 0.00 0.0
Work Order 09-22-14
Work Began 00-00-00
Work Completed  
Time Computed 11-21-14
Contract Working Days 353
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 10
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-45-761
ALTUS TRAFFIC MANAGEMENT LLC (0.97%)
BROCK ENVIRONMENTAL, LLC (0.53%)
ATS DRILLING, INC. (7.00%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(1.19%)
Contract # 06143014
Totals 2944434.81 6036.66 10264.66 0.3

CountyDALLAS
Highway CS
From GALATYN PARKWAY EXTENSION FROM US75
To PALISADES BLVD IN RICHARDSON
CSJ 0918-45-821
Proj ID CM 2007(892)
Work Type ROADWAY EXTENSION
 
0.169 2999312.68 0.00 3229167.00 100.0
CountyDALLAS
Highway VA
From GALATYN PARKWAY EXTENSION FROM US75
To PALISADES BLVD IN RICHARDSON
CSJ 0918-47-009
Proj ID CC 918-47-9
Work Type ROW UTL. ADJ.
 
0.027 63229.80 0.00 84756.54 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-09-11
Work Began 01-11-12
Work Completed 11-20-14
Time Computed 01-03-12
Contract Working Days 270
Addl Days Granted 88
Working Days Charged 358
Percent Time Used 100
Contractor(s)
REBCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-45-821
COWTOWN TRAFFIC CONTROL, INC.(0.39%)
NORTH TEXAS CONTRACTING, INC.(6.01%)
CONCRETE CUTTING BY BOND (0.18%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.48%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.17%)
SCOTT DERR PAINTING CO, LLC(0.37%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.40%)
INTEGRATED ROADWAY SERVICES, INC.(5.23%)
ROAD MASTER STRIPING LLC (0.77%)
WEST TEXAS REBAR PLACERS INC.(1.07%)
HOUSTON SAWING & DRILLING(0.07%)
DOWN UNDER CONSTRUCTION(0.04%)
SYNERGY SIGNS & SERVICES (0.08%)
Contract # 09113011
Totals 3062542.48 0.00 3313923.54 100.0

CountyDALLAS
Highway CS
From ON PLEASANT RUN RD, E OF SUNRISE RD
To WEST OF IH 45
CSJ 0918-45-844
Proj ID HP 2010(854)
Work Type GRD, STR, PVMT, SIGNS
 
0.759 7719831.64 1437.17 7786322.21 99.9
Work Order 04-03-13
Work Began 04-22-13
Work Completed  
Time Computed 04-22-13
Contract Working Days 270
Addl Days Granted 7
Working Days Charged 277
Percent Time Used 100
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-45-844
MCL CONTRACTING, LLC (1.04%)
FOUNDATION DRILLERS, INC.(1.55%)
S & S BRIDGE PAINTING, INC.(0.12%)
HOUSTON SAWING & DRILLING(0.07%)
STORM WATER MANAGEMENT, INC. (0.51%)
IOWA BRIDGE & CULVERT, LC(0.32%)
COWTOWN TRAFFIC CONTROL, INC.(0.19%)
STRIPING TECHNOLOGY, L.P.(1.07%)
GREAT WESTERN ERECTORS (0.10%)
PEACHTREE CONSTRUCTION, LTD. (8.07%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.62%)
COWBOY TRUCKING(1.80%)
TEX OP CONSTRUCTION, LP(0.20%)
W.O.E. CONSTRUCTION(0.03%)
TWS ENVIRONMENTAL, LLC (0.22%)
INTEGRATED ROADWAY SERVICES, INC.(2.35%)
PLACIDO CONSTRUCTION COMPANY (0.46%)
LONE STAR HIGHWAY PRODUCTS, INC. (5.42%)
Contract # 12123014
Totals 7719831.64 1437.17 7786322.21 99.9

CountyDALLAS
Highway CS
From ON WHITLOCK RD, FROM IH 35E
To OLD DENTON RD IN CARROLLTON
CSJ 0918-45-864
Proj ID STP 2009(860)MM
Work Type GR, STRS & SURF
 
0.505 3063573.24 10142.00 10142.00 0.3
CountyDALLAS
Highway CS
From ON WHITLOCK RD, FROM IH 35E
To OLD DENTON RD IN CARROLLTON
CSJ 0918-47-116
Proj ID RW 918-47-116
Work Type ADJUSTMENT OF UTILITIES IN CONSTRUC
 
0.505 372163.90 0.00 0.00 0.0
Work Order 09-11-14
Work Began 00-00-00
Work Completed  
Time Computed 12-09-14
Contract Working Days 276
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TISEO PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0918-45-864
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143222
Totals 3435737.14 10142.00 10142.00 0.2

CountyDENTON
Highway VA
From VARIOUS LOCATIONS ON STATE HIGHWAYS
To IN DENTON COUNTY
CSJ 0918-46-263
Proj ID STP 2013(385)
Work Type CONSTRUCT CURB RAMPS
 
0.001 1930243.96 0.00 2068968.74 99.9
Work Order 05-29-13
Work Began 08-07-13
Work Completed  
Time Computed 06-14-13
Contract Working Days 288
Addl Days Granted 0
Working Days Charged 332
Percent Time Used 115
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-46-263
BUYERS BARRICADES, INC.(2.43%)
A-STAR MASONRY AND STUCCO, LLC (5.18%)
DURABLE SPECIALTIES, INC.(7.61%)
TI-ZACK CONCRETE, INC. ( 53.70%)
BTA SERVICES, LTD. (2.35%)
COWBOY TRUCKING(1.86%)
STAR OPERATIONS, INC.(4.73%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.23%)
LONE STAR HIGHWAY PRODUCTS, INC. (2.21%)
MEL"S ELECTRIC SERVICE, INC. (5.34%)
GARZA CONCRETE CONSTRUCTION(4.62%)
Contract # 02133011
Totals 1930243.96 0.00 2068968.74 99.9

CountyDALLAS
Highway VA
From VARIOUS LOCATIONS ON STATE HIGHWAYS
To IN DALLAS COUNTY
CSJ 0918-47-052
Proj ID STP 1102(553)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2270944.30 128903.00 1250106.00 55.0
Work Order 07-25-14
Work Began 09-02-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 244
Addl Days Granted 0
Working Days Charged 114
Percent Time Used 46
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-052
CLASSIC TEJAS CONSTRUCTION, INC. ( 17.31%)
Contract # 06143039
Totals 2270944.30 128903.00 1250106.00 55.0

CountyDALLAS
Highway VA
From VARIOUS LOCATIONS ON STATE HIGHWAYS
To IN DALLAS COUNTY
CSJ 0918-47-100
Proj ID NH 2015(653)
Work Type CONSTRUCT CURB RAMPS
 
0.001 3464886.46 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 315
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-100
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153224
Totals 3464886.46 0.00 0.00 0.0

CountyCOLLIN
Highway FM 981
From AT INDIAN CREEK AND RELIEF #2
To .
CSJ 1012-03-017
Proj ID BR 2015(067)
Work Type REPL BRIDGE
 
0.261 1828296.80 114764.32 114764.32 6.2
Work Order 10-17-14
Work Began 02-16-15
Work Completed  
Time Computed 12-16-14
Contract Working Days 141
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 4
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1012-03-017
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.50%)
ACTION COMMERCIAL SERVICES, L.L.C. (0.31%)
FORTSON CONTRACTING, INC.(1.72%)
MCL CONTRACTING, LLC (0.72%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(3.04%)
SCOTT DERR PAINTING CO, LLC(0.13%)
SYNERGY SIGNS & SERVICES, LLC(0.15%)
TEX OP CONSTRUCTION, LP(0.97%)
TEXAS SHAFTS, INC. (8.73%)
MCL CONTRACTING, LLC (0.28%)
USA SWPPP INSPECTIONS, INC.(2.46%)
Contract # 08143032
Totals 1828296.80 114764.32 114764.32 6.2

CountyCOLLIN
Highway FM 546
From WEST OF THE CROSSINGS RD
To FM 982
CSJ 1013-01-028
Proj ID STP 1402(180)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
5.051 5997170.81 605132.35 1497371.37 24.9
Work Order 09-15-14
Work Began 12-01-14
Work Completed  
Time Computed 12-01-14
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 20
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1013-01-028
TOTAL HIGHWAY MAINTENANCE, LLC (1.22%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(0.43%)
FARR FOUNDATION, INC.(3.02%)
EROSION CONTROL MANAGEMENT SERVICES(0.36%)
K & S UTILITY CONTRACTORS, INC.( 21.42%)
MARCOM"S MOWING SERVICE, LLC (3.13%)
ACU CONSTRUCTION LLC (0.45%)
GOLDEN TREE MAINTENANCE(0.13%)
Contract # 07143245
Totals 5997170.81 605132.35 1497371.37 24.9

CountyROCKWALL
Highway FM 740
From FM 549 / FM 550 INTERSECTION
To FM 1140 NORTH IN HEATH
CSJ 1014-03-049
Proj ID C 1014-3-49
Work Type GRADING, STRUCTURES, DRAINAGE, & PVMT
 
1.856 12967453.42 2515.47 170871.82 1.3
Work Order 11-14-13
Work Began 00-00-00
Work Completed  
Time Computed 08-11-14
Contract Working Days 412
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1014-03-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08133209
Totals 12967453.42 2515.47 170871.82 1.3

CountyROCKWALL
Highway FM 3549
From SH 66
To FM 552
CSJ 1015-01-022
Proj ID STP 2015(590)
Work Type BASE REPAIR, LEVEL UP, OVERLAY
 
2.319 2576274.62 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 1015-01-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153221
Totals 2576274.62 0.00 0.00 0.0

CountyROCKWALL
Highway FM 551
From NORTH OF IH 30
To SH 66
CSJ 1016-01-027
Proj ID STP 2014(766)
Work Type BASE REPAIR, LEVEL UP, OVERLAY
 
2.479 5349450.72 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-07-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 126
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1016-01-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143232
Totals 5349450.72 0.00 0.00 0.0

CountyCOLLIN
Highway FM 1138
From ROCKWALL COUNTY LINE
To FM 6 IN NEVADA
CSJ 1016-02-017
Proj ID STP 2014(006)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
4.216 3337173.45 0.00 2887521.64 87.5
Work Order 12-04-13
Work Began 03-12-14
Work Completed  
Time Computed 02-02-14
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 195
Percent Time Used 121
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1016-02-017
FORTSON CONTRACTING, INC.(0.17%)
ENVIRONMENTAL STANDARDS, INC.(3.91%)
ALTUS TRAFFIC MANAGEMENT LLC (0.37%)
DUSTROL, INC.(2.74%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.85%)
J & M CONTRACTING, COMPANY ( 19.06%)
MARCOM"S MOWING SERVICE, LLC (1.36%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(3.49%)
Contract # 09133215
Totals 3337173.45 0.00 2887521.64 87.5

CountyDALLAS
Highway FM 1382
From NEW CLARK ROAD
To WEST OF STRAUS RD IN CEDAR HILL
CSJ 1047-03-063
Proj ID C 1047-3-63
Work Type INTERSECTION IMPROVEMENTS
 
0.493 1893193.60 19216.27 1302770.56 68.8
Work Order 01-06-14
Work Began 02-26-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 300
Addl Days Granted 1
Working Days Charged 256
Percent Time Used 85
Contractor(s)
CD BUILDERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1047-03-063
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(7.09%)
ODUM SERVICES, L.P.(0.39%)
SIEMENS INDUSTRY, INC. (2.95%)
USA EROSION, INC.(1.02%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.17%)
MELS ELECTRIC, L.P.(2.98%)
ALLIANCE GEOTECHNICAL GROUP(0.20%)
GLL CORPORATION DBA MG TRUCKING(3.30%)
W.O.E. CONSTRUCTION(0.82%)
Contract # 11133021
Totals 1893193.60 19216.27 1302770.56 68.8

CountyELLIS
Highway FM 664
From NORTH OF US 287
To SOUTH OF RED OAK CREEK IN OVILLA
CSJ 1051-01-042
Proj ID STP 2015(654)
Work Type ADD 3 - FOOT PAVED SHOULDERS
 
7.303 11142221.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 293
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1051-01-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153213
Totals 11142221.20 0.00 0.00 0.0

CountyELLIS
Highway FM 876
From AT BIG ONION CREEK
To .
CSJ 1051-02-017
Proj ID BR 2015(591)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.255 1721378.55 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 360
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 1051-02-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153207
Totals 1721378.55 0.00 0.00 0.0

CountyTARRANT
Highway IH 30
From 0.5 MILES WEST OF N. FIELDER ROAD
To DALLAS/TARRANT COUNTY LINE
CSJ 1068-02-135
Proj ID C 1068-2-135
Work Type ITS, ETC, SIGNS
 
6.091 6960302.24 15000.00 5140647.68 73.8
CountyDALLAS
Highway IH 30
From TARRANT/DALLAS COUNTY LINE
To SYLVAN AVE.
CSJ 1068-04-147
Proj ID IM 0305(082)
Work Type STR, GR, PVMT, PVMT MKGS, SIGNS, ITS
 
12.664 56121468.07 1307729.07 40394566.79 71.9
Work Order 02-28-13
Work Began 03-25-13
Work Completed  
Time Computed 03-16-13
Contract Working Days 728
Addl Days Granted 0
Working Days Charged 561
Percent Time Used 77
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-147
COWTOWN TRAFFIC CONTROL, INC.(0.04%)
THE ANCHOR GROUP, INC. (0.02%)
ANTIGO CONSTRUCTION, INC.(0.02%)
DUSTROL, INC.(0.33%)
DUSTIN ALLEN, INC. (0.41%)
HOUSTON SAWING & DRILLING(0.02%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.09%)
PENHALL COMPANY(0.06%)
STORM WATER MANAGEMENT, INC. (0.13%)
VSTRUCTURAL LLC(0.42%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.12%)
W.O.E. CONSTRUCTION(0.64%)
STRIPING TECHNOLOGY, L.P.(2.08%)
MICA CORPORATION ( 19.67%)
W. W. FOUNDATION DRILLING, LTD.(2.65%)
K & S UTILITY CONTRACTORS, INC.(4.66%)
INDUS CONSTRUCTION, L.P. (0.56%)
PRESSURE CLEANING SERVICE, INC. DBA WATERBLASTING.COM(0.06%)
RAMBO CONTRACTING, INC.(1.19%)
NORTH TEXAS REBAR, LLC (0.00%)
HERDEZ TRUCKING, INC.(0.09%)
J.H. PAINTING COMPANY(0.41%)
MCL CONTRACTING, LLC (0.09%)
Contract # 12123201
Totals 63081770.31 1322729.07 45535214.47 72.1

CountyDALLAS
Highway IH 30
From BELT LINE RD. IN GRAND PRAIRIE
To N.E. 15TH ST.
CSJ 1068-04-142
Proj ID STP 2011(706)MM
Work Type GR, STR, PVMT, SIGNS, BUILDING
 
0.767 7282375.53 85313.11 9620575.01 100.0
CountyDALLAS
Highway IH 30
From BELT LINE RD.
To MACARTHUR BLVD.
CSJ 1068-04-145
Proj ID C 1068-4-145
Work Type GR, STR, PVMT, SIGNS
 
2.060 7497722.23 49970.00 7581597.40 100.0
Work Order 02-15-11
Work Began 04-22-11
Work Completed 12-22-14
Time Computed 04-16-11
Contract Working Days 491
Addl Days Granted 219
Working Days Charged 686
Percent Time Used 96
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-142
DUSTROL, INC. (ROANOKE)(0.09%)
FORTSON CONTRACTING, INC.(0.81%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(5.65%)
BUYERS BARRICADES, INC.(0.04%)
THE ANCHOR GROUP, INC. (0.38%)
CONCRETE CUTTING BY BOND (0.06%)
COWTOWN TRAFFIC CONTROL, INC.(0.19%)
FARR FOUNDATION, INC.(6.20%)
GK CONSTRUCTION, LLC (0.66%)
C.T. AND S. METALWORKS, INC. (1.72%)
CENTRAL NORTH CONSTRUCTION, LLC(2.17%)
STAR OPERATIONS, INC.(3.43%)
MCMAHON CONTRACTING, L.P.( 20.81%)
STRIPE-A-ZONE, INC.(0.61%)
ALLIANCE GEOTECHNICAL GROUP(0.15%)
PIBURN & CARSON, LLC (0.50%)
FOUNDATION DRILLERS, INC.(0.15%)
COWBOY TRUCKING(0.13%)
RMI WORLDWIDE, LLC (0.05%)
LONE STAR HIGHWAY PRODUCTS, INC. (2.50%)
USA SWPPP INSPECTIONS, INC.(0.45%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.02%)
SUPREME SAWING AND SEALING (0.24%)
J.L. STEEL REINFORCING, LLC(0.09%)
W.O.E. CONSTRUCTION(0.05%)
L & E HART ENTERPRISES, INC. (2.20%)
STORM WATER MANAGEMENT, INC. (0.03%)
SCOTT DERR PAINTING CO, LLC(0.12%)
STRAIGHT LINE SAWING & SEALING (0.14%)
UTILITY AND ENVIRONMENTAL SERVICES, INCORPORATED (0.10%)
Contract # 12103201
Totals 14780097.76 135283.11 17202172.41 100.0

CountyDALLAS
Highway IH 30
From COCKRELL HILL ROAD
To WESTMORELAND RD IN DALLAS
CSJ 1068-04-154
Proj ID C 1068-4-154
Work Type GRADING, PAVEMENT, SIGNS, PVMT MKGS
 
2.704 9814841.51 551337.60 1325008.68 13.5
Work Order 09-09-14
Work Began 11-11-14
Work Completed  
Time Computed 09-25-14
Contract Working Days 321
Addl Days Granted 0
Working Days Charged 90
Percent Time Used 28
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-154
K & S UTILITY CONTRACTORS, INC.(9.08%)
OSCAR ORDUNO, INC. (4.26%)
STORM WATER MANAGEMENT, INC. (0.29%)
Contract # 07143214
Totals 9814841.51 551337.60 1325008.68 13.5

CountyKAUFMAN
Highway FM 740
From BUFFALO CREEK
To '
CSJ 1091-01-016
Proj ID STP 2009(601)ES
Work Type REPL BR & APPRS
 
0.323 2856520.65 0.00 3905954.84 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-28-09
Work Began 02-16-10
Work Completed 12-10-14
Time Computed 10-14-09
Contract Working Days 389
Addl Days Granted 101
Working Days Charged 525
Percent Time Used 107
Contractor(s)
DOUGHTIE CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1091-01-016
BTA SERVICES, LTD. (0.58%)
PREMIER PAVING, LTD. ( 10.17%)
COWTOWN TRAFFIC CONTROL, INC.(0.30%)
CENTRAL TEXAS ENVIRONMENTAL SERVICES, LLC(0.42%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.98%)
D & E CONTRACTORS(8.87%)
HOLES INCORPORATED (0.98%)
TEX OP CONSTRUCTION, LP(0.35%)
JUST GROOVING, LTD.(0.19%)
LONE STAR HIGHWAY PRODUCTS, INC. (3.67%)
CLEMONS TRUCKING (0.36%)
SOUTHWEST CRUSHING, LLC(0.36%)
BREDA COMPANY, INC.(0.24%)
INTERSTATE SAFETY SYSTEMS, INC.(3.92%)
WEBBER BARRIER SERVICES, INC.(3.07%)
ODUM SERVICES, L.P.(0.74%)
Contract # 07093216
Totals 2856520.65 0.00 3905954.84 100.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10