Monthly State Let Construction Report For Dallas District As Of Dec 10, 2014 Page 7 Of 9

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCOLLIN
Highway FM 546
From WEST OF THE CROSSINGS RD
To FM 982
CSJ 1013-01-028
Proj ID STP 1402(180)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
5.051 5997170.81 49100.00 49100.00 0.8
Work Order 09-15-14
Work Began 12-01-14
Work Completed  
Time Computed 10-01-14
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1013-01-028
TOTAL HIGHWAY MAINTENANCE, LLC (1.22%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(0.43%)
FARR FOUNDATION, INC.(3.02%)
EROSION CONTROL MANAGEMENT SERVICES(0.36%)
K & S UTILITY CONTRACTORS, INC.( 21.42%)
MARCOM"S MOWING SERVICE, LLC (3.13%)
ACU CONSTRUCTION LLC (0.45%)
Contract # 07143245
Totals 5997170.81 49100.00 49100.00 0.8

CountyROCKWALL
Highway FM 740
From FM 549 / FM 550 INTERSECTION
To FM 1140 NORTH IN HEATH
CSJ 1014-03-049
Proj ID C 1014-3-49
Work Type GRADING, STRUCTURES, DRAINAGE, & PVMT
 
1.856 12967453.42 119654.00 119654.00 0.9
Work Order 11-14-13
Work Began 00-00-00
Work Completed  
Time Computed 08-11-14
Contract Working Days 412
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1014-03-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08133209
Totals 12967453.42 119654.00 119654.00 0.9

CountyROCKWALL
Highway FM 551
From NORTH OF IH 30
To SH 66
CSJ 1016-01-027
Proj ID STP 2014(766)
Work Type BASE REPAIR, LEVEL UP, OVERLAY
 
2.479 5349450.72 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-07-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 126
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1016-01-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143232
Totals 5349450.72 0.00 0.00 0.0

CountyCOLLIN
Highway FM 1138
From ROCKWALL COUNTY LINE
To FM 6 IN NEVADA
CSJ 1016-02-017
Proj ID STP 2014(006)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
4.216 3337173.45 232696.90 2870580.67 86.8
Work Order 12-04-13
Work Began 03-12-14
Work Completed  
Time Computed 02-02-14
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 187
Percent Time Used 116
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1016-02-017
FORTSON CONTRACTING, INC.(0.17%)
ENVIRONMENTAL STANDARDS, INC.(3.91%)
ALTUS TRAFFIC MANAGEMENT LLC (0.37%)
DUSTROL, INC.(2.74%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.85%)
J & M CONTRACTING, COMPANY ( 19.06%)
MARCOM"S MOWING SERVICE, LLC (1.36%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(3.49%)
Contract # 09133215
Totals 3337173.45 232696.90 2870580.67 86.8

CountyDALLAS
Highway FM 1382
From NEW CLARK ROAD
To WEST OF STRAUS RD IN CEDAR HILL
CSJ 1047-03-063
Proj ID C 1047-3-63
Work Type INTERSECTION IMPROVEMENTS
 
0.493 1893193.60 33870.99 1031135.73 54.4
Work Order 01-06-14
Work Began 02-26-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 300
Addl Days Granted 1
Working Days Charged 196
Percent Time Used 65
Contractor(s)
CD BUILDERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1047-03-063
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(7.09%)
ODUM SERVICES, L.P.(0.90%)
SIEMENS INDUSTRY, INC. (2.95%)
USA EROSION, INC.(1.02%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.17%)
MELS ELECTRIC, L.P.(2.98%)
ALLIANCE GEOTECHNICAL GROUP(0.20%)
GLL CORPORATION DBA MG TRUCKING(3.30%)
W.O.E. CONSTRUCTION(0.82%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(1.78%)
Contract # 11133021
Totals 1893193.60 33870.99 1031135.73 54.4

CountyTARRANT
Highway IH 30
From 0.5 MILES WEST OF N. FIELDER ROAD
To DALLAS/TARRANT COUNTY LINE
CSJ 1068-02-135
Proj ID C 1068-2-135
Work Type ITS, ETC, SIGNS
 
6.091 6960302.24 0.00 5123125.85 73.6
CountyDALLAS
Highway IH 30
From TARRANT/DALLAS COUNTY LINE
To SYLVAN AVE.
CSJ 1068-04-147
Proj ID IM 0305(082)
Work Type STR, GR, PVMT, PVMT MKGS, SIGNS, ITS
 
12.664 56121468.07 1113798.32 36493782.04 65.0
Work Order 02-28-13
Work Began 03-25-13
Work Completed  
Time Computed 03-16-13
Contract Working Days 728
Addl Days Granted 0
Working Days Charged 491
Percent Time Used 67
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-147
COWTOWN TRAFFIC CONTROL, INC.(0.04%)
THE ANCHOR GROUP, INC. (0.02%)
ANTIGO CONSTRUCTION, INC.(0.02%)
DUSTROL, INC.(0.33%)
DUSTIN ALLEN, INC. (0.41%)
HOUSTON SAWING & DRILLING(0.02%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.09%)
PENHALL COMPANY(0.06%)
STORM WATER MANAGEMENT, INC. (0.13%)
VSTRUCTURAL LLC(0.42%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.12%)
W.O.E. CONSTRUCTION(0.64%)
STRIPING TECHNOLOGY, L.P.(2.08%)
MICA CORPORATION ( 19.67%)
W. W. FOUNDATION DRILLING, LTD.(2.65%)
K & S UTILITY CONTRACTORS, INC.(4.66%)
INDUS CONSTRUCTION, L.P. (0.56%)
PRESSURE CLEANING SERVICE, INC. DBA WATERBLASTING.COM(0.06%)
RAMBO CONTRACTING, INC.(1.19%)
NORTH TEXAS REBAR, LLC (0.13%)
HERDEZ TRUCKING, INC.(0.09%)
J.H. PAINTING COMPANY(0.41%)
Contract # 12123201
Totals 63081770.31 1113798.32 41616907.89 65.9

CountyDALLAS
Highway IH 30
From BELT LINE RD. IN GRAND PRAIRIE
To N.E. 15TH ST.
CSJ 1068-04-142
Proj ID STP 2011(706)MM
Work Type GR, STR, PVMT, SIGNS, BUILDING
 
0.767 7282375.53 4449.18 9344268.46 99.9
CountyDALLAS
Highway IH 30
From BELT LINE RD.
To MACARTHUR BLVD.
CSJ 1068-04-145
Proj ID C 1068-4-145
Work Type GR, STR, PVMT, SIGNS
 
2.060 7497722.23 5333.24 7531627.40 99.9
Work Order 02-15-11
Work Began 04-22-11
Work Completed  
Time Computed 04-16-11
Contract Working Days 491
Addl Days Granted 219
Working Days Charged 686
Percent Time Used 96
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-142
DUSTROL, INC. (ROANOKE)(0.09%)
FORTSON CONTRACTING, INC.(0.81%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(5.65%)
BUYERS BARRICADES, INC.(0.04%)
THE ANCHOR GROUP, INC. (0.38%)
CONCRETE CUTTING BY BOND (0.06%)
COWTOWN TRAFFIC CONTROL, INC.(0.19%)
FARR FOUNDATION, INC.(6.20%)
GK CONSTRUCTION, LLC (0.66%)
C.T. AND S. METALWORKS, INC. (1.72%)
CENTRAL NORTH CONSTRUCTION, LLC(2.17%)
STAR OPERATIONS, INC.(3.43%)
MCMAHON CONTRACTING, L.P.( 20.81%)
STRIPE-A-ZONE, INC.(0.61%)
ALLIANCE GEOTECHNICAL GROUP(0.15%)
PIBURN & CARSON, LLC (0.50%)
FOUNDATION DRILLERS, INC.(0.15%)
COWBOY TRUCKING(0.13%)
RMI WORLDWIDE, LLC (0.05%)
LONE STAR HIGHWAY PRODUCTS, INC. (2.50%)
USA SWPPP INSPECTIONS, INC.(0.45%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.02%)
SUPREME SAWING AND SEALING (0.24%)
J.L. STEEL REINFORCING, LLC(0.09%)
W.O.E. CONSTRUCTION(0.05%)
L & E HART ENTERPRISES, INC. (2.20%)
STORM WATER MANAGEMENT, INC. (0.03%)
SCOTT DERR PAINTING CO, LLC(0.12%)
STRAIGHT LINE SAWING & SEALING (0.14%)
UTILITY AND ENVIRONMENTAL SERVICES, INCORPORATED (0.10%)
Contract # 12103201
Totals 14780097.76 9782.42 16875895.86 99.9

CountyDALLAS
Highway IH 30
From COCKRELL HILL ROAD
To WESTMORELAND RD IN DALLAS
CSJ 1068-04-154
Proj ID C 1068-4-154
Work Type GRADING, PAVEMENT, SIGNS, PVMT MKGS
 
2.704 9814841.51 67146.80 67146.80 0.6
Work Order 09-09-14
Work Began 11-11-14
Work Completed  
Time Computed 09-25-14
Contract Working Days 321
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 8
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-154
K & S UTILITY CONTRACTORS, INC.(9.08%)
OSCAR ORDUNO, INC. (4.26%)
STORM WATER MANAGEMENT, INC. (0.29%)
Contract # 07143214
Totals 9814841.51 67146.80 67146.80 0.6

CountyKAUFMAN
Highway FM 740
From BUFFALO CREEK
To '
CSJ 1091-01-016
Proj ID STP 2009(601)ES
Work Type REPL BR & APPRS
 
0.323 2856520.65 120.00 3878146.17 99.9
Work Order 09-28-09
Work Began 02-16-10
Work Completed  
Time Computed 10-14-09
Contract Working Days 389
Addl Days Granted 101
Working Days Charged 525
Percent Time Used 107
Contractor(s)
DOUGHTIE CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1091-01-016
BTA SERVICES, LTD. (0.58%)
PREMIER PAVING, LTD. ( 10.17%)
COWTOWN TRAFFIC CONTROL, INC.(0.30%)
CENTRAL TEXAS ENVIRONMENTAL SERVICES, LLC(0.42%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.98%)
D & E CONTRACTORS(8.87%)
HOLES INCORPORATED (0.98%)
TEX OP CONSTRUCTION, LP(0.35%)
JUST GROOVING, LTD.(0.19%)
LONE STAR HIGHWAY PRODUCTS, INC. (3.67%)
CLEMONS TRUCKING (0.36%)
SOUTHWEST CRUSHING, LLC(0.36%)
BREDA COMPANY, INC.(0.24%)
INTERSTATE SAFETY SYSTEMS, INC.(3.92%)
WEBBER BARRIER SERVICES, INC.(3.07%)
ODUM SERVICES, L.P.(0.74%)
Contract # 07093216
Totals 2856520.65 120.00 3878146.17 99.9

CountyKAUFMAN
Highway FM 740
From RANCH ROAD IN FORNEY
To ROCKWALL COUNTY LINE
CSJ 1091-01-019
Proj ID STP 2013(318)
Work Type GR, BASE, PVMT, HMAC, PVMT MKGS, SI
 
6.023 5599999.92 457433.87 4775739.10 86.2
Work Order 06-20-13
Work Began 07-25-13
Work Completed  
Time Computed 07-06-13
Contract Working Days 210
Addl Days Granted 40
Working Days Charged 298
Percent Time Used 119
Contractor(s)
WESTFIELD INSURANCE GROUP
SUBCONTRACTOR(S) FOR CCSJ: 1091-01-019
PEACHTREE CONSTRUCTION, LTD. ( 39.38%)
HIGHWAY 19 CONSTRUCTION, LLC (8.06%)
TEXAS HIGHWAY MAINTENANCE, LLC (1.20%)
USA SWPPP INSPECTIONS, INC.(2.50%)
DUSTROL, INC.(3.13%)
INTEGRATED ROADWAY SERVICES, INC.(2.53%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.40%)
PEACHTREE CONSTRUCTION, LTD. ( 39.68%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.69%)
USA SWPPP INSPECTIONS, INC.(1.15%)
DUSTROL, INC.(1.91%)
FORTSON CONTRACTING, INC.(0.97%)
BRENDA PRICE TRUCKING(2.54%)
FANNIN TREE FARM, LTD(0.64%)
Contract # 04133223
Totals 5599999.92 457433.87 4775739.10 86.2

CountyROCKWALL
Highway FM 740 ETC
From AT AMY PARKS ELEMENTARY SCHOOL
To IN CITY OF HEATH
CSJ 1091-04-019
Proj ID STP 1102(212)SRS
Work Type PEDESTRIAN WALKWAY IMPROVEMENTS#2
 
0.982 1049080.05 2325.63 765823.81 72.9
Work Order 12-03-13
Work Began 05-19-14
Work Completed  
Time Computed 02-01-14
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 70
Percent Time Used 92
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1091-04-019
BRENDA PRICE TRUCKING(1.20%)
DUSTROL, INC.(0.68%)
LONE STAR MANHOLE & STRUCTURES, LLC(1.79%)
ROAD MASTER STRIPING LLC (0.32%)
USA SWPPP INSPECTIONS, INC.(3.66%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.55%)
Contract # 08133057
Totals 1049080.05 2325.63 765823.81 72.9

CountyELLIS
Highway FM 879
From AT BRANCH OF MUSTANG CREEK
To .
CSJ 1159-02-031
Proj ID BR 2013(832)
Work Type REPLACE BR & APPRS
 
0.134 889807.76 40784.29 502287.05 56.4
Work Order 10-24-13
Work Began 01-15-14
Work Completed  
Time Computed 12-23-13
Contract Working Days 245
Addl Days Granted 0
Working Days Charged 237
Percent Time Used 96
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1159-02-031
FORTSON CONTRACTING, INC.(2.52%)
HOUSTON SAWING & DRILLING(0.33%)
MCL CONTRACTING, LLC (1.05%)
ALTUS TRAFFIC MANAGEMENT LLC (1.05%)
PEACHTREE CONSTRUCTION, LTD. (5.55%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.38%)
STORM WATER MANAGEMENT, INC. (1.03%)
STRIPING TECHNOLOGY, L.P.(1.46%)
W.O.E. CONSTRUCTION(0.13%)
MCL CONTRACTING, LLC (0.23%)
Contract # 07133013
Totals 889807.76 40784.29 502287.05 56.4

CountyDENTON
Highway FM 1171
From WEST OF US 377
To WEST OF SHILOH RD
CSJ 1311-01-034
Proj ID C 1311-1-34
Work Type GR, STRS, BASE, CRCP, PVMT MKGS, SIGNS
 
7.011 45721253.16 1526202.63 11616931.60 25.4
Work Order 06-05-13
Work Began 06-02-14
Work Completed  
Time Computed 03-02-14
Contract Working Days 693
Addl Days Granted 0
Working Days Charged 125
Percent Time Used 18
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1311-01-034
BREDA COMPANY, INC.(0.96%)
BUYERS BARRICADES, INC.(0.20%)
CINTEREX US, INC.(1.17%)
CLLA GROUP, LLC(9.39%)
DUSTROL, INC.(0.30%)
INTEGRATED ROADWAY SERVICES, INC.(2.34%)
JAGOE-PUBLIC COMPANY ( 14.10%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.74%)
THELIN RECYCLING COMPANY, L.P. (0.16%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.10%)
W.O.E. CONSTRUCTION(0.28%)
WYLIE DRILLING & DRAINAGE, INC.(0.83%)
VENUS CONSTRUCTION (7.23%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.35%)
SLATON BROTHERS, INC.(0.58%)
CB SERVICES, INC.(0.10%)
Contract # 03133002
Totals 45721253.16 1526202.63 11616931.60 25.4

CountyDENTON
Highway FM 1385
From US 380
To APPROX. 2 MILES NORTH OF FM 428
CSJ 1315-01-025
Proj ID STP 1402(028)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
7.588 9063184.19 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 378
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 1315-01-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143208
Totals 9063184.19 0.00 0.00 0.0

CountyDENTON
Highway FM 423
From US 380
To 0.8 MI SOUTH OF FM 2934
CSJ 1315-02-009
Proj ID C 1315-2-9
Work Type WIDEN TO 6 LANE DIVIDED URBAN
 
3.488 29826069.73 737808.98 1504752.42 5.0
Work Order 12-12-13
Work Began 10-08-14
Work Completed  
Time Computed 09-08-14
Contract Working Days 603
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 5
Contractor(s)
MCM
SUBCONTRACTOR(S) FOR CCSJ: 1315-02-009
TOTAL HIGHWAY MAINTENANCE, LLC (0.96%)
STORM WATER MANAGEMENT, INC. (0.28%)
BOWMAN ENGINEERING & CONSULTING, INC.(0.84%)
FORTSON CONTRACTING, INC.(0.09%)
IEA, INC (9.39%)
JAGOE-PUBLIC COMPANY ( 10.82%)
OSCAR ORDUNO, INC. (0.23%)
ROADWAY SOLUTIONS, INC.(4.78%)
ROBERTS TRUCKING (1.98%)
RUSSO CORPORATION(0.55%)
Contract # 09133204
Totals 29826069.73 737808.98 1504752.42 5.0

CountyCOLLIN
Highway FM 1378
From 585 SOUTH OF WHITE ROCK CREEK
To NORTH OF WHITE ROCK CREEK
CSJ 1392-01-035
Proj ID BR 2014(872)
Work Type REPL BRIDGE
 
0.526 1788995.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-09-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ACCELERATED CRITICAL PATH, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1392-01-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143231
Totals 1788995.75 0.00 0.00 0.0

CountyCOLLIN
Highway FM 1378
From FM 2514
To 0.2 MILE SOUTH OF FOREST GROVE RD
CSJ 1392-01-040
Proj ID STP 2015(395)
Work Type BASE REPAIR AND OVERLAY
 
6.057 2696578.78 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 192
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1392-01-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143007
Totals 2696578.78 0.00 0.00 0.0

CountyELLIS
Highway FM 1387
From WEST OF KENSINGTON DR
To EAST OF WALNUT GROVE RD
CSJ 1394-02-023
Proj ID CC 1394-2-23
Work Type GRADING, PAVING, STRUCTURES, SIGNS
 
0.925 4091255.00 395238.95 2982583.28 72.9
Work Order 08-06-13
Work Began 10-16-13
Work Completed  
Time Computed 10-05-13
Contract Working Days 309
Addl Days Granted 0
Working Days Charged 297
Percent Time Used 96
Contractor(s)
TISEO PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 1394-02-023
BROCK ENVIRONMENTAL, LLC (1.34%)
MEL"S ELECTRIC SERVICE, INC. (3.36%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 16.40%)
RPM XCONSTRUCTION, LLC (8.29%)
STRIPING TECHNOLOGY, L.P.(1.65%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (6.50%)
DALLAS LITE AND BARRICADE INC. (0.65%)
DUSTROL, INC.(0.91%)
CROSSROADS, L.P. (0.37%)
T-BAR FENCE, INC.(0.09%)
W.O.E. CONSTRUCTION(7.41%)
FOUR STAR EXCAVATING INC (9.19%)
INLET STRUCTURE SPECIALTIES LTD. (1.66%)
IRON CONCRETE CONSTRUCTION COMPANY, INC. (1.66%)
J.R. STEEL TIE (0.83%)
Contract # 04133010
Totals 4091255.00 395238.95 2982583.28 72.9

CountyELLIS
Highway FM 55
From SH 34
To 0.14 MI S OF NASH HOWARD RD
CSJ 1451-01-024
Proj ID STP 2014(874)
Work Type GR, BASE, PVMT MKGS, SIGNS
 
5.052 5538628.87 59229.00 59229.00 1.0
Work Order 10-02-14
Work Began 12-01-14
Work Completed  
Time Computed 10-18-14
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-024
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(3.86%)
STRIPING TECHNOLOGY, L.P.(0.83%)
SAN-ANN-CO., INC.(1.01%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(0.25%)
FORTSON CONTRACTING, INC.(3.25%)
OLDEN, INC.(5.14%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.49%)
Contract # 07143018
Totals 5538628.87 59229.00 59229.00 1.0

CountyDENTON
Highway FM 720
From AT HARTS BRANCH
To .
CSJ 1567-01-021
Proj ID BR 2010(983)
Work Type REPL BR & APPRS
 
0.080 1726268.66 32177.50 1437770.54 83.2
CountyDENTON
Highway FM 720
From AT LITTLE ELM CREEK BRANCH OF LAKE
To LEWISVILLE
CSJ 1567-01-022
Proj ID BR 2010(983)
Work Type REPL BR & APPRS
 
0.484 15758790.61 55665.00 15536196.86 98.5
CountyDENTON
Highway FM 720
From 0.2 MI W OF GARZA LANE (W OF LAKE L
To 0.1 MI WEST OF FM 423
CSJ 1567-01-029
Proj ID STP 2010(982)MM
Work Type GRADING, STR, PVMT, SIGNS
 
4.493 33538923.64 936591.09 27329910.30 81.4
CountyDENTON
Highway FM 720
From 0.2 MILE WEST OF GARZA LANE
To 0.1 MILE WEST OF FM 423
CSJ 1567-01-032
Proj ID RW 1567-1-32
Work Type ROW ACQ. AND UTIL. ADJUST.
 
0.001 3297279.80 0.00 460852.58 13.9
Work Order 09-13-10
Work Began 07-14-11
Work Completed  
Time Computed 03-12-11
Contract Working Days 577
Addl Days Granted 83
Working Days Charged 643
Percent Time Used 97
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1567-01-029
ATS DRILLING, L.P. (5.77%)
BRENDA PRICE TRUCKING(0.22%)
CRAIG OLDEN, INC.(0.61%)
DALLAS LITE AND BARRICADE INC. (0.11%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21%)
HIGHWAY TECHNOLOGIES, INC. (0.31%)
L & E HART ENTERPRISES, INC. (2.09%)
MICA CORPORATION (4.78%)
NORTH TEXAS REBAR, LLC (5.54%)
PENHALL COMPANY(0.05%)
RAMBO CONTRACTING, INC.(2.62%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(6.26%)
S & V CONSTRUCTION LLC (0.05%)
SOUTH TEXAS PAINTING COMPANY (0.15%)
STORM WATER MANAGEMENT, INC. (0.10%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.28%)
TEX OP CONSTRUCTION, LP(0.99%)
WEIR BROS.,INC.(5.19%)
GREAT WESTERN ERECTORS (0.12%)
DURABLE SPECIALTIES, INC.(1.39%)
LAYFIELD CONSTRUCTION, INC (0.01%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.36%)
GREAT WESTERN ERECTORS (0.49%)
Contract # 07103001
Totals 54321262.71 1024433.59 44764730.28 82.4

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9