Monthly State Let Construction Report For Dallas District As Of Jul 11, 2014 Page 7 Of 8

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyKAUFMAN
Highway FM 741
From FM 740
To MONITOR BLVD. IN FORNEY
CSJ 1092-01-018
Proj ID STP 2013(453)
Work Type LANDSCAPE DEVELOPMENT
 
1.976 298102.56 13446.56 334846.35 99.9
Work Order 05-20-13
Work Began 07-10-13
Work Completed  
Time Computed 06-05-13
Contract Working Days 92
Addl Days Granted 4
Working Days Charged 101
Percent Time Used 105
Contractor(s)
LANDSCAPE CONTRACTING AND IRRIGATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1092-01-018
TOTAL HIGHWAY MAINTENANCE, LLC (1.41%)
FIRELINE SERVICES, INC.(2.01%)
SYSTEM ELECTRIC CO. DBA MCBRIDE ELECTRIC (3.65%)
CC TREE FARMS, L.L.C.(5.05%)
AQUA BORE(0.98%)
Contract # 03133221
Totals 298102.56 13446.56 334846.35 99.9

CountyELLIS
Highway FM 879
From AT BRANCH OF MUSTANG CREEK
To .
CSJ 1159-02-031
Proj ID BR 2013(832)
Work Type REPLACE BR & APPRS
 
0.134 889807.76 29447.36 358994.43 40.3
Work Order 10-24-13
Work Began 01-15-14
Work Completed  
Time Computed 12-23-13
Contract Working Days 245
Addl Days Granted 0
Working Days Charged 129
Percent Time Used 52
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1159-02-031
FORTSON CONTRACTING, INC.(2.52%)
HOUSTON SAWING & DRILLING(0.33%)
MCL CONTRACTING, LLC (1.05%)
ALTUS TRAFFIC MANAGEMENT LLC (1.05%)
PEACHTREE CONSTRUCTION, LTD. (5.55%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.38%)
STORM WATER MANAGEMENT, INC. (1.03%)
STRIPING TECHNOLOGY, L.P.(1.46%)
W.O.E. CONSTRUCTION(0.13%)
MCL CONTRACTING, LLC (0.23%)
Contract # 07133013
Totals 889807.76 29447.36 358994.43 40.3

CountyDENTON
Highway FM 1171
From WEST OF US 377
To WEST OF SHILOH RD
CSJ 1311-01-034
Proj ID C 1311-1-34
Work Type GR, STRS, BASE, CRCP, PVMT MKGS, SIGNS
 
7.011 45721253.16 1723018.95 2710178.27 5.9
Work Order 06-05-13
Work Began 06-02-14
Work Completed  
Time Computed 03-02-14
Contract Working Days 693
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 2
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1311-01-034
BREDA COMPANY, INC.(0.96%)
BUYERS BARRICADES, INC.(0.20%)
CINTEREX US, INC.(1.17%)
CLLA GROUP, LLC(9.39%)
DUSTROL, INC.(0.30%)
INTEGRATED ROADWAY SERVICES, INC.(2.34%)
JAGOE-PUBLIC COMPANY ( 14.10%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.74%)
THELIN RECYCLING COMPANY, L.P. (0.16%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.10%)
W.O.E. CONSTRUCTION(0.28%)
WYLIE DRILLING & DRAINAGE, INC.(0.83%)
VENUS CONSTRUCTION (3.09%)
Contract # 03133002
Totals 45721253.16 1723018.95 2710178.27 5.9

CountyDENTON
Highway FM 423
From US 380
To 0.8 MI SOUTH OF FM 2934
CSJ 1315-02-009
Proj ID C 1315-2-9
Work Type WIDEN TO 6 LANE DIVIDED URBAN
 
3.488 29826069.73 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-12-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 603
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MCM
SUBCONTRACTOR(S) FOR CCSJ: 1315-02-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09133204
Totals 29826069.73 0.00 0.00 0.0

CountyCOLLIN
Highway FM 1378
From 585 SOUTH OF WHITE ROCK CREEK
To NORTH OF WHITE ROCK CREEK
CSJ 1392-01-035
Proj ID BR 2014(872)
Work Type REPL BRIDGE
 
0.526 1788995.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ACCELERATED CRITICAL PATH, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1392-01-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143231
Totals 1788995.75 0.00 0.00 0.0

CountyELLIS
Highway FM 1387
From WEST OF KENSINGTON DR
To EAST OF WALNUT GROVE RD
CSJ 1394-02-023
Proj ID CC 1394-2-23
Work Type GRADING, PAVING, STRUCTURES, SIGNS
 
0.925 4091255.00 346715.87 1316920.62 32.1
Work Order 08-06-13
Work Began 10-16-13
Work Completed  
Time Computed 10-05-13
Contract Working Days 309
Addl Days Granted 0
Working Days Charged 188
Percent Time Used 60
Contractor(s)
TISEO PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 1394-02-023
BROCK ENVIRONMENTAL, LLC (1.34%)
MEL"S ELECTRIC SERVICE, INC. (3.36%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 16.40%)
RPM XCONSTRUCTION, LLC (8.29%)
STRIPING TECHNOLOGY, L.P.(1.65%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (6.50%)
DALLAS LITE AND BARRICADE INC. (0.65%)
DUSTROL, INC.(0.91%)
CROSSROADS, L.P. (0.37%)
T-BAR FENCE, INC.(0.09%)
W.O.E. CONSTRUCTION(7.41%)
FOUR STAR EXCAVATING INC (9.19%)
INLET STRUCTURE SPECIALTIES LTD. (1.66%)
IRON CONCRETE CONSTRUCTION COMPANY, INC. (1.66%)
J.R. STEEL TIE (0.83%)
Contract # 04133010
Totals 4091255.00 346715.87 1316920.62 32.1

CountyELLIS
Highway FM 55
From SH 34
To 0.14 MI S OF NASH HOWARD RD
CSJ 1451-01-024
Proj ID STP 2014(874)
Work Type GR, BASE, PVMT MKGS, SIGNS
 
5.052 5538628.87 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143018
Totals 5538628.87 0.00 0.00 0.0

CountyDENTON
Highway FM 720
From AT HARTS BRANCH
To .
CSJ 1567-01-021
Proj ID BR 2010(983)
Work Type REPL BR & APPRS
 
0.080 1726268.66 206034.71 1232386.62 71.3
CountyDENTON
Highway FM 720
From AT LITTLE ELM CREEK BRANCH OF LAKE
To LEWISVILLE
CSJ 1567-01-022
Proj ID BR 2010(983)
Work Type REPL BR & APPRS
 
0.484 15758790.61 1576710.88 13204901.02 83.7
CountyDENTON
Highway FM 720
From 0.2 MI W OF GARZA LANE (W OF LAKE L
To 0.1 MI WEST OF FM 423
CSJ 1567-01-029
Proj ID STP 2010(982)MM
Work Type GRADING, STR, PVMT, SIGNS
 
4.493 33538923.64 -249038.56 22448671.42 66.9
CountyDENTON
Highway FM 720
From 0.2 MILE WEST OF GARZA LANE
To 0.1 MILE WEST OF FM 423
CSJ 1567-01-032
Proj ID RW 1567-1-32
Work Type ROW ACQ. AND UTIL. ADJUST.
 
0.001 3297279.80 0.00 460852.58 13.9
Work Order 09-13-10
Work Began 07-14-11
Work Completed  
Time Computed 03-12-11
Contract Working Days 577
Addl Days Granted 8
Working Days Charged 538
Percent Time Used 91
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1567-01-029
ATS DRILLING, L.P. (5.77%)
BRENDA PRICE TRUCKING(0.22%)
CRAIG OLDEN, INC.(0.61%)
DALLAS LITE AND BARRICADE INC. (0.11%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21%)
HIGHWAY TECHNOLOGIES, INC. (0.31%)
L & E HART ENTERPRISES, INC. (2.09%)
MICA CORPORATION (4.78%)
NORTH TEXAS REBAR, LLC (5.54%)
PENHALL COMPANY(0.05%)
RAMBO CONTRACTING, INC.(2.62%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(6.26%)
S & V CONSTRUCTION LLC (0.05%)
SOUTH TEXAS PAINTING COMPANY (0.15%)
STORM WATER MANAGEMENT, INC. (0.10%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.28%)
TEX OP CONSTRUCTION, LP(0.99%)
WEIR BROS.,INC.(5.19%)
GREAT WESTERN ERECTORS (0.12%)
DURABLE SPECIALTIES, INC.(1.39%)
LAYFIELD CONSTRUCTION, INC (0.01%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.36%)
GREAT WESTERN ERECTORS (0.49%)
Contract # 07103001
Totals 54321262.71 1533707.03 37346811.64 68.7

CountyDENTON
Highway FM 720
From ELDORADO PKWY (FM 720)
To SOUTH OF MARTOP
CSJ 1567-01-025
Proj ID C 1567-1-25
Work Type GR, STRS & PVT
 
2.565 15597320.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-11-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 420
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1567-01-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143001
Totals 15597320.25 0.00 0.00 0.0

CountyDENTON
Highway FM 720
From FINSBURY TRAIL
To FM 423
CSJ 1567-01-035
Proj ID STP 2013(666)
Work Type LANDSCAPE DEVELOPMENT
 
1.160 524000.00 9147.75 510201.25 97.3
Work Order 09-05-13
Work Began 09-25-13
Work Completed  
Time Computed 09-21-13
Contract Working Days 83
Addl Days Granted 0
Working Days Charged 72
Percent Time Used 86
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 1567-01-035
HIGHWAY BARRICADES AND SERVICES, LLC (1.47%)
AQUA BORE(5.66%)
MATERIALS MANAGEMENT SERVICES(0.30%)
Contract # 05133010
Totals 524000.00 9147.75 510201.25 97.3

CountyDENTON
Highway FM 423
From STEWARTS CREEK ROAD
To SH 121
CSJ 1567-02-020
Proj ID C 1567-2-20
Work Type WIDEN TO 6 LANE DIVIDED URBAN
 
3.761 43849314.67 0.00 1293077.42 2.9
CountyDENTON
Highway FM 423
From STEWARTS CREEK ROAD
To SH 121
CSJ 1567-02-030
Proj ID RW 1567-2-30
Work Type ROW ACQ, RELOC & UTILITIES
 
3.794 8015048.33 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-05-11
Work Began 00-00-00
Work Completed  
Time Computed 06-02-12
Contract Working Days 642
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BALFOUR BEATTY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1567-02-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09113202
Totals 51864363.00 0.00 1293077.42 2.4

CountyDENTON
Highway FM 423
From STEWARTS CREEK ROAD
To SH 121
CSJ 1567-02-032
Proj ID C 1567-2-32
Work Type WIDEN TO 6 LANE DIVIDED URBAN
 
3.761 49691109.92 0.00 0.00 0.0
CountyDENTON
Highway FM 423
From STEWARTS CREEK ROAD
To SH 121
CSJ 1567-02-033
Proj ID RW 1567-2-33
Work Type ADJUSTMENT OF UTILITIES
 
3.761 8252384.38 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 756
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1567-02-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143001
Totals 57943494.30 0.00 0.00 0.0

CountyDENTON
Highway FM 407
From FM 1830
To WEST OF LANTANA TRAIL
CSJ 1785-01-028
Proj ID C 1785-1-28
Work Type GR, STRS & PVT.
 
6.126 12873212.87 55073.28 13389739.34 99.9
Work Order 09-16-11
Work Began 03-01-12
Work Completed  
Time Computed 03-01-12
Contract Working Days 497
Addl Days Granted 86
Working Days Charged 612
Percent Time Used 104
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1785-01-028
BREDA COMPANY, INC.(1.11%)
BRENDA PRICE TRUCKING(0.00%)
CONCRETE CUTTING BY BOND (0.50%)
FARR FOUNDATION, INC.(0.24%)
FORTSON CONTRACTING, INC.(0.13%)
HIGHWAY TECHNOLOGIES, INC. (0.00%)
IOWA BRIDGE & CULVERT, LC(1.16%)
MICA CORPORATION (2.69%)
MIKE ALBERT, INC.(4.47%)
TEXAS CURB CUT, LP (0.05%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.82%)
THELIN RECYCLING CO., LLC(0.23%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.45%)
C.T. AND S. METALWORKS, INC. (0.00%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(2.03%)
PENHALL COMPANY(0.00%)
STRIPING TECHNOLOGY, L.P.(0.99%)
Contract # 07113205
Totals 12873212.87 55073.28 13389739.34 99.9

CountyDENTON
Highway FM 407
From W. OF CHIN CHAPEL
To W. OF BRIARHILL BLVD.
CSJ 1950-01-026
Proj ID C 1950-1-26
Work Type GRADING, STRUCTURES, BAND AND SURF
 
1.369 5419912.44 0.00 6161230.32 99.9
Work Order 02-16-10
Work Began 09-21-10
Work Completed  
Time Computed 05-17-10
Contract Working Days 300
Addl Days Granted 209
Working Days Charged 485
Percent Time Used 95
Contractor(s)
TISEO PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 1950-01-026
AXIS CONTRACTING, INC. (1.90%)
BROCK ENVIRONMENTAL, LLC (0.38%)
BUYERS BARRICADES, INC.(0.52%)
DURABLE SPECIALTIES, INC.(1.95%)
FORTSON CONTRACTING, INC.(0.02%)
IOWA BRIDGE & CULVERT, LC(1.45%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 17.25%)
STRIPE-A-ZONE, INC.(1.19%)
T & R EXCAVATION, INC. ( 21.56%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.21%)
TOMAS REYES TRUCKING, INC. (2.93%)
W.O.E. CONSTRUCTION(0.14%)
TEXAS INLETS, INC. (3.48%)
DUSTROL, INC.(3.03%)
Contract # 01103007
Totals 5419912.44 0.00 6161230.32 99.9

CountyCOLLIN
Highway FM 2551
From FM 544
To FM 2514
CSJ 2056-01-045
Proj ID C 2056-1-45
Work Type GR., STR., BASE AND PAVEMENT
 
2.953 15783469.03 556032.56 8436174.71 53.4
Work Order 12-07-11
Work Began 11-26-12
Work Completed  
Time Computed 06-25-12
Contract Working Days 480
Addl Days Granted 5
Working Days Charged 344
Percent Time Used 70
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2056-01-045
ARTEX ELECTRIC, INC. (3.54%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 14.01%)
DALLAS LITE AND BARRICADE INC. (0.25%)
DUSTIN ALLEN, INC. (0.30%)
SOUTHWEST CONSTRUCTION SERVICES(0.46%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.90%)
WYLIE DRILLING & DRAINAGE, INC.(0.19%)
BROCK ENVIRONMENTAL, LLC (0.15%)
THELIN RECYCLING COMPANY, L.P. (0.16%)
DUSTROL, INC.(0.35%)
JM MATERIALS, INC. (4.40%)
PANTHER CREEK TRANSPORTATION, INC. (0.57%)
USA SWPPP INSPECTIONS, INC.(0.01%)
MCL CONTRACTING, LLC (0.01%)
BREDA COMPANY, INC.(0.00%)
CTBX, INC. (0.52%)
HERDEZ TRUCKING, INC.(0.00%)
A BROTHERS MILLING, LLC(0.41%)
Contract # 06113239
Totals 15783469.03 556032.56 8436174.71 53.4

CountyDENTON
Highway LP 288
From IH 35
To US 377 / US 380
CSJ 2250-02-016
Proj ID STP 2014(661)
Work Type FULL DEPTH CONCRETE PAVEMENT REPAIR
 
6.722 3653118.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-30-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 210
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2250-02-016
ALTUS TRAFFIC MANAGEMENT LLC (0.47%)
BRENDA PRICE TRUCKING(6.28%)
PEACHTREE CONSTRUCTION, LTD. (3.78%)
STRAIGHT LINE SAWING & SEALING (5.96%)
STRIPING TECHNOLOGY, L.P.(1.01%)
ACU CONSTRUCTION LLC (0.44%)
USA EROSION, INC.(0.36%)
Contract # 05143209
Totals 3653118.00 0.00 0.00 0.0

CountyDALLAS
Highway IH 635
From EAST OF CENTERVILLE RD.
To NORTHWEST HIGHWAY
CSJ 2374-02-124
Proj ID C 2374-2-124
Work Type GR, PVMT, SIGNS, PVMT MRKGS
 
1.288 7718650.04 677771.51 8104725.61 99.9
Work Order 10-12-09
Work Began 04-05-11
Work Completed  
Time Computed 04-10-10
Contract Working Days 459
Addl Days Granted 145
Working Days Charged 602
Percent Time Used 99
Contractor(s)
GLENN THURMAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2374-02-124
DALLAS LITE AND BARRICADE INC. (0.26%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(7.66%)
TEX OP CONSTRUCTION, LP(1.06%)
NORTH TEXAS BOMANITE, INC. (0.63%)
AMERICAN INTELOCK & MODULAR CONSTRUCTION, INC. (4.79%)
DT CONSTRUCTION SERVICES (0.52%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.77%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.92%)
CONCRETE CUTTING BY BOND (0.21%)
INDUS CONSTRUCTION, L.P. (0.54%)
INTEGRATED ROADWAY SERVICES, INC.(5.14%)
CRAIG OLDEN, INC.(1.40%)
LARRETT, INC.( 21.33%)
CB SERVICES, INC.(1.91%)
MIKE ALBERT, INC.(6.03%)
CONCRETE PENETRATING CO. (0.09%)
SOUTHWEST CONSTRUCTION SERVICES(2.19%)
Contract # 09093060
Totals 7718650.04 677771.51 8104725.61 99.9

CountyDALLAS
Highway IH 20
From AT IH 45 RAMP FROM EB IH 20
To NB IH 45
CSJ 2374-03-057
Proj ID IM 0205(151)
Work Type ADD LANE TO DIRECT CONNECTION RAMP
 
1.418 5699998.00 0.00 4268601.09 74.8
Work Order 10-07-11
Work Began 01-12-12
Work Completed  
Time Computed 12-06-11
Contract Working Days 471
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 77
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 2374-03-057
ALLIANCE GEOTECHNICAL GROUP(0.00%)
AXIS CONTRACTING, INC. (1.14%)
BREDA COMPANY, INC.(0.96%)
BROCK ENVIRONMENTAL, LLC (0.71%)
CONCRETE CUTTING BY BOND (0.26%)
DUSTIN ALLEN, INC. (1.41%)
DUSTROL, INC.(0.87%)
FOUNDATION DRILLERS, INC.(1.05%)
HIGHWAY TECHNOLOGIES, INC. (0.55%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (1.12%)
MELS ELECTRIC, L.P.(0.34%)
STRIPING TECHNOLOGY, L.P.(0.93%)
GREAT WESTERN ERECTORS (0.06%)
ERWIN STEEL WORKS, LLC (0.11%)
RG PAINTING(0.39%)
MAGNUM SAWING(0.34%)
D & D STUD WELDING (0.17%)
Contract # 08113245
Totals 5699998.00 0.00 4268601.09 74.8

CountyDALLAS
Highway IH 20
From IH 35E
To IH 45
CSJ 2374-03-076
Proj ID CM 2013(987)
Work Type ITS
 
14.982 1858920.39 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-13-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 164
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 4
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2374-03-076
CITY BUILD UTILITY SUPPLY(3.38%)
ALTUS TRAFFIC MANAGEMENT LLC (0.71%)
ODUM SERVICES, L.P.(1.51%)
INTEGRATED ROADWAY SERVICES, INC.( 39.01%)
ADVANCED FIBER SERVICES(0.79%)
Contract # 09133012
Totals 1858920.39 0.00 0.00 0.0

CountyDALLAS
Highway IH 20
From EAST OF POLK RD
To EAST OF IH 45
CSJ 2374-03-081
Proj ID IM 0205(153)
Work Type LANDSCAPE DEVELOPMENT
 
9.604 399270.75 19317.83 340219.49 85.2
Work Order 10-17-13
Work Began 11-12-13
Work Completed  
Time Computed 11-02-13
Contract Working Days 103
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 100
Contractor(s)
BEVERLY SUE GLOBAL SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2374-03-081
GONZALES CONSTRUCTION( 32.56%)
BUYERS BARRICADES, INC.(2.50%)
SATELLITE CABLE CONSTTRUCTION, INC.(7.51%)
ERASMO SPRINKLER & REPAIR( 25.04%)
FOX CONCRETE INNOVATIONS (9.35%)
FAIRWAY LANDSCAPE AND NURSERY, INC.(3.89%)
GUERREROS CONSTRUCTION (7.51%)
Contract # 07133215
Totals 399270.75 19317.83 340219.49 85.2

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8