Monthly State Let Construction Report For Dallas District As Of Sep 15, 2014 Page 7 Of 8

Last Update: Monday, September 15, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyKAUFMAN
Highway FM 740
From RANCH ROAD IN FORNEY
To ROCKWALL COUNTY LINE
CSJ 1091-01-019
Proj ID STP 2013(318)
Work Type GR, BASE, PVMT, HMAC, PVMT MKGS, SI
 
6.023 5599999.92 460180.12 3663223.39 66.0
Work Order 06-20-13
Work Began 07-25-13
Work Completed  
Time Computed 07-06-13
Contract Working Days 210
Addl Days Granted 32
Working Days Charged 276
Percent Time Used 114
Contractor(s)
WESTFIELD INSURANCE GROUP
SUBCONTRACTOR(S) FOR CCSJ: 1091-01-019
PEACHTREE CONSTRUCTION, LTD. ( 39.38%)
HIGHWAY 19 CONSTRUCTION, LLC (8.06%)
TEXAS HIGHWAY MAINTENANCE, LLC (1.20%)
USA SWPPP INSPECTIONS, INC.(2.50%)
DUSTROL, INC.(3.13%)
INTEGRATED ROADWAY SERVICES, INC.(2.53%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.40%)
PEACHTREE CONSTRUCTION, LTD. ( 39.68%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.69%)
USA SWPPP INSPECTIONS, INC.(1.15%)
DUSTROL, INC.(1.91%)
FORTSON CONTRACTING, INC.(0.97%)
BRENDA PRICE TRUCKING(2.54%)
Contract # 04133223
Totals 5599999.92 460180.12 3663223.39 66.0

CountyROCKWALL
Highway FM 740 ETC
From AT AMY PARKS ELEMENTARY SCHOOL
To IN CITY OF HEATH
CSJ 1091-04-019
Proj ID STP 1102(212)SRS
Work Type PEDESTRIAN WALKWAY IMPROVEMENTS#2
 
0.982 1049080.05 401432.85 731279.73 69.7
Work Order 12-03-13
Work Began 05-19-14
Work Completed  
Time Computed 02-01-14
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 69
Percent Time Used 90
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1091-04-019
BRENDA PRICE TRUCKING(1.20%)
DUSTROL, INC.(0.68%)
LONE STAR MANHOLE & STRUCTURES, LLC(1.79%)
ROAD MASTER STRIPING LLC (0.32%)
USA SWPPP INSPECTIONS, INC.(3.66%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.55%)
Contract # 08133057
Totals 1049080.05 401432.85 731279.73 69.7

CountyELLIS
Highway FM 879
From AT BRANCH OF MUSTANG CREEK
To .
CSJ 1159-02-031
Proj ID BR 2013(832)
Work Type REPLACE BR & APPRS
 
0.134 889807.76 29760.10 389800.35 43.8
Work Order 10-24-13
Work Began 01-15-14
Work Completed  
Time Computed 12-23-13
Contract Working Days 245
Addl Days Granted 0
Working Days Charged 173
Percent Time Used 70
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1159-02-031
FORTSON CONTRACTING, INC.(2.52%)
HOUSTON SAWING & DRILLING(0.33%)
MCL CONTRACTING, LLC (1.05%)
ALTUS TRAFFIC MANAGEMENT LLC (1.05%)
PEACHTREE CONSTRUCTION, LTD. (5.55%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.38%)
STORM WATER MANAGEMENT, INC. (1.03%)
STRIPING TECHNOLOGY, L.P.(1.46%)
W.O.E. CONSTRUCTION(0.13%)
MCL CONTRACTING, LLC (0.23%)
Contract # 07133013
Totals 889807.76 29760.10 389800.35 43.8

CountyDENTON
Highway FM 1171
From WEST OF US 377
To WEST OF SHILOH RD
CSJ 1311-01-034
Proj ID C 1311-1-34
Work Type GR, STRS, BASE, CRCP, PVMT MKGS, SIGNS
 
7.011 45721253.16 1759229.99 5437148.22 11.8
Work Order 06-05-13
Work Began 06-02-14
Work Completed  
Time Computed 03-02-14
Contract Working Days 693
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 8
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1311-01-034
BREDA COMPANY, INC.(0.96%)
BUYERS BARRICADES, INC.(0.20%)
CINTEREX US, INC.(1.17%)
CLLA GROUP, LLC(9.39%)
DUSTROL, INC.(0.30%)
INTEGRATED ROADWAY SERVICES, INC.(2.34%)
JAGOE-PUBLIC COMPANY ( 14.10%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.74%)
THELIN RECYCLING COMPANY, L.P. (0.16%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.10%)
W.O.E. CONSTRUCTION(0.28%)
WYLIE DRILLING & DRAINAGE, INC.(0.83%)
VENUS CONSTRUCTION (3.09%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.35%)
CB SERVICES, INC.(0.10%)
SLATON BROTHERS, INC.(0.58%)
Contract # 03133002
Totals 45721253.16 1759229.99 5437148.22 11.8

CountyDENTON
Highway FM 1385
From US 380
To APPROX. 2 MILES NORTH OF FM 428
CSJ 1315-01-025
Proj ID STP 1402(028)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
7.588 9063184.19 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 378
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 1315-01-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143208
Totals 9063184.19 0.00 0.00 0.0

CountyDENTON
Highway FM 423
From US 380
To 0.8 MI SOUTH OF FM 2934
CSJ 1315-02-009
Proj ID C 1315-2-9
Work Type WIDEN TO 6 LANE DIVIDED URBAN
 
3.488 29826069.73 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-12-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 603
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MCM
SUBCONTRACTOR(S) FOR CCSJ: 1315-02-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09133204
Totals 29826069.73 0.00 0.00 0.0

CountyCOLLIN
Highway FM 1378
From 585 SOUTH OF WHITE ROCK CREEK
To NORTH OF WHITE ROCK CREEK
CSJ 1392-01-035
Proj ID BR 2014(872)
Work Type REPL BRIDGE
 
0.526 1788995.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ACCELERATED CRITICAL PATH, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1392-01-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143231
Totals 1788995.75 0.00 0.00 0.0

CountyELLIS
Highway FM 1387
From WEST OF KENSINGTON DR
To EAST OF WALNUT GROVE RD
CSJ 1394-02-023
Proj ID CC 1394-2-23
Work Type GRADING, PAVING, STRUCTURES, SIGNS
 
0.925 4091255.00 208602.32 2121773.14 51.8
Work Order 08-06-13
Work Began 10-16-13
Work Completed  
Time Computed 10-05-13
Contract Working Days 309
Addl Days Granted 0
Working Days Charged 233
Percent Time Used 75
Contractor(s)
TISEO PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 1394-02-023
BROCK ENVIRONMENTAL, LLC (1.34%)
MEL"S ELECTRIC SERVICE, INC. (3.36%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 16.40%)
RPM XCONSTRUCTION, LLC (8.29%)
STRIPING TECHNOLOGY, L.P.(1.65%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (6.50%)
DALLAS LITE AND BARRICADE INC. (0.65%)
DUSTROL, INC.(0.91%)
CROSSROADS, L.P. (0.37%)
T-BAR FENCE, INC.(0.09%)
W.O.E. CONSTRUCTION(7.41%)
FOUR STAR EXCAVATING INC (9.19%)
INLET STRUCTURE SPECIALTIES LTD. (1.66%)
IRON CONCRETE CONSTRUCTION COMPANY, INC. (1.66%)
J.R. STEEL TIE (0.83%)
Contract # 04133010
Totals 4091255.00 208602.32 2121773.14 51.8

CountyELLIS
Highway FM 55
From SH 34
To 0.14 MI S OF NASH HOWARD RD
CSJ 1451-01-024
Proj ID STP 2014(874)
Work Type GR, BASE, PVMT MKGS, SIGNS
 
5.052 5538628.87 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143018
Totals 5538628.87 0.00 0.00 0.0

CountyDENTON
Highway FM 720
From AT HARTS BRANCH
To .
CSJ 1567-01-021
Proj ID BR 2010(983)
Work Type REPL BR & APPRS
 
0.080 1726268.66 15000.00 1402015.22 81.2
CountyDENTON
Highway FM 720
From AT LITTLE ELM CREEK BRANCH OF LAKE
To LEWISVILLE
CSJ 1567-01-022
Proj ID BR 2010(983)
Work Type REPL BR & APPRS
 
0.484 15758790.61 817274.20 14559883.86 92.3
CountyDENTON
Highway FM 720
From 0.2 MI W OF GARZA LANE (W OF LAKE L
To 0.1 MI WEST OF FM 423
CSJ 1567-01-029
Proj ID STP 2010(982)MM
Work Type GRADING, STR, PVMT, SIGNS
 
4.493 33538923.64 1165262.55 24310074.57 72.4
CountyDENTON
Highway FM 720
From 0.2 MILE WEST OF GARZA LANE
To 0.1 MILE WEST OF FM 423
CSJ 1567-01-032
Proj ID RW 1567-1-32
Work Type ROW ACQ. AND UTIL. ADJUST.
 
0.001 3297279.80 0.00 460852.58 13.9
Work Order 09-13-10
Work Began 07-14-11
Work Completed  
Time Computed 03-12-11
Contract Working Days 577
Addl Days Granted 8
Working Days Charged 581
Percent Time Used 99
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1567-01-029
ATS DRILLING, L.P. (5.77%)
BRENDA PRICE TRUCKING(0.22%)
CRAIG OLDEN, INC.(0.61%)
DALLAS LITE AND BARRICADE INC. (0.11%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21%)
HIGHWAY TECHNOLOGIES, INC. (0.31%)
L & E HART ENTERPRISES, INC. (2.09%)
MICA CORPORATION (4.78%)
NORTH TEXAS REBAR, LLC (5.54%)
PENHALL COMPANY(0.05%)
RAMBO CONTRACTING, INC.(2.62%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(6.26%)
S & V CONSTRUCTION LLC (0.05%)
SOUTH TEXAS PAINTING COMPANY (0.15%)
STORM WATER MANAGEMENT, INC. (0.10%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.28%)
TEX OP CONSTRUCTION, LP(0.99%)
WEIR BROS.,INC.(5.19%)
GREAT WESTERN ERECTORS (0.12%)
DURABLE SPECIALTIES, INC.(1.39%)
LAYFIELD CONSTRUCTION, INC (0.01%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.36%)
GREAT WESTERN ERECTORS (0.49%)
Contract # 07103001
Totals 54321262.71 1997536.75 40732826.23 74.9

CountyDENTON
Highway FM 720
From ELDORADO PKWY (FM 720)
To SOUTH OF MARTOP
CSJ 1567-01-025
Proj ID C 1567-1-25
Work Type GR, STRS & PVT
 
2.565 15597320.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-11-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 420
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1567-01-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143001
Totals 15597320.25 0.00 0.00 0.0

CountyDENTON
Highway FM 423
From STEWARTS CREEK ROAD
To SH 121
CSJ 1567-02-032
Proj ID C 1567-2-32
Work Type WIDEN TO 6 LANE DIVIDED URBAN
 
3.761 49691109.92 0.00 0.00 0.0
CountyDENTON
Highway FM 423
From STEWARTS CREEK ROAD
To SH 121
CSJ 1567-02-033
Proj ID RW 1567-2-33
Work Type ADJUSTMENT OF UTILITIES
 
3.761 8252384.38 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-27-14
Work Began 00-00-00
Work Completed  
Time Computed 09-12-14
Contract Working Days 756
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1567-02-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143001
Totals 57943494.30 0.00 0.00 0.0

CountyDENTON
Highway FM 407
From FM 1830
To WEST OF LANTANA TRAIL
CSJ 1785-01-028
Proj ID C 1785-1-28
Work Type GR, STRS & PVT.
 
6.126 12873212.87 111608.78 13723899.11 99.9
Work Order 09-16-11
Work Began 03-01-12
Work Completed  
Time Computed 03-01-12
Contract Working Days 497
Addl Days Granted 123
Working Days Charged 659
Percent Time Used 106
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1785-01-028
BREDA COMPANY, INC.(1.11%)
BRENDA PRICE TRUCKING(0.00%)
CONCRETE CUTTING BY BOND (0.50%)
FARR FOUNDATION, INC.(0.24%)
FORTSON CONTRACTING, INC.(0.13%)
HIGHWAY TECHNOLOGIES, INC. (0.00%)
IOWA BRIDGE & CULVERT, LC(1.16%)
MICA CORPORATION (2.69%)
MIKE ALBERT, INC.(4.47%)
TEXAS CURB CUT, LP (0.05%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.82%)
THELIN RECYCLING CO., LLC(0.23%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.45%)
C.T. AND S. METALWORKS, INC. (0.00%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(2.03%)
PENHALL COMPANY(0.00%)
STRIPING TECHNOLOGY, L.P.(0.99%)
DURABLE SPECIALTIES, INC.(2.56%)
Contract # 07113205
Totals 12873212.87 111608.78 13723899.11 99.9

CountyDENTON
Highway FM 407
From W. OF CHIN CHAPEL
To W. OF BRIARHILL BLVD.
CSJ 1950-01-026
Proj ID C 1950-1-26
Work Type GRADING, STRUCTURES, BAND AND SURF
 
1.369 5419912.44 0.00 6166065.78 99.9
Work Order 02-16-10
Work Began 09-21-10
Work Completed  
Time Computed 05-17-10
Contract Working Days 300
Addl Days Granted 209
Working Days Charged 485
Percent Time Used 95
Contractor(s)
TISEO PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 1950-01-026
AXIS CONTRACTING, INC. (1.90%)
BROCK ENVIRONMENTAL, LLC (0.38%)
BUYERS BARRICADES, INC.(0.52%)
DURABLE SPECIALTIES, INC.(1.95%)
FORTSON CONTRACTING, INC.(0.02%)
IOWA BRIDGE & CULVERT, LC(1.45%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 17.25%)
STRIPE-A-ZONE, INC.(1.19%)
T & R EXCAVATION, INC. ( 21.56%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.21%)
TOMAS REYES TRUCKING, INC. (2.93%)
W.O.E. CONSTRUCTION(0.14%)
TEXAS INLETS, INC. (3.48%)
DUSTROL, INC.(3.03%)
Contract # 01103007
Totals 5419912.44 0.00 6166065.78 99.9

CountyCOLLIN
Highway FM 2551
From FM 544
To FM 2514
CSJ 2056-01-045
Proj ID C 2056-1-45
Work Type GR., STR., BASE AND PAVEMENT
 
2.953 15783469.03 726301.14 9901715.56 62.7
Work Order 12-07-11
Work Began 11-26-12
Work Completed  
Time Computed 06-25-12
Contract Working Days 480
Addl Days Granted 5
Working Days Charged 387
Percent Time Used 79
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2056-01-045
ARTEX ELECTRIC, INC. (3.54%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 14.01%)
DALLAS LITE AND BARRICADE INC. (0.25%)
DUSTIN ALLEN, INC. (0.30%)
SOUTHWEST CONSTRUCTION SERVICES(0.46%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.90%)
WYLIE DRILLING & DRAINAGE, INC.(0.19%)
BROCK ENVIRONMENTAL, LLC (0.15%)
THELIN RECYCLING COMPANY, L.P. (0.16%)
DUSTROL, INC.(0.35%)
JM MATERIALS, INC. (4.40%)
PANTHER CREEK TRANSPORTATION, INC. (0.57%)
USA SWPPP INSPECTIONS, INC.(0.01%)
MCL CONTRACTING, LLC (0.01%)
BREDA COMPANY, INC.(0.00%)
CTBX, INC. (0.52%)
HERDEZ TRUCKING, INC.(0.00%)
A BROTHERS MILLING, LLC(0.41%)
Contract # 06113239
Totals 15783469.03 726301.14 9901715.56 62.7

CountyDENTON
Highway LP 288
From IH 35
To US 377 / US 380
CSJ 2250-02-016
Proj ID STP 2014(661)
Work Type FULL DEPTH CONCRETE PAVEMENT REPAIR
 
6.722 3653118.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-30-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 210
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2250-02-016
ALTUS TRAFFIC MANAGEMENT LLC (0.47%)
BRENDA PRICE TRUCKING(6.28%)
PEACHTREE CONSTRUCTION, LTD. (3.78%)
STRAIGHT LINE SAWING & SEALING (5.96%)
STRIPING TECHNOLOGY, L.P.(1.01%)
ACU CONSTRUCTION LLC (0.44%)
USA EROSION, INC.(0.36%)
Contract # 05143209
Totals 3653118.00 0.00 0.00 0.0

CountyDALLAS
Highway IH 635
From EAST OF CENTERVILLE RD.
To NORTHWEST HIGHWAY
CSJ 2374-02-124
Proj ID C 2374-2-124
Work Type GR, PVMT, SIGNS, PVMT MRKGS
 
1.288 7718650.04 147423.73 8450755.12 99.9
Work Order 10-12-09
Work Began 04-05-11
Work Completed  
Time Computed 04-10-10
Contract Working Days 459
Addl Days Granted 145
Working Days Charged 649
Percent Time Used 107
Contractor(s)
GLENN THURMAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2374-02-124
DALLAS LITE AND BARRICADE INC. (0.26%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(7.66%)
TEX OP CONSTRUCTION, LP(1.06%)
NORTH TEXAS BOMANITE, INC. (0.63%)
AMERICAN INTELOCK & MODULAR CONSTRUCTION, INC. (4.79%)
DT CONSTRUCTION SERVICES (0.52%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.77%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.92%)
CONCRETE CUTTING BY BOND (0.21%)
INDUS CONSTRUCTION, L.P. (0.54%)
INTEGRATED ROADWAY SERVICES, INC.(5.14%)
CRAIG OLDEN, INC.(1.40%)
LARRETT, INC.( 21.33%)
CB SERVICES, INC.(1.91%)
MIKE ALBERT, INC.(6.03%)
CONCRETE PENETRATING CO. (0.09%)
SOUTHWEST CONSTRUCTION SERVICES(2.19%)
Contract # 09093060
Totals 7718650.04 147423.73 8450755.12 99.9

CountyDALLAS
Highway IH 635
From IH 20
To IH 30
CSJ 2374-02-136
Proj ID CM 1402(030)
Work Type FULL ITS
 
14.781 6594770.84 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 240
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 2374-02-136
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143229
Totals 6594770.84 0.00 0.00 0.0

CountyDALLAS
Highway IH 20
From AT IH 45 RAMP FROM EB IH 20
To NB IH 45
CSJ 2374-03-057
Proj ID IM 0205(151)
Work Type ADD LANE TO DIRECT CONNECTION RAMP
 
1.418 5699998.00 0.00 4268601.09 74.8
Work Order 10-07-11
Work Began 01-12-12
Work Completed  
Time Computed 12-06-11
Contract Working Days 471
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 77
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 2374-03-057
ALLIANCE GEOTECHNICAL GROUP(0.00%)
AXIS CONTRACTING, INC. (1.14%)
BREDA COMPANY, INC.(0.96%)
BROCK ENVIRONMENTAL, LLC (0.71%)
CONCRETE CUTTING BY BOND (0.26%)
DUSTIN ALLEN, INC. (1.41%)
DUSTROL, INC.(0.87%)
FOUNDATION DRILLERS, INC.(1.05%)
HIGHWAY TECHNOLOGIES, INC. (0.55%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (1.12%)
MELS ELECTRIC, L.P.(0.34%)
STRIPING TECHNOLOGY, L.P.(0.93%)
GREAT WESTERN ERECTORS (0.06%)
ERWIN STEEL WORKS, LLC (0.11%)
RG PAINTING(0.39%)
MAGNUM SAWING(0.34%)
D & D STUD WELDING (0.17%)
Contract # 08113245
Totals 5699998.00 0.00 4268601.09 74.8

CountyDALLAS
Highway IH 20
From IH 35E
To IH 45
CSJ 2374-03-076
Proj ID CM 2013(987)
Work Type ITS
 
14.982 1858920.39 115158.68 379398.23 20.4
Work Order 03-13-14
Work Began 07-15-14
Work Completed  
Time Computed 06-12-14
Contract Working Days 164
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 28
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2374-03-076
CITY BUILD UTILITY SUPPLY(3.38%)
ALTUS TRAFFIC MANAGEMENT LLC (0.71%)
ODUM SERVICES, L.P.(1.51%)
INTEGRATED ROADWAY SERVICES, INC.( 39.01%)
ADVANCED FIBER SERVICES(0.79%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.41%)
Contract # 09133012
Totals 1858920.39 115158.68 379398.23 20.4

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8