Monthly State Let Construction Report For Dallas District As Of Jul 12, 2016 Page 7 Of 9

Last Update: Tuesday, July 12, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyELLIS
Highway FM 664
From NORTH OF US 287
To SOUTH OF RED OAK CREEK IN OVILLA
CSJ 1051-01-042
Proj ID STP 2015(654)
Work Type ADD 3 - FOOT PAVED SHOULDERS
 
7.303 11142221.20 551503.27 5587917.82 50.1
Work Order 04-20-15
Work Began 06-22-15
Work Completed  
Time Computed 12-23-15
Contract Working Days 293
Addl Days Granted 29
Working Days Charged 256
Percent Time Used 79
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1051-01-042
BROCK ENVIRONMENTAL SERVICES, LLC(0.31%)
CROSSROADS, L.P. (0.48%)
DUSTROL, INC.(1.95%)
STRIPING TECHNOLOGY, L.P.(0.63%)
PEACHTREE CONSTRUCTION, LTD. ( 33.79%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.89%)
JE CASEY, LLC(1.56%)
SYNERGY SIGNS & SERVICES (0.72%)
OSCAR ORDUNO, INC. (2.36%)
BRENDA PRICE TRUCKING(1.09%)
AAA DRILLING FOUNDATION CO., INC.(0.32%)
FORTSON CONTRACTING, INC.(0.58%)
LONE STAR BARRIER SERVICES, LLC(0.53%)
Contract # 03153213
Totals 11142221.20 551503.27 5587917.82 50.1

CountyELLIS
Highway FM 876
From AT BIG ONION CREEK
To .
CSJ 1051-02-017
Proj ID BR 2015(591)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.255 1721378.55 195555.59 1274239.97 74.0
Work Order 04-03-15
Work Began 09-15-15
Work Completed  
Time Computed 09-15-15
Contract Working Days 360
Addl Days Granted 0
Working Days Charged 202
Percent Time Used 56
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 1051-02-017
N-LINE TRAFFIC MAINTENANCE, L.P. (0.93%)
IOWA BRIDGE & CULVERT, LC(3.59%)
STRIPING TECHNOLOGY, L.P.(1.60%)
GJ SEEDING, LLC(5.27%)
FOUNDATION DRILLERS, INC.(3.17%)
FRAIRE"S REBAR, INC(4.42%)
F & K BUILDERS (2.81%)
PEACHTREE CONSTRUCTION, LTD. (6.81%)
CLEMONS TRUCKING (2.17%)
JANEK & WHITTEN CONSTRUCTION INC.(0.43%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(5.70%)
FORTSON CONTRACTING, INC.(1.45%)
Contract # 02153207
Totals 1721378.55 195555.59 1274239.97 74.0

CountyTARRANT
Highway IH 30
From 0.5 MILES WEST OF N. FIELDER ROAD
To DALLAS/TARRANT COUNTY LINE
CSJ 1068-02-135
Proj ID C 1068-2-135
Work Type ITS, ETC, SIGNS
 
6.091 6960302.24 2663.52 6571085.84 94.4
CountyDALLAS
Highway IH 30
From TARRANT/DALLAS COUNTY LINE
To SYLVAN AVE.
CSJ 1068-04-147
Proj ID IM 0305(082)
Work Type STR, GR, PVMT, PVMT MKGS, SIGNS, ITS
 
12.664 56121468.07 113423.55 57701346.59 99.9
Work Order 02-28-13
Work Began 03-25-13
Work Completed  
Time Computed 03-16-13
Contract Working Days 728
Addl Days Granted 84
Working Days Charged 955
Percent Time Used 117
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-147
COWTOWN TRAFFIC CONTROL, INC.(0.04%)
THE ANCHOR GROUP, INC. (0.02%)
ANTIGO CONSTRUCTION, INC.(0.02%)
DUSTROL, INC.(0.33%)
DUSTIN ALLEN, INC. (0.41%)
HOUSTON SAWING & DRILLING(0.02%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.09%)
PENHALL COMPANY(0.06%)
STORM WATER MANAGEMENT, INC. (0.13%)
VSTRUCTURAL LLC(0.42%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.12%)
W.O.E. CONSTRUCTION(0.64%)
STRIPING TECHNOLOGY, L.P.(2.08%)
MICA CORPORATION ( 19.67%)
W. W. FOUNDATION DRILLING, LTD.(2.65%)
K & S UTILITY CONTRACTORS, INC.(4.66%)
INDUS CONSTRUCTION, L.P. (0.56%)
PRESSURE CLEANING SERVICE, INC. DBA WATERBLASTING.COM(0.06%)
RAMBO CONTRACTING, INC.(1.19%)
NORTH TEXAS REBAR, LLC (0.00%)
HERDEZ TRUCKING, INC.(0.09%)
J.H. PAINTING COMPANY(0.41%)
MCL CONTRACTING, LLC (0.09%)
CB SERVICES, INC.(0.06%)
VFC, INC (0.11%)
STRIPE-A-ZONE, INC.(1.00%)
DALLAS LITE AND BARRICADE INC. (0.00%)
Contract # 12123201
Totals 63081770.31 116087.07 64272432.43 99.9

CountyDALLAS
Highway IH 30
From BELTLINE ROAD
To MAC ARTHUR BLVD.
CSJ 1068-04-122
Proj ID C 1068-4-122
Work Type GR, STRS & PAV
 
1.522 24620668.27 0.00 0.00 0.0
CountyDALLAS
Highway IH 30
From BELT LINE RD
To MACARTHUR RD
CSJ 1068-04-137
Proj ID ROW 1068-4-137
Work Type ROW ACQ, UTIL & RELOC
 
0.760 565255.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-16-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 538
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAYDON CENTRAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-122
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(2.91%)
LAYFIELD CONSTRUCTION, INC (0.24%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.38%)
BOWMAN ENGINEERING & CONSTRUCTION, INC.(9.83%)
Contract # 12153004
Totals 25185923.27 0.00 0.00 0.0

CountyDALLAS
Highway IH 30
From NW 7TH STREET
To BELTLINE ROAD
CSJ 1068-04-148
Proj ID STP 2016(740)MM
Work Type GR, DRN, RET WLS, CONC PAV, SIG, PV MRKS
 
1.011 7991673.30 209515.31 290533.24 3.6
Work Order 04-01-16
Work Began 05-18-16
Work Completed  
Time Computed 05-18-16
Contract Working Days 380
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 7
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-148
ALTUS TRAFFIC MANAGEMENT LLC (0.17%)
W.O.E. CONSTRUCTION(2.42%)
C.T. AND S. METALWORKS, INC. (0.37%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.22%)
FORTSON CONTRACTING, INC.(0.31%)
K & S UTILITY CONTRACTORS, INC.( 12.19%)
MICA CORPORATION (3.52%)
STORM WATER MANAGEMENT, INC. (0.23%)
STRIPE-A-ZONE, INC.(1.02%)
SYNERGY SIGNS & SERVICES (0.36%)
TEXAS BOMANITE (0.05%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.32%)
TEXAS SHAFTS, INC. (0.67%)
Contract # 02163225
Totals 7991673.30 209515.31 290533.24 3.6

CountyDALLAS
Highway IH 30
From COCKRELL HILL ROAD
To WESTMORELAND RD IN DALLAS
CSJ 1068-04-154
Proj ID C 1068-4-154
Work Type GRADING, PAVEMENT, SIGNS, PVMT MKGS
 
2.704 9814841.51 108159.23 7860273.83 81.2
Work Order 09-09-14
Work Began 11-11-14
Work Completed  
Time Computed 09-25-14
Contract Working Days 321
Addl Days Granted 5
Working Days Charged 429
Percent Time Used 131
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-154
K & S UTILITY CONTRACTORS, INC.(9.08%)
OSCAR ORDUNO, INC. (4.26%)
STORM WATER MANAGEMENT, INC. (0.29%)
SLATON BROTHERS, INC.(4.57%)
W.O.E. CONSTRUCTION(7.63%)
Contract # 07143214
Totals 9814841.51 108159.23 7860273.83 81.2

CountyKAUFMAN
Highway FM 741
From US 175
To EAST OF FM 548
CSJ 1092-01-017
Proj ID STP 2015(778)
Work Type GR, BASE, ACP OVERLAY, PVMT MKGS
 
7.726 4550316.19 60951.75 4398652.75 98.1
Work Order 03-23-15
Work Began 06-03-15
Work Completed  
Time Computed 04-23-15
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 255
Percent Time Used 136
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1092-01-017
ALTUS TRAFFIC MANAGEMENT LLC (0.26%)
TEXAS ENVIRONMENTAL MANAGEMENT SA, INC.(4.68%)
DUSTROL, INC.(4.57%)
MARCOM"S MOWING SERVICE, LLC (1.16%)
J & M CONTRACTING, COMPANY (7.65%)
STRIPING TECHNOLOGY, L.P.(1.43%)
FORTSON CONTRACTING, INC.(0.60%)
C & J TREE SERVICE (0.03%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (4.68%)
Contract # 02153235
Totals 4550316.19 60951.75 4398652.75 98.1

CountyELLIS
Highway FM 875
From AT WAXAHACHIE CREEK
To .
CSJ 1159-01-022
Proj ID BR 2013(604)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.471 3724841.00 26660.86 26660.86 0.7
Work Order 08-13-15
Work Began 00-00-00
Work Completed  
Time Computed 12-11-15
Contract Working Days 467
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 1159-01-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153025
Totals 3724841.00 26660.86 26660.86 0.7

CountyELLIS
Highway FM 879
From 2.1 MILES WEST OF IKE RD
To 0.3 MILE WEST OF FM 1722
CSJ 1159-02-032
Proj ID STP 1502(328)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
6.667 9549753.04 522996.75 3404554.93 35.6
Work Order 07-31-15
Work Began 09-03-15
Work Completed  
Time Computed 07-31-15
Contract Working Days 315
Addl Days Granted 12
Working Days Charged 221
Percent Time Used 67
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1159-02-032
CROSS ROADS, L.P.(0.38%)
BROCK ENVIRONMENTAL SERVICES, LLC(0.19%)
ACU CONSTRUCTION LLC (1.24%)
STRIPING TECHNOLOGY, L.P.(0.61%)
SYNERGY SIGNS & SERVICES (0.28%)
FORTSON CONTRACTING, INC.(1.62%)
NORTH EASTERN PAVERS (4.90%)
PEACHTREE CONSTRUCTION, LTD. ( 13.21%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (4.95%)
HAYWARD BAKER, INC.(0.67%)
BRENDA PRICE TRUCKING(6.89%)
Contract # 06153225
Totals 9549753.04 522996.75 3404554.93 35.6

CountyELLIS
Highway FM 984
From AT DRAW, 1.7 MI SOUTH OF SH 34
To .
CSJ 1211-01-018
Proj ID BR 2015(483)
Work Type REPL BR AND APPR
 
0.117 879623.40 0.00 53517.71 6.0
CountyELLIS
Highway FM 984
From AT ONION CREEK RELIEF #1 AND #2
To .
CSJ 1211-01-019
Proj ID BR 2015(484)
Work Type REPL BR
 
0.156 1453823.50 0.00 304074.80 20.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-02-15
Work Began 02-25-16
Work Completed  
Time Computed 02-25-16
Contract Working Days 379
Addl Days Granted 0
Working Days Charged 66
Percent Time Used 17
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 1211-01-018
FORTSON CONTRACTING, INC.(2.16%)
USA EROSION, INC.(3.94%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.48%)
STRIPING TECHNOLOGY, L.P.(1.23%)
TEX OP CONSTRUCTION, LP(1.11%)
W. W. FOUNDATION DRILLING, LTD.(5.36%)
Contract # 01153012
Totals 2333446.90 0.00 357592.51 15.3

CountyKAUFMAN
Highway FM 1388
From FM 148
To US 175
CSJ 1217-03-019
Proj ID STP 2016(360)
Work Type GR, BASE, ACP OVERLAY, PVMT MKGS
 
12.030 17608683.44 236445.58 1943354.51 11.0
CountyKAUFMAN
Highway FM 1388
From AT KINGS CREEK RELIEF #2
To .
CSJ 1217-03-020
Proj ID BR 2016(361)
Work Type REPLACE BRIDGE
 
0.495 4432389.14 0.00 2630.00 0.0
Work Order 01-29-16
Work Began 04-11-16
Work Completed  
Time Computed 04-11-16
Contract Working Days 580
Addl Days Granted 0
Working Days Charged 69
Percent Time Used 11
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1217-03-019
ALTUS TRAFFIC MANAGEMENT LLC (0.13%)
SOUTHWEST CONSTRUCTION SERVICES(0.39%)
K & S UTILITY CONTRACTORS, INC.(9.31%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.72%)
A-CORE, INC. (0.02%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(0.05%)
PEACHTREE CONSTRUCTION, LTD. (4.40%)
INDUS CONSTRUCTION, L.P. (0.07%)
SOUTHERN CROSS CONTRACTORS, LLC(0.08%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(5.40%)
SYNERGY SIGNS & SERVICES, LLC(0.39%)
FARR FOUNDATION, INC.(0.56%)
FORTSON CONTRACTING, INC.(0.74%)
TRP CONSTRUCTION GROUP, LLC(0.60%)
HERDEZ TRUCKING, INC.(2.17%)
RAMBO CONTRACTING, INC.(4.73%)
TEXOP CONSTRUCTION (0.07%)
Contract # 12153205
Totals 22041072.58 236445.58 1945984.51 8.8

CountyNAVARRO
Highway FM 1126
From AT CHAMBERS CREEK, SW OF IH 45
To .
CSJ 1289-01-029
Proj ID BR 1602(046)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.890 6714487.74 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-02-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 386
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1289-01-029
A. L. HELMCAMP, INC. ( 22.43%)
IOWA BRIDGE & CULVERT, LC(1.25%)
AARON CONCRETE CONTRACTORS, L.P. (3.51%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.82%)
FORTSON CONTRACTING, INC.(0.29%)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(0.29%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.26%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.42%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.37%)
Contract # 04163237
Totals 6714487.74 0.00 0.00 0.0

CountyDENTON
Highway FM 1171
From WEST OF US 377
To WEST OF SHILOH RD
CSJ 1311-01-034
Proj ID C 1311-1-34
Work Type GR, STRS, BASE, CRCP, PVMT MKGS, SIGNS
 
7.011 45721253.16 1659661.28 42067487.91 92.0
Work Order 06-05-13
Work Began 06-02-14
Work Completed  
Time Computed 03-02-14
Contract Working Days 693
Addl Days Granted 0
Working Days Charged 520
Percent Time Used 75
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1311-01-034
BREDA COMPANY, INC.(0.96%)
BUYERS BARRICADES, INC.(0.20%)
CINTEREX US, INC.(1.17%)
CLLA GROUP, LLC(9.39%)
DUSTROL, INC.(0.30%)
INTEGRATED ROADWAY SERVICES, INC.(2.34%)
JAGOE-PUBLIC COMPANY ( 14.10%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.74%)
THELIN RECYCLING COMPANY, L.P. (0.16%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.10%)
W.O.E. CONSTRUCTION(0.28%)
WYLIE DRILLING & DRAINAGE, INC.(0.83%)
VENUS CONSTRUCTION (7.23%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.35%)
SLATON BROTHERS, INC.(0.58%)
CB SERVICES, INC.(0.10%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.07%)
LLOYD D. NABORS DEMOLITION LLC (0.12%)
STORM WATER MANAGEMENT, INC. (0.07%)
THE LANE CONSTRUCTION CORPORATION(0.93%)
SCOTT DERR PAINTING CO, LLC(0.06%)
Contract # 03133002
Totals 45721253.16 1659661.28 42067487.91 92.0

CountyDENTON
Highway FM 1171
From ON CORPS OF ENGINEERS PROPERTY
To NEAR WHITE'S BRANCH
CSJ 1311-01-053
Proj ID C 1311-1-53
Work Type TREES AND PLANTS
 
0.001 148908.50 0.00 61596.76 41.3
CountyDENTON
Highway FM 2499
From FM 2181
To HICKORY CREEK
CSJ 2681-01-022
Proj ID NH 1502(094)
Work Type LANDSCAPE DEVELOPMENT
 
1.112 299148.05 0.00 277336.91 92.7
Work Order 07-20-15
Work Began 08-04-15
Work Completed  
Time Computed 08-04-15
Contract Working Days 60
Addl Days Granted 2
Working Days Charged 34
Percent Time Used 54
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2681-01-022
ALTUS TRAFFIC MANAGEMENT LLC (0.85%)
AMAYA UTILITY(0.56%)
QUICK SET CONCRETE, INC. (5.50%)
Contract # 05153018
Totals 448056.55 0.00 338933.67 75.6

CountyDENTON
Highway FM 1385
From US 380
To APPROX. 2 MILES NORTH OF FM 428
CSJ 1315-01-025
Proj ID STP 1402(028)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
7.588 9063184.19 343924.31 6687555.92 73.7
Work Order 12-10-14
Work Began 07-10-15
Work Completed  
Time Computed 06-08-15
Contract Working Days 378
Addl Days Granted 0
Working Days Charged 251
Percent Time Used 66
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1315-01-025
ALTUS TRAFFIC MANAGEMENT LLC (0.54%)
ASHLAR CONTRACTING COMPANY (8.41%)
SAMMY SMALLWOOD COMPANY(0.61%)
STRIPING TECHNOLOGY, L.P.(1.77%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(7.84%)
W.S. CONSTRUCTION COMPANY(6.71%)
JM YANEZ CONSTRUCTION(8.03%)
Contract # 09143208
Totals 9063184.19 343924.31 6687555.92 73.7

CountyDENTON
Highway FM 423
From US 380
To 0.8 MI SOUTH OF FM 2934
CSJ 1315-02-009
Proj ID C 1315-2-9
Work Type WIDEN TO 6 LANE DIVIDED URBAN
 
3.488 29826069.73 929688.50 18389289.72 61.6
Work Order 12-12-13
Work Began 10-08-14
Work Completed  
Time Computed 09-08-14
Contract Working Days 603
Addl Days Granted 0
Working Days Charged 440
Percent Time Used 72
Contractor(s)
MCM
SUBCONTRACTOR(S) FOR CCSJ: 1315-02-009
TOTAL HIGHWAY MAINTENANCE, LLC (0.96%)
STORM WATER MANAGEMENT, INC. (0.28%)
BOWMAN ENGINEERING & CONSULTING, INC.(0.84%)
FORTSON CONTRACTING, INC.(0.09%)
IEA, INC (9.39%)
JAGOE-PUBLIC COMPANY ( 10.82%)
OSCAR ORDUNO, INC. (0.23%)
ROADWAY SOLUTIONS, INC.(4.78%)
ROBERTS TRUCKING (1.98%)
RUSSO CORPORATION(0.55%)
DUSTROL, INC.(0.49%)
W.O.E. CONSTRUCTION(4.50%)
TRANSPORT TRUST(0.96%)
RICHMOND HYDROMULCH AND SEEDING, LLC (0.27%)
Contract # 09133204
Totals 29826069.73 929688.50 18389289.72 61.6

CountyCOLLIN
Highway FM 1378
From 585 SOUTH OF WHITE ROCK CREEK
To NORTH OF WHITE ROCK CREEK
CSJ 1392-01-035
Proj ID BR 2014(872)
Work Type REPL BRIDGE
 
0.526 1788995.75 143520.48 1000434.01 55.9
Work Order 10-09-14
Work Began 08-10-15
Work Completed  
Time Computed 04-07-15
Contract Working Days 300
Addl Days Granted 10
Working Days Charged 220
Percent Time Used 70
Contractor(s)
ACCELERATED CRITICAL PATH, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1392-01-035
BREDA COMPANY, INC.(0.40%)
CROSSROADS, L.P. (0.90%)
D & S ENGINEERING LABS (0.45%)
DUSTROL, INC.(2.56%)
FOUNDATION DRILLERS, INC.(0.91%)
CRAIG OLDEN, INC.(1.77%)
LINDAMOOD DEMOLITION, INC. (1.39%)
MCRYAN HAULING, INC. (1.87%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.32%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.08%)
LONE STAR BARRIER SERVICES, LLC(0.90%)
MARCOM"S MOWING SERVICE, LLC (0.70%)
Contract # 07143231
Totals 1788995.75 143520.48 1000434.01 55.9

CountyKAUFMAN
Highway FM 1836
From FM 2515
To FM 90
CSJ 1397-01-030
Proj ID STP 2016(289)
Work Type SHLDR WDN, STR EXT, REMX, SC, PAV MRKS
 
6.905 6141935.93 6283.00 45315.00 0.7
Work Order 01-29-16
Work Began 04-19-16
Work Completed  
Time Computed 04-18-16
Contract Working Days 218
Addl Days Granted 0
Working Days Charged 44
Percent Time Used 20
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 1397-01-030
PEACHTREE CONSTRUCTION, LTD. (1.77%)
S & S BRIDGE PAINTING, INC.(4.51%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.11%)
TRP CONSTRUCTION GROUP, LLC(1.23%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.55%)
DUSTIN ALLEN, INC. (1.46%)
FARR FOUNDATION, INC.(1.51%)
K & S UTILITY CONTRACTORS, INC.(6.21%)
WITHERS CONSTRUCTION, LLC(0.63%)
ALTUS TRAFFIC MANAGEMENT LLC (0.20%)
CAMBRIDGEMOEN LLC(2.28%)
GIBSON & ASSOCIATES, INC.(1.87%)
Contract # 11153024
Totals 6141935.93 6283.00 45315.00 0.7

CountyKAUFMAN
Highway FM 1836
From SH 34
To 0.28 MI EAST OF CR 146
CSJ 1397-01-031
Proj ID C 1397-1-31
Work Type PROVIDE ADDITIONAL PAVED SURFACE
 
4.269 5943147.30 0.00 2640.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 166
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1397-01-031
ALTUS TRAFFIC MANAGEMENT LLC (0.17%)
ODUM SERVICES, L.P.(1.02%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.55%)
J & M CONTRACTING, COMPANY ( 20.60%)
Contract # 01163240
Totals 5943147.30 0.00 2640.00 0.0

CountyELLIS
Highway FM 55
From AT LITTLE ONION CREEK
To .
CSJ 1451-01-020
Proj ID BR 2005(274)
Work Type REPLACE BRIDGES AND APPROACHES
 
0.312 2010620.16 50250.00 351557.23 17.4
Work Order 07-24-15
Work Began 02-18-16
Work Completed  
Time Computed 11-21-15
Contract Working Days 340
Addl Days Granted 0
Working Days Charged 93
Percent Time Used 27
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-020
TEXOP CONSTRUCTION (1.10%)
FORTSON CONTRACTING, INC.(2.27%)
SAN-ANN-CO., INC.(0.96%)
USA EROSION, INC.(4.31%)
STRIPING TECHNOLOGY, L.P.(1.50%)
W. W. FOUNDATION DRILLING, LTD.(2.35%)
Contract # 05153220
Totals 2010620.16 50250.00 351557.23 17.4

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9