Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDALLAS
Highway CS
From S MARSALIS AVE AT FIVEMILE CREEK
To .
CSJ 0918-45-761
Proj ID BR 2007(306)
Work Type REPL BR & APPRS
 
0.077 2688948.21 107962.16 1455324.88 54.1
CountyDALLAS
Highway CS
From S MARSALIS AVE AT FIVEMILE CREEK
To .
CSJ 0918-47-085
Proj ID RW 918-47-85
Work Type ADJUSTMENT OF UTILITIES
 
0.090 255486.60 0.00 72407.00 28.3
Work Order 09-22-14
Work Began 03-30-15
Work Completed  
Time Computed 11-21-14
Contract Working Days 353
Addl Days Granted 0
Working Days Charged 351
Percent Time Used 99
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-45-761
ALTUS TRAFFIC MANAGEMENT LLC (0.97%)
BROCK ENVIRONMENTAL, LLC (0.53%)
ATS DRILLING, INC. (7.00%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(1.19%)
FRAIRE"S REBAR, INC(8.53%)
STRIPE-A-ZONE, INC.(0.16%)
ACTION SERVICES(0.29%)
FORTSON CONTRACTING, INC.(0.26%)
IOWA BRIDGE & CULVERT, LC(0.33%)
METRO CUTTING AND SEALING, INC.(0.20%)
DUSTROL, INC.(0.30%)
J & M MANHOLE CONSTRUCTION (0.30%)
RICE TUNNELING & BORING, INC.(0.25%)
MAGNUM MANHOLE & UNDERGROUND COMPANY (0.36%)
CLEMONS TRUCKING (1.23%)
FOUNDATION DRILLERS, INC.(1.17%)
K & A STEEL, LLC (1.73%)
XIT PAVING AND CONSTRUCTION INC. (1.11%)
F & K BUILDERS (4.45%)
Contract # 06143014
Totals 2944434.81 107962.16 1527731.88 51.8

CountyDALLAS
Highway CS
From RED OAK RD AT TEN MILE CREEK
To IN THE CITY OF LANCASTER
CSJ 0918-45-791
Proj ID BR 2013(493)
Work Type REHAB BRIDGE AND APPROACHES
 
0.100 1305085.00 37040.00 37040.00 2.8
Work Order 03-15-16
Work Began 05-17-16
Work Completed  
Time Computed 05-17-16
Contract Working Days 247
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 2
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-45-791
PENHALL COMPANY(0.24%)
PEACHTREE CONSTRUCTION, LTD. (1.41%)
S&S BRIDGE PAINTING( 22.66%)
ODUM SERVICES, L.P.(1.39%)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(0.46%)
ACU CONSTRUCTION LLC (1.01%)
USA SWPPP INSPECTIONS, INC.(2.02%)
Contract # 11153230
Totals 1305085.00 37040.00 37040.00 2.8

CountyDALLAS
Highway CS
From ON WHITLOCK RD, FROM IH 35E
To OLD DENTON RD IN CARROLLTON
CSJ 0918-45-864
Proj ID STP 2009(860)MM
Work Type GR, STRS & SURF
 
0.505 3063573.24 0.00 12988.07 0.4
CountyDALLAS
Highway CS
From ON WHITLOCK RD, FROM IH 35E
To OLD DENTON RD IN CARROLLTON
CSJ 0918-47-116
Proj ID RW 918-47-116
Work Type ADJUSTMENT OF UTILITIES IN CONSTRUC
 
0.505 372163.90 0.00 0.00 0.0
Work Order 09-11-14
Work Began 00-00-00
Work Completed  
Time Computed 12-09-14
Contract Working Days 276
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TISEO PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0918-45-864
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143222
Totals 3435737.14 0.00 12988.07 0.3

CountyDENTON
Highway PW
From AT RAY ROBERTS (ISLE DUBOIS)
To STATE PARK
CSJ 0918-46-269
Proj ID C 918-46-269
Work Type REHABILITATE ROADS
 
0.001 1587178.56 0.00 1753072.90 99.9
Work Order 05-21-15
Work Began 08-07-15
Work Completed  
Time Computed 06-21-15
Contract Working Days 91
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 69
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0918-46-269
ALTUS TRAFFIC MANAGEMENT LLC (0.21%)
STRIPING TECHNOLOGY, L.P.(9.73%)
USA SWPPP INSPECTIONS, INC.(1.90%)
Contract # 04153243
Totals 1587178.56 0.00 1753072.90 99.9

CountyDALLAS
Highway VA
From VARIOUS LOCATIONS ON STATE HIGHWAYS
To IN DALLAS COUNTY
CSJ 0918-47-052
Proj ID STP 1102(553)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2270944.30 0.00 2162311.95 95.2
Work Order 07-25-14
Work Began 09-02-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 244
Addl Days Granted 0
Working Days Charged 239
Percent Time Used 97
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-052
CLASSIC TEJAS CONSTRUCTION, INC. ( 17.31%)
ACTION SERVICES(1.21%)
Contract # 06143039
Totals 2270944.30 0.00 2162311.95 95.2

CountyDALLAS
Highway VA
From VARIOUS LOCATIONS ON STATE HIGHWAYS
To IN DALLAS COUNTY
CSJ 0918-47-100
Proj ID NH 2015(653)
Work Type CONSTRUCT CURB RAMPS
 
0.001 3464886.46 174589.70 2835393.60 81.8
Work Order 04-22-15
Work Began 06-22-15
Work Completed  
Time Computed 05-08-15
Contract Working Days 315
Addl Days Granted 0
Working Days Charged 243
Percent Time Used 77
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-100
CLASSIC TEJAS CONSTRUCTION, INC. ( 10.16%)
Contract # 03153224
Totals 3464886.46 174589.70 2835393.60 81.8

CountyDALLAS
Highway CS
From JEFFERSON ST AT MERRIFIELD ST
To .
CSJ 0918-47-101
Proj ID STP 1502(494)HES
Work Type INSTALL TRAFFIC SIGNAL
 
0.100 395282.15 39860.85 279079.82 70.6
CountyDALLAS
Highway CS
From WESTMORELAND AT CLARENDON
To .
CSJ 0918-47-103
Proj ID STP 1502(496)HES
Work Type IMPROVE TRAFFIC SIGNALS
 
0.100 257625.45 225.00 22725.00 8.8
CountyDALLAS
Highway CS
From MCKINNEY AT MAPLE
To .
CSJ 0918-47-110
Proj ID STP 1502(495)HES
Work Type IMPROVE TRAFFIC SIGNALS
 
0.100 150048.25 0.00 22500.00 14.9
Work Order 10-05-15
Work Began 02-29-16
Work Completed  
Time Computed 02-29-16
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 42
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-101
DALLAS LITE AND BARRICADE INC. (1.43%)
MABAK DIRECTIONAL DRILLING (4.36%)
AUGER DRILLING, INC. (0.99%)
Contract # 07153012
Totals 802955.85 40085.85 324304.82 40.3

CountyDALLAS
Highway CS
From BELT LINE ROAD AT DALLAS PKWY
To .
CSJ 0918-47-120
Proj ID STP 1602(110)HES
Work Type IMPROVE TRAFFIC SIGNALS
 
1.000 1300500.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 172
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-120
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163228
Totals 1300500.00 0.00 0.00 0.0

CountyCOLLIN
Highway FM 546
From SH 5
To EAST OF COUNTRY LN/AIRPORT RD
CSJ 1013-01-026
Proj ID C 1013-1-26
Work Type GR, PVMT, STR, SIGNS, PVMT MKGS
 
1.724 17391616.98 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 411
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1013-01-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163037
Totals 17391616.98 0.00 0.00 0.0

CountyCOLLIN
Highway FM 546
From WEST OF THE CROSSINGS RD
To FM 982
CSJ 1013-01-028
Proj ID STP 1402(180)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
5.051 5997170.81 30564.30 5742412.42 96.9
Work Order 09-15-14
Work Began 12-01-14
Work Completed  
Time Computed 12-01-14
Contract Working Days 263
Addl Days Granted 21
Working Days Charged 332
Percent Time Used 116
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1013-01-028
TOTAL HIGHWAY MAINTENANCE, LLC (1.22%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(0.43%)
FARR FOUNDATION, INC.(3.02%)
EROSION CONTROL MANAGEMENT SERVICES(0.36%)
K & S UTILITY CONTRACTORS, INC.( 21.42%)
MARCOM"S MOWING SERVICE, LLC (3.13%)
ACU CONSTRUCTION LLC (0.45%)
GOLDEN TREE MAINTENANCE(0.13%)
IOWA BRIDGE & CULVERT, LC(0.51%)
Contract # 07143245
Totals 5997170.81 30564.30 5742412.42 96.9

CountyROCKWALL
Highway FM 548
From SH 276
To SH 66
CSJ 1014-02-041
Proj ID STP 2016(145)
Work Type WDN, STR, REMX, OL, PV MRKS
 
12.751 13784401.35 345062.97 1029518.05 7.4
Work Order 02-03-16
Work Began 03-28-16
Work Completed  
Time Computed 03-28-16
Contract Working Days 363
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 16
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1014-02-041
TEXOP CONSTRUCTION (1.79%)
EROSION CONTROL MANAGEMENT SERVICES(0.48%)
PREMIER PAVING, LTD. ( 22.61%)
SCOTT PAVING, INC. (3.33%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.66%)
TRP CONSTRUCTION GROUP, LLC(0.94%)
DALLAS LITE AND BARRICADE INC. (0.54%)
RICE ENVIRONMENTAL SERVICES(1.23%)
Contract # 10153205
Totals 13784401.35 345062.97 1029518.05 7.4

CountyROCKWALL
Highway FM 740
From FM 549 / FM 550 INTERSECTION
To FM 1140 NORTH IN HEATH
CSJ 1014-03-049
Proj ID C 1014-3-49
Work Type GRADING, STRUCTURES, DRAINAGE, & PVMT
 
1.856 12967453.42 110781.81 2116027.66 16.3
Work Order 11-14-13
Work Began 07-20-15
Work Completed  
Time Computed 08-11-14
Contract Working Days 412
Addl Days Granted 0
Working Days Charged 115
Percent Time Used 27
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1014-03-049
W.O.E. CONSTRUCTION(0.30%)
TEX OP CONSTRUCTION, LP(2.01%)
TEXAS INLETS, INC. (3.62%)
SYNERGY SIGNS & SERVICES, LLC(0.37%)
HAYWARD BAKER, INC.(0.81%)
STRIPING TECHNOLOGY, L.P.(0.99%)
USA SWPPP INSPECTIONS, INC.(1.15%)
PREMIER PAVING, LTD. (4.86%)
DURABLE SPECIALTIES, INC.(3.25%)
BREDA COMPANY, INC.(0.67%)
BUYERS BARRICADES, INC.(0.31%)
BRENDA PRICE TRUCKING(4.98%)
FANNIN TREE FARM, LTD(0.33%)
Contract # 08133209
Totals 12967453.42 110781.81 2116027.66 16.3

CountyROCKWALL
Highway FM 3549
From SH 66
To FM 552
CSJ 1015-01-022
Proj ID STP 2015(590)
Work Type BASE REPAIR, LEVEL UP, OVERLAY
 
2.319 2576274.62 133619.92 2828863.31 99.9
Work Order 03-30-15
Work Began 08-05-15
Work Completed  
Time Computed 04-15-15
Contract Working Days 165
Addl Days Granted 31
Working Days Charged 195
Percent Time Used 99
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 1015-01-022
PEACHTREE CONSTRUCTION, LTD. ( 14.69%)
K & S UTILITY CONTRACTORS, INC.(9.85%)
ALTUS TRAFFIC MANAGEMENT LLC (0.36%)
USA SWPPP INSPECTIONS, INC.(2.61%)
STRIPING TECHNOLOGY, L.P.(1.47%)
BAHENA CONSTRUCTION CO.,INC. (0.28%)
RAMBO CONTRACTING, INC.(2.41%)
Contract # 02153221
Totals 2576274.62 133619.92 2828863.31 99.9

CountyROCKWALL
Highway FM 551
From NORTH OF IH 30
To SH 66
CSJ 1016-01-027
Proj ID STP 2014(766)
Work Type BASE REPAIR, LEVEL UP, OVERLAY
 
2.479 5349450.72 542754.38 3370417.92 63.0
Work Order 08-07-14
Work Began 06-15-15
Work Completed  
Time Computed 02-03-15
Contract Working Days 126
Addl Days Granted 62
Working Days Charged 162
Percent Time Used 86
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1016-01-027
DUSTROL, INC.(4.85%)
PREMIER PAVING, LTD. ( 29.61%)
USA SWPPP INSPECTIONS, INC.(1.91%)
FORTSON CONTRACTING, INC.(1.26%)
STRIPING TECHNOLOGY, L.P.(0.71%)
HAYWOOD BAKER(1.24%)
SYNERGY SIGNS & SERVICES, LLC(0.86%)
BRENDA PRICE TRUCKING(1.08%)
FANNIN TREE FARM, LTD(0.13%)
Contract # 06143232
Totals 5349450.72 542754.38 3370417.92 63.0

CountyROCKWALL
Highway FM 1138
From SH 66
To COLLIN COUNTY LINE
CSJ 1016-03-013
Proj ID STP 1602(216)
Work Type BASE REPAIR, LEVEL UP, OVERLAY
 
1.065 1329420.20 0.00 0.00 0.0
CountyROCKWALL
Highway FM 35
From IH 30
To HUNT COUNTY LINE
CSJ 1017-02-012
Proj ID STP 1602(216)
Work Type MILL, BS REP, OV
 
1.539 627099.96 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1016-03-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163033
Totals 1956520.16 0.00 0.00 0.0

CountyELLIS
Highway FM 85
From IH 45
To FM 1182
CSJ 1050-01-017
Proj ID STP 2016(146)
Work Type ACP OVERLAY, GR, STR, PVMT MKGS
 
8.401 12874396.21 544387.86 1599925.36 12.4
Work Order 12-21-15
Work Began 03-14-16
Work Completed  
Time Computed 03-14-16
Contract Working Days 490
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 10
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1050-01-017
FARR FOUNDATION, INC.(0.78%)
LONE STAR BARRIER SERVICES, LLC(0.82%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.18%)
SHALOM SERVICES CORPORATION(1.22%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.24%)
WOLFE CONSTRUCTION GROUP, INC. (0.30%)
STRIPING TECHNOLOGY, L.P.(0.81%)
PROJECT 2015, LLC(3.53%)
UNDER CONSTRUCTION INC.(0.00%)
GLL CORPORATION DBA MG TRUCKING(0.01%)
NIXON ENGINEERING(0.00%)
Contract # 10153212
Totals 12874396.21 544387.86 1599925.36 12.4

CountyELLIS
Highway FM 664
From NORTH OF US 287
To SOUTH OF RED OAK CREEK IN OVILLA
CSJ 1051-01-042
Proj ID STP 2015(654)
Work Type ADD 3 - FOOT PAVED SHOULDERS
 
7.303 11142221.20 667930.24 5036414.55 45.2
Work Order 04-20-15
Work Began 06-22-15
Work Completed  
Time Computed 12-23-15
Contract Working Days 293
Addl Days Granted 0
Working Days Charged 233
Percent Time Used 79
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1051-01-042
BROCK ENVIRONMENTAL SERVICES, LLC(0.31%)
CROSSROADS, L.P. (0.48%)
DUSTROL, INC.(1.95%)
STRIPING TECHNOLOGY, L.P.(0.63%)
PEACHTREE CONSTRUCTION, LTD. ( 33.79%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.89%)
JE CASEY, LLC(1.56%)
SYNERGY SIGNS & SERVICES (0.72%)
OSCAR ORDUNO, INC. (2.36%)
BRENDA PRICE TRUCKING(1.09%)
AAA DRILLING FOUNDATION CO., INC.(0.32%)
FORTSON CONTRACTING, INC.(0.58%)
LONE STAR BARRIER SERVICES, LLC(0.53%)
Contract # 03153213
Totals 11142221.20 667930.24 5036414.55 45.2

CountyELLIS
Highway FM 876
From AT BIG ONION CREEK
To .
CSJ 1051-02-017
Proj ID BR 2015(591)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.255 1721378.55 390941.96 1078684.38 62.6
Work Order 04-03-15
Work Began 09-15-15
Work Completed  
Time Computed 09-15-15
Contract Working Days 360
Addl Days Granted 0
Working Days Charged 180
Percent Time Used 50
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 1051-02-017
N-LINE TRAFFIC MAINTENANCE, L.P. (0.93%)
IOWA BRIDGE & CULVERT, LC(3.59%)
STRIPING TECHNOLOGY, L.P.(1.60%)
GJ SEEDING, LLC(5.27%)
FOUNDATION DRILLERS, INC.(3.17%)
FRAIRE"S REBAR, INC(4.42%)
F & K BUILDERS (2.81%)
PEACHTREE CONSTRUCTION, LTD. (6.81%)
CLEMONS TRUCKING (2.17%)
JANEK & WHITTEN CONSTRUCTION INC.(0.43%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(5.70%)
FORTSON CONTRACTING, INC.(1.45%)
Contract # 02153207
Totals 1721378.55 390941.96 1078684.38 62.6

CountyTARRANT
Highway IH 30
From 0.5 MILES WEST OF N. FIELDER ROAD
To DALLAS/TARRANT COUNTY LINE
CSJ 1068-02-135
Proj ID C 1068-2-135
Work Type ITS, ETC, SIGNS
 
6.091 6960302.24 139201.73 6568422.32 94.3
CountyDALLAS
Highway IH 30
From TARRANT/DALLAS COUNTY LINE
To SYLVAN AVE.
CSJ 1068-04-147
Proj ID IM 0305(082)
Work Type STR, GR, PVMT, PVMT MKGS, SIGNS, ITS
 
12.664 56121468.07 521507.59 57587923.04 99.9
Work Order 02-28-13
Work Began 03-25-13
Work Completed  
Time Computed 03-16-13
Contract Working Days 728
Addl Days Granted 84
Working Days Charged 930
Percent Time Used 114
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-147
COWTOWN TRAFFIC CONTROL, INC.(0.04%)
THE ANCHOR GROUP, INC. (0.02%)
ANTIGO CONSTRUCTION, INC.(0.02%)
DUSTROL, INC.(0.33%)
DUSTIN ALLEN, INC. (0.41%)
HOUSTON SAWING & DRILLING(0.02%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.09%)
PENHALL COMPANY(0.06%)
STORM WATER MANAGEMENT, INC. (0.13%)
VSTRUCTURAL LLC(0.42%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.12%)
W.O.E. CONSTRUCTION(0.64%)
STRIPING TECHNOLOGY, L.P.(2.08%)
MICA CORPORATION ( 19.67%)
W. W. FOUNDATION DRILLING, LTD.(2.65%)
K & S UTILITY CONTRACTORS, INC.(4.66%)
INDUS CONSTRUCTION, L.P. (0.56%)
PRESSURE CLEANING SERVICE, INC. DBA WATERBLASTING.COM(0.06%)
RAMBO CONTRACTING, INC.(1.19%)
NORTH TEXAS REBAR, LLC (0.00%)
HERDEZ TRUCKING, INC.(0.09%)
J.H. PAINTING COMPANY(0.41%)
MCL CONTRACTING, LLC (0.09%)
CB SERVICES, INC.(0.06%)
VFC, INC (0.11%)
STRIPE-A-ZONE, INC.(1.00%)
Contract # 12123201
Totals 63081770.31 660709.32 64156345.36 99.9

CountyDALLAS
Highway IH 30
From BELTLINE ROAD
To MAC ARTHUR BLVD.
CSJ 1068-04-122
Proj ID C 1068-4-122
Work Type GR, STRS & PAV
 
1.522 24620668.27 0.00 0.00 0.0
CountyDALLAS
Highway IH 30
From BELT LINE RD
To MACARTHUR RD
CSJ 1068-04-137
Proj ID ROW 1068-4-137
Work Type ROW ACQ, UTIL & RELOC
 
0.760 565255.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-16-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 538
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAYDON CENTRAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1068-04-122
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153004
Totals 25185923.27 0.00 0.00 0.0