Monthly State Let Construction Report For Dallas District As Of Aug 10, 2015 Page 6 Of 11

Last Update: Monday, August 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCOLLIN
Highway SH 121
From SH 5
To 1.65 MILES WEST OF FM 455
CSJ 0549-03-027
Proj ID C 549-3-27
Work Type GRD, STR, BASE, PVMT, SIGNS
 
5.918 43893899.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-14-15
Work Began 00-00-00
Work Completed  
Time Computed 09-13-15
Contract Working Days 768
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0549-03-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153202
Totals 43893899.25 0.00 0.00 0.0

CountyELLIS
Highway SH 34
From FM 667
To US 287
CSJ 0568-01-046
Proj ID STP 2015(482)HES
Work Type TEXTURE SHDRS AND CTR LINE TEXTURIN
 
16.811 199164.27 0.00 0.00 0.0
Work Order 02-18-15
Work Began 00-00-00
Work Completed  
Time Computed 03-06-15
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0568-01-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153205
Totals 199164.27 0.00 0.00 0.0

CountyDALLAS
Highway SL 12
From IH 30
To FERGUSON RD
CSJ 0581-01-140
Proj ID NH 2014(268)
Work Type LANDSCAPE DEVELOPMENT
 
1.394 268951.00 17402.50 271221.49 99.9
Work Order 11-18-14
Work Began 12-15-14
Work Completed  
Time Computed 12-04-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 101
Contractor(s)
GREY CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0581-01-140
ALTUS TRAFFIC MANAGEMENT LLC (3.71%)
UNLIMITED UTILITY CONSTRUCTION (4.79%)
PAVEMENT SERVICES( 12.02%)
Contract # 10143228
Totals 268951.00 17402.50 271221.49 99.9

CountyDALLAS
Highway LP 12
From COCKRELL HILL ROAD
To ANDERSON ST
CSJ 0581-02-139
Proj ID NH 2014(581)
Work Type BRIDGE DECK AND JOINT REPAIRS
 
5.116 253575.50 0.00 231135.73 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-05-14
Work Began 10-27-14
Work Completed 02-09-15
Time Computed 09-02-14
Contract Working Days 94
Addl Days Granted 0
Working Days Charged 38
Percent Time Used 40
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0581-02-139
CROSSROADS, L.P. (2.85%)
Contract # 04143213
Totals 253575.50 0.00 231135.73 100.0

CountyDALLAS
Highway LP 12
From SP 408
To WEST FORK OF TRINITY RIVER
CSJ 0581-02-140
Proj ID NH 2014(659)
Work Type FULL DEPTH REPAIR, MILL AND OVERLAY
 
4.413 2679703.82 0.00 2603905.38 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-22-14
Work Began 09-17-14
Work Completed 03-06-15
Time Computed 09-17-14
Contract Working Days 106
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 86
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0581-02-140
ALTUS TRAFFIC MANAGEMENT LLC (0.35%)
APAC-KANSAS( 10.81%)
BROCK ENVIRONMENTAL, LLC (0.60%)
DUSTROL, INC.(7.15%)
O. TREVINO CONSTRUCTION, LLC (7.23%)
W.O.E. CONSTRUCTION(1.29%)
BRENDA PRICE TRUCKING(0.15%)
COWBOY TRUCKING(1.05%)
STRIPING TECHNOLOGY, L.P.(5.39%)
MARCOM"S MOWING SERVICE, LLC (0.06%)
Contract # 05143025
Totals 2679703.82 0.00 2603905.38 100.0

CountyDALLAS
Highway SL 12
From ILLINOIS AVENUE
To NORTH OF SINGLETON BLVD
CSJ 0581-02-141
Proj ID STP 1502(042)
Work Type FDR - CP AND OVERLAY ON FRONTAGE RDS
 
8.760 2761594.56 206327.19 380918.91 13.7
Work Order 04-20-15
Work Began 06-15-15
Work Completed  
Time Computed 05-06-15
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 12
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0581-02-141
AUSTIN BRIDGE & ROAD SERVICES, LP( 33.94%)
EROSION CONTROL MANAGEMENT SERVICES(0.27%)
DURABLE SPECIALTIES, INC.(0.96%)
ALTUS TRAFFIC MANAGEMENT LLC (0.51%)
STRIPING TECHNOLOGY, L.P.(3.68%)
BRENDA PRICE TRUCKING(2.14%)
UNDER CONSTRUCTION INC.(2.54%)
Contract # 03153219
Totals 2761594.56 206327.19 380918.91 13.7

CountyELLIS
Highway FM 66
From AT OAK BRANCH
To .
CSJ 0596-02-038
Proj ID BR 2015(066)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.206 1798061.60 0.00 0.00 0.0
Work Order 12-01-14
Work Began 07-27-15
Work Completed  
Time Computed 01-30-15
Contract Working Days 343
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0596-02-038
FRAIRE"S REBAR, INC(6.74%)
ALTUS TRAFFIC MANAGEMENT LLC (0.71%)
DUSTROL, INC.(1.39%)
METRO CUTTING AND SEALING, INC.(0.28%)
IOWA BRIDGE & CULVERT, LC(3.21%)
HAYWARD BAKER, INC.(2.40%)
TEXAS SHAFTS, INC. (5.42%)
FORTSON CONTRACTING, INC.(1.73%)
USA SWPPP INSPECTIONS, INC.(1.84%)
TEXAS HIGHWAY MAINTENANCE, LLC (1.78%)
DENALI SERVICES & TRANSPORT LLC(0.79%)
Contract # 09143226
Totals 1798061.60 0.00 0.00 0.0

CountyELLIS
Highway FM 66
From AT WEST FORK GREATHOUSE BRANCH
To .
CSJ 0596-02-039
Proj ID BR 1502(321)
Work Type REPLACE BRIDGES AND APPROACHES
 
0.374 3421432.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 396
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0596-02-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153022
Totals 3421432.25 0.00 0.00 0.0

CountyELLIS
Highway FM 66
From 0.475 MI W OF GREATHOUSE RD
To 0.375 MI E OF GREATHOUSE RD
CSJ 0596-02-042
Proj ID STP 2015(846)HES
Work Type ADD LEFT TURN LANE
 
0.427 2085055.65 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 159
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0596-02-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153223
Totals 2085055.65 0.00 0.00 0.0

CountyELLIS
Highway FM 66
From FM 308
To 0.4 MI S OF BRINDLEY RD
CSJ 0596-02-043
Proj ID STP 1502(491)HES
Work Type WIDEN PAVEMENT
 
1.859 2446061.87 0.00 0.00 0.0
CountyELLIS
Highway FM 66
From 0.4 MI S OF BRINDLEY RD
To FM 916
CSJ 0596-02-045
Proj ID STP 1502(490)
Work Type WIDEN PAVEMENT
 
1.593 1809353.61 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 136
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0596-02-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153031
Totals 4255415.48 0.00 0.00 0.0

CountyCOLLIN
Highway FM 6
From AT SABINE CREEK
To .
CSJ 0619-01-023
Proj ID BR 1502(323)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.760 3493547.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 292
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0619-01-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153015
Totals 3493547.40 0.00 0.00 0.0

CountyDENTON
Highway FM 544
From FM 2281
To 0.17 MILE WEST OF JOSEY LANE
CSJ 0619-05-034
Proj ID STP 1402(111)MM
Work Type GR, STR, BASE, PVMT, SIGNS, MKGS
 
2.311 21406881.99 2324.40 2324.40 0.0
CountyDENTON
Highway FM 544
From AT KCS RR, E OF FM 2281
To .
CSJ 0619-05-036
Proj ID BR 2014(763)
Work Type REPL BR & APPR
 
0.060 5316292.06 25000.00 215654.99 4.0
CountyDENTON
Highway FM 544
From 0.17 MILES WEST OF JOSEY LN
To PARKER/DOZIER RD.
CSJ 0619-05-037
Proj ID HP 2008(733)
Work Type RECONSTRUCT EXISTING ROADWAY
 
1.136 8667784.26 107221.72 107221.72 1.2
Work Order 03-23-15
Work Began 07-06-15
Work Completed  
Time Computed 07-06-15
Contract Working Days 755
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 2
Contractor(s)
MCM
SUBCONTRACTOR(S) FOR CCSJ: 0619-05-036
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(9.65%)
OSCAR ORDUNO, INC. (0.17%)
LIRA ELECTRIC(1.75%)
FORTSON CONTRACTING, INC.(0.16%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.00%)
BOWMAN ENGINEERING & CONSTRUCTION, INC.(6.33%)
BROCK ENVIRONMENTAL SERVICES, LLC(0.31%)
EXTREME ENVIRONMENTAL SERVICES (0.09%)
ALTUS TRAFFIC MANAGEMENT LLC (2.54%)
Contract # 09143001
Totals 35390958.31 134546.12 325201.11 0.9

CountyKAUFMAN
Highway FM 986
From TOWN NORTH DR IN TERRELL
To CR 2326 (NEAR HUNT C/L)
CSJ 0642-05-023
Proj ID STP 2013(768)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
6.560 3869442.70 121388.25 3605074.52 93.1
Work Order 08-19-13
Work Began 10-07-13
Work Completed  
Time Computed 10-07-13
Contract Working Days 207
Addl Days Granted 88
Working Days Charged 207
Percent Time Used 70
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0642-05-023
BAHENA CONSTRUCTION CO.,INC. ( 17.30%)
CATOCON, INC.(0.94%)
DUSTROL, INC.(1.97%)
EROSION CONTROL MANAGEMENT SERVICES(2.13%)
FARR FOUNDATION, INC.(1.26%)
PEACHTREE CONSTRUCTION, LTD. ( 23.73%)
STRIPING TECHNOLOGY, L.P.(1.34%)
ALTUS TRAFFIC MANAGEMENT LLC (0.72%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.10%)
Contract # 06133017
Totals 3869442.70 121388.25 3605074.52 93.1

CountyKAUFMAN
Highway FM 429
From SH 243
To US 80
CSJ 0697-03-027
Proj ID STP 2015(393)HES
Work Type TEXTURE SHOULDERS AND CENTERLINE
 
21.758 207202.70 0.00 187772.23 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-07-15
Work Began 02-09-15
Work Completed 07-01-15
Time Computed 01-23-15
Contract Working Days 104
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 25
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0697-03-027
FLEX SUPPLY, LLC (5.30%)
COWBELL TRAFFIC SERVICES, INC. ( 29.14%)
STRIPING SYSTEMS, INC. (0.92%)
Contract # 12143221
Totals 207202.70 0.00 187772.23 100.0

CountyDENTON
Highway FM 156 ETC
From SOUTH HICKORY CREEK
To 0.1 MI NORTH OF FM 2450
CSJ 0718-01-051
Proj ID STP 2007(014)
Work Type ADD 10' SHOULDERS AND REHAB
 
10.779 7732000.00 6345.98 7440302.92 97.0
Work Order 09-26-13
Work Began 11-11-13
Work Completed  
Time Computed 10-12-13
Contract Working Days 288
Addl Days Granted 10
Working Days Charged 355
Percent Time Used 119
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0718-01-051
W.O.E. CONSTRUCTION(4.24%)
J & M CONTRACTING, COMPANY (4.78%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.95%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.52%)
TEXAS SHAFTS, INC. (1.79%)
MASTERPIECE GRINDING & GROOVING, LLC (0.05%)
HJC FARMS, INC.(0.49%)
FORTSON CONTRACTING, INC.(2.68%)
BREDA COMPANY, INC.(0.42%)
ALTUS TRAFFIC MANAGEMENT LLC (0.50%)
MCL CONTRACTING, LLC (0.09%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.11%)
Contract # 07133229
Totals 7732000.00 6345.98 7440302.92 97.0

CountyKAUFMAN
Highway FM 148
From FM 1390 SOUTH
To US 175 SOUTH
CSJ 0751-02-023
Proj ID STP 2014(660)
Work Type MILL, REPAIR, OL, STR, MRKS, SIGN
 
7.475 10805279.10 540219.82 3155962.06 29.2
Work Order 07-08-14
Work Began 10-01-14
Work Completed  
Time Computed 09-06-14
Contract Working Days 246
Addl Days Granted 0
Working Days Charged 114
Percent Time Used 46
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0751-02-023
TRP CONSTRUCTION GROUP, LLC(0.94%)
ALTUS TRAFFIC MANAGEMENT LLC (0.21%)
SAMMY G. SMALLWOOD (0.54%)
FORTSON CONTRACTING, INC.(2.15%)
K & S UTILITY CONTRACTORS, INC.(6.70%)
USA SWPPP INSPECTIONS, INC.(1.95%)
W.O.E. CONSTRUCTION(2.93%)
PEACHTREE CONSTRUCTION, LTD. (4.30%)
HORIZON SIGNAL TECHNOLOGIES, INC.(0.04%)
Contract # 05143221
Totals 10805279.10 540219.82 3155962.06 29.2

CountyELLIS
Highway FM 663
From SOUTH OF US 287
To NORTH OF US 287
CSJ 0815-08-027
Proj ID PTF 2013(451)
Work Type STR, PVMT, PVMT MKGS
 
0.568 4728943.55 250541.16 3910451.02 83.8
Work Order 05-16-13
Work Began 06-30-14
Work Completed  
Time Computed 06-01-13
Contract Working Days 161
Addl Days Granted 0
Working Days Charged 217
Percent Time Used 134
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0815-08-027
TOTAL HIGHWAY MAINTENANCE, LLC (0.26%)
WYLIE DRILLING & DRAINAGE, INC.(0.75%)
USA SWPPP INSPECTIONS, INC.(1.93%)
STRIPING TECHNOLOGY, L.P.(1.20%)
SOUTHEAST GRINDING & GROOVING, LLC (0.05%)
SCOTT DERR PAINTING CO, LLC(0.20%)
MCL CONTRACTING, LLC (0.48%)
LONE STAR BARRIER SERVICES, LLC(0.83%)
INLET STRUCTURE SPECIALTIES LTD. (1.27%)
DUSTROL, INC.(0.51%)
DURABLE SPECIALTIES, INC.(5.94%)
PREMIER PAVING, LTD. ( 10.88%)
CHRISTINE"S CONCERTE SAWING & SEALING LLC(0.17%)
T-BAR FENCE, INC.(0.67%)
W.O.E. CONSTRUCTION(0.17%)
Contract # 03133216
Totals 4728943.55 250541.16 3910451.02 83.8

CountyDENTON
Highway FM 455
From AT BOOM CREEK
To .
CSJ 0816-02-053
Proj ID BR 2014(764)
Work Type REPLACE EXISTING BRIDGE AND APPROAC
 
1.646 3335495.22 154265.35 928354.05 27.8
Work Order 09-09-14
Work Began 04-08-15
Work Completed  
Time Computed 09-25-14
Contract Working Days 193
Addl Days Granted 0
Working Days Charged 81
Percent Time Used 41
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0816-02-053
ALTUS TRAFFIC MANAGEMENT LLC (0.39%)
FOUNDATION DRILLERS, INC.(1.63%)
HJC FARMS, INC.(0.21%)
LAYFIELD CONSTRUCTION, INC (1.66%)
LINDAMOOD DEMOLITION, INC. (0.41%)
MCL CONTRACTING, LLC (1.58%)
PENHALL COMPANY(0.08%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.40%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.98%)
THELIN RECYCLING COMPANY, L.P. (0.29%)
VILHAUER ENTERPRISES, LLC(2.42%)
Contract # 06143238
Totals 3335495.22 154265.35 928354.05 27.8

CountyCOLLIN
Highway FM 455
From US 75 NB FRONTAGE ROAD
To SH 5
CSJ 0816-04-044
Proj ID C 816-4-44
Work Type GR, STRS, BASE, SURF, PAV, MARK
 
1.960 12399737.47 0.00 463968.57 3.7
Work Order 09-03-13
Work Began 00-00-00
Work Completed  
Time Computed 03-02-14
Contract Working Days 251
Addl Days Granted 37
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0816-04-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133204
Totals 12399737.47 0.00 463968.57 3.7

CountyCOLLIN
Highway FM 455
From CR 98
To FM 3356
CSJ 0816-04-047
Proj ID STP 2014(700)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
8.080 5536032.38 48392.56 5626146.57 100.0
Work Order 06-20-14
Work Began 07-09-14
Work Completed 07-30-15
Time Computed 07-06-14
Contract Working Days 191
Addl Days Granted 16
Working Days Charged 207
Percent Time Used 100
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0816-04-047
TRP CONSTRUCTION GROUP, LLC(1.04%)
ALTUS TRAFFIC MANAGEMENT LLC (0.26%)
RICE ENVIRONMENTAL SERVICES(2.95%)
W.S. CONSTRUCTION COMPANY( 10.92%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(3.34%)
FORTSON CONTRACTING, INC.(0.18%)
Contract # 04143009
Totals 5536032.38 48392.56 5626146.57 100.0