Monthly State Let Construction Report For Dallas District As Of Jul 12, 2016 Page 6 Of 9

Last Update: Tuesday, July 12, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyELLIS
Highway CR
From FOREST BROOK DR AT RED OAK CREEK
To CITY OF OAK LEAF
CSJ 0918-22-141
Proj ID BR 2013(598)
Work Type REPL BR
 
0.084 1038508.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-07-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-22-141
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153036
Totals 1038508.40 0.00 0.00 0.0

CountyDALLAS
Highway CS
From ON PLEASANT RUN RD. AT BEE BRANCH
To IN CITY OF DESOTO
CSJ 0918-45-731
Proj ID BR 2006(473)
Work Type REPL BR & APPRS
 
0.259 3181746.72 66920.93 2639572.51 82.9
Work Order 09-30-14
Work Began 03-24-15
Work Completed  
Time Computed 10-16-14
Contract Working Days 247
Addl Days Granted 31
Working Days Charged 260
Percent Time Used 93
Contractor(s)
IOWA BRIDGE & CULVERT, LC
SUBCONTRACTOR(S) FOR CCSJ: 0918-45-731
TOTAL HIGHWAY MAINTENANCE, LLC (0.45%)
ACU CONSTRUCTION LLC (0.53%)
TISEO PAVING CO. ( 11.06%)
RICE ENVIRONMENTAL SERVICES(0.12%)
MELS ELECTRIC, L.P.(0.36%)
FORTSON CONTRACTING, INC.(0.20%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.41%)
MCL CONTRACTING, LLC (0.05%)
PREMIER PAVING, LTD. (4.57%)
T & R EXCAVATION, INC. (5.83%)
STRIPE-A-ZONE, INC.(0.81%)
UNDERGROUND COALITION, INC.(3.67%)
USA SWPPP INSPECTIONS, INC.(1.36%)
ENVIRONMENTAL SAFETY SERVICES, INC.(5.47%)
FOUNDATION DRILLERS, INC.(1.52%)
FARR FOUNDATION, INC.(0.76%)
DFW SERVICES, LLC(3.67%)
KDAT (2.65%)
VENUS CONSTRUCTION (1.32%)
Contract # 07143014
Totals 3181746.72 66920.93 2639572.51 82.9

CountyDALLAS
Highway CS
From LAKERIDGE PKWY, S OF GREAT SW PKWY
To IH 20 EB FRTG ROAD
CSJ 0918-45-747
Proj ID STP 2011(413)MM
Work Type GR, STRS AND PVT
 
1.968 15998353.47 0.00 17141322.49 99.9
Work Order 01-10-11
Work Began 02-28-11
Work Completed  
Time Computed 01-26-11
Contract Working Days 366
Addl Days Granted 341
Working Days Charged 706
Percent Time Used 99
Contractor(s)
LONE STAR CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-45-747
TOTAL HIGHWAY MAINTENANCE, LLC (0.54%)
PREMIER PAVING, LTD. (9.76%)
A.M.S. COMPANY, INC. (7.39%)
TEXAS STAR TRANSPORT, LP (2.21%)
DENALI SERVICES, L.P.(0.22%)
ALLIANCE TRUCKING(0.59%)
SUPREME SAWING AND SEALING (0.04%)
WYLIE DRILLING & DRAINAGE, INC.(2.14%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.46%)
UNDERGROUND COALITION, INC.(5.46%)
J.L. STEEL REINFORCING, LLC(0.17%)
THURMAN TRANSPORTATION, INC. (0.36%)
TRYMOR TRUCKING, INC.(0.14%)
INTEGRATED ROADWAY SERVICES, INC.(4.31%)
TCB FOUNDATION DRILLERS, INC.(0.58%)
INDUS CONSTRUCTION, L.P. (1.78%)
CONCRETE CUTTING BY BOND (0.30%)
JM MATERIALS, INC. (0.14%)
A BROTHERS MILLING, LLC(0.06%)
SCOTT DERR PAINTING CO (0.07%)
J & M MANHOLE CONSTRUCTION (0.02%)
RICE ENVIRONMENTAL SERVICES(0.09%)
VANN/ELLI, INC.(0.04%)
STRIPE-A-ZONE, INC.(0.04%)
PHILLIPS LAWN SPRINKLER CO., INC.(0.35%)
ARTEX ELECTRIC, INC. (0.09%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.15%)
Contract # 11103001
Totals 15998353.47 0.00 17141322.49 99.9

CountyDALLAS
Highway CS
From S MARSALIS AVE AT FIVEMILE CREEK
To .
CSJ 0918-45-761
Proj ID BR 2007(306)
Work Type REPL BR & APPRS
 
0.077 2688948.21 39.90 1455364.78 54.1
CountyDALLAS
Highway CS
From S MARSALIS AVE AT FIVEMILE CREEK
To .
CSJ 0918-47-085
Proj ID RW 918-47-85
Work Type ADJUSTMENT OF UTILITIES
 
0.090 255486.60 0.00 72407.00 28.3
Work Order 09-22-14
Work Began 03-30-15
Work Completed  
Time Computed 11-21-14
Contract Working Days 353
Addl Days Granted 0
Working Days Charged 351
Percent Time Used 99
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-45-761
ALTUS TRAFFIC MANAGEMENT LLC (0.97%)
BROCK ENVIRONMENTAL, LLC (0.53%)
ATS DRILLING, INC. (7.00%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(1.19%)
FRAIRE"S REBAR, INC(8.53%)
STRIPE-A-ZONE, INC.(0.16%)
ACTION SERVICES(0.29%)
FORTSON CONTRACTING, INC.(0.26%)
IOWA BRIDGE & CULVERT, LC(0.33%)
METRO CUTTING AND SEALING, INC.(0.20%)
DUSTROL, INC.(0.30%)
J & M MANHOLE CONSTRUCTION (0.30%)
RICE TUNNELING & BORING, INC.(0.25%)
MAGNUM MANHOLE & UNDERGROUND COMPANY (0.36%)
CLEMONS TRUCKING (1.23%)
FOUNDATION DRILLERS, INC.(1.17%)
K & A STEEL, LLC (1.73%)
XIT PAVING AND CONSTRUCTION INC. (1.11%)
F & K BUILDERS (4.45%)
Contract # 06143014
Totals 2944434.81 39.90 1527771.78 51.8

CountyDALLAS
Highway CS
From RED OAK RD AT TEN MILE CREEK
To IN THE CITY OF LANCASTER
CSJ 0918-45-791
Proj ID BR 2013(493)
Work Type REHAB BRIDGE AND APPROACHES
 
0.100 1305085.00 249175.80 286215.80 21.9
Work Order 03-15-16
Work Began 05-17-16
Work Completed  
Time Computed 05-17-16
Contract Working Days 247
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 12
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-45-791
PENHALL COMPANY(0.24%)
PEACHTREE CONSTRUCTION, LTD. (1.41%)
S&S BRIDGE PAINTING( 22.66%)
ODUM SERVICES, L.P.(1.39%)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(0.46%)
ACU CONSTRUCTION LLC (1.01%)
USA SWPPP INSPECTIONS, INC.(2.02%)
Contract # 11153230
Totals 1305085.00 249175.80 286215.80 21.9

CountyDALLAS
Highway CS
From ON WHITLOCK RD, FROM IH 35E
To OLD DENTON RD IN CARROLLTON
CSJ 0918-45-864
Proj ID STP 2009(860)MM
Work Type GR, STRS & SURF
 
0.505 3063573.24 0.00 12988.07 0.4
CountyDALLAS
Highway CS
From ON WHITLOCK RD, FROM IH 35E
To OLD DENTON RD IN CARROLLTON
CSJ 0918-47-116
Proj ID RW 918-47-116
Work Type ADJUSTMENT OF UTILITIES IN CONSTRUC
 
0.505 372163.90 0.00 0.00 0.0
Work Order 09-11-14
Work Began 00-00-00
Work Completed  
Time Computed 12-09-14
Contract Working Days 276
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TISEO PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0918-45-864
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143222
Totals 3435737.14 0.00 12988.07 0.3

CountyDENTON
Highway PW
From AT RAY ROBERTS (ISLE DUBOIS)
To STATE PARK
CSJ 0918-46-269
Proj ID C 918-46-269
Work Type REHABILITATE ROADS
 
0.001 1587178.56 0.00 1753072.90 99.9
Work Order 05-21-15
Work Began 08-07-15
Work Completed  
Time Computed 06-21-15
Contract Working Days 91
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 69
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0918-46-269
ALTUS TRAFFIC MANAGEMENT LLC (0.21%)
STRIPING TECHNOLOGY, L.P.(9.73%)
USA SWPPP INSPECTIONS, INC.(1.90%)
Contract # 04153243
Totals 1587178.56 0.00 1753072.90 99.9

CountyDALLAS
Highway VA
From VARIOUS LOCATIONS ON STATE HIGHWAYS
To IN DALLAS COUNTY
CSJ 0918-47-052
Proj ID STP 1102(553)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2270944.30 0.00 2162311.95 95.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-25-14
Work Began 09-02-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 244
Addl Days Granted 0
Working Days Charged 239
Percent Time Used 97
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-052
CLASSIC TEJAS CONSTRUCTION, INC. ( 17.31%)
ACTION SERVICES(1.21%)
Contract # 06143039
Totals 2270944.30 0.00 2162311.95 95.2

CountyDALLAS
Highway CS
From CEDAR HILL STATE PARK
To NEW CLARK RD IN CITY OF CEDAR HILL
CSJ 0918-47-097
Proj ID STP 2014(156)TE
Work Type HIKE AND BIKE TRAIL
 
1.368 2766088.00 0.00 0.00 0.0
CountyDALLAS
Highway FM 1382
From AT CEDAR HILL STATE PARK SPINE RD
To .
CSJ 1047-03-066
Proj ID C 1047-3-66
Work Type GR, BS, ASPH PVMT, PVMT MKGS
 
0.267 1257559.70 0.00 0.00 0.0
CountyDALLAS
Highway FM 1382
From SOUTHEAST OF WEST SPINE ROAD
To WEST OF NEW CLARK ROAD
CSJ 1047-03-068
Proj ID CM 1602(423)
Work Type INTERSECTION IMPROVEMENTS
 
0.600 1197552.40 0.00 0.00 0.0
CountyDALLAS
Highway FM 1382
From AT CEDAR HILL STATE PARK SPINE RD
To .
CSJ 1047-03-070
Proj ID NH 1602(422)
Work Type TRAF SIG
 
0.196 827701.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1047-03-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163040
Totals 6048901.10 0.00 0.00 0.0

CountyDALLAS
Highway VA
From VARIOUS LOCATIONS ON STATE HIGHWAYS
To IN DALLAS COUNTY
CSJ 0918-47-100
Proj ID NH 2015(653)
Work Type CONSTRUCT CURB RAMPS
 
0.001 3464886.46 102395.00 2937788.60 84.7
Work Order 04-22-15
Work Began 06-22-15
Work Completed  
Time Computed 05-08-15
Contract Working Days 315
Addl Days Granted 0
Working Days Charged 259
Percent Time Used 82
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-100
CLASSIC TEJAS CONSTRUCTION, INC. ( 10.16%)
Contract # 03153224
Totals 3464886.46 102395.00 2937788.60 84.7

CountyDALLAS
Highway CS
From JEFFERSON ST AT MERRIFIELD ST
To .
CSJ 0918-47-101
Proj ID STP 1502(494)HES
Work Type INSTALL TRAFFIC SIGNAL
 
0.100 395282.15 14489.60 293569.42 74.2
CountyDALLAS
Highway CS
From WESTMORELAND AT CLARENDON
To .
CSJ 0918-47-103
Proj ID STP 1502(496)HES
Work Type IMPROVE TRAFFIC SIGNALS
 
0.100 257625.45 38456.69 61181.69 23.7
CountyDALLAS
Highway CS
From MCKINNEY AT MAPLE
To .
CSJ 0918-47-110
Proj ID STP 1502(495)HES
Work Type IMPROVE TRAFFIC SIGNALS
 
0.100 150048.25 0.00 22500.00 14.9
Work Order 10-05-15
Work Began 02-29-16
Work Completed  
Time Computed 02-29-16
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 74
Percent Time Used 52
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-101
DALLAS LITE AND BARRICADE INC. (1.43%)
MABAK DIRECTIONAL DRILLING (4.36%)
AUGER DRILLING, INC. (0.99%)
Contract # 07153012
Totals 802955.85 52946.29 377251.11 46.9

CountyDALLAS
Highway CS
From BELT LINE ROAD AT DALLAS PKWY
To .
CSJ 0918-47-120
Proj ID STP 1602(110)HES
Work Type IMPROVE TRAFFIC SIGNALS
 
1.000 1300500.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 172
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-120
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163228
Totals 1300500.00 0.00 0.00 0.0

CountyCOLLIN
Highway FM 546
From SH 5
To EAST OF COUNTRY LN/AIRPORT RD
CSJ 1013-01-026
Proj ID C 1013-1-26
Work Type GR, PVMT, STR, SIGNS, PVMT MKGS
 
1.724 17391616.98 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 411
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1013-01-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163037
Totals 17391616.98 0.00 0.00 0.0

CountyCOLLIN
Highway FM 546
From WEST OF THE CROSSINGS RD
To FM 982
CSJ 1013-01-028
Proj ID STP 1402(180)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
5.051 5997170.81 29872.50 5772284.92 97.1
Work Order 09-15-14
Work Began 12-01-14
Work Completed  
Time Computed 12-01-14
Contract Working Days 263
Addl Days Granted 21
Working Days Charged 332
Percent Time Used 116
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1013-01-028
TOTAL HIGHWAY MAINTENANCE, LLC (1.22%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(0.43%)
FARR FOUNDATION, INC.(3.02%)
EROSION CONTROL MANAGEMENT SERVICES(0.36%)
K & S UTILITY CONTRACTORS, INC.( 21.42%)
MARCOM"S MOWING SERVICE, LLC (3.13%)
ACU CONSTRUCTION LLC (0.45%)
GOLDEN TREE MAINTENANCE(0.13%)
IOWA BRIDGE & CULVERT, LC(0.51%)
Contract # 07143245
Totals 5997170.81 29872.50 5772284.92 97.1

CountyROCKWALL
Highway FM 548
From SH 276
To SH 66
CSJ 1014-02-041
Proj ID STP 2016(145)
Work Type WDN, STR, REMX, OL, PV MRKS
 
12.751 13784401.35 807134.22 1836652.27 13.3
Work Order 02-03-16
Work Began 03-28-16
Work Completed  
Time Computed 03-28-16
Contract Working Days 363
Addl Days Granted 0
Working Days Charged 80
Percent Time Used 22
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1014-02-041
TEXOP CONSTRUCTION (1.79%)
EROSION CONTROL MANAGEMENT SERVICES(0.48%)
PREMIER PAVING, LTD. ( 22.61%)
SCOTT PAVING, INC. (3.33%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.66%)
TRP CONSTRUCTION GROUP, LLC(0.94%)
DALLAS LITE AND BARRICADE INC. (0.54%)
COMEN ENTERPRISE (1.34%)
COWBOY TRUCKING(4.54%)
Contract # 10153205
Totals 13784401.35 807134.22 1836652.27 13.3

CountyROCKWALL
Highway FM 740
From FM 549 / FM 550 INTERSECTION
To FM 1140 NORTH IN HEATH
CSJ 1014-03-049
Proj ID C 1014-3-49
Work Type GRADING, STRUCTURES, DRAINAGE, & PVMT
 
1.856 12967453.42 283241.94 2399269.60 18.5
Work Order 11-14-13
Work Began 07-20-15
Work Completed  
Time Computed 08-11-14
Contract Working Days 412
Addl Days Granted 0
Working Days Charged 135
Percent Time Used 32
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1014-03-049
W.O.E. CONSTRUCTION(0.30%)
TEX OP CONSTRUCTION, LP(2.01%)
TEXAS INLETS, INC. (3.62%)
SYNERGY SIGNS & SERVICES, LLC(0.37%)
HAYWARD BAKER, INC.(0.81%)
STRIPING TECHNOLOGY, L.P.(0.99%)
USA SWPPP INSPECTIONS, INC.(1.15%)
PREMIER PAVING, LTD. (4.86%)
DURABLE SPECIALTIES, INC.(3.25%)
BREDA COMPANY, INC.(0.67%)
BUYERS BARRICADES, INC.(0.31%)
BRENDA PRICE TRUCKING(4.98%)
FANNIN TREE FARM, LTD(0.33%)
Contract # 08133209
Totals 12967453.42 283241.94 2399269.60 18.5

CountyROCKWALL
Highway FM 3549
From SH 66
To FM 552
CSJ 1015-01-022
Proj ID STP 2015(590)
Work Type BASE REPAIR, LEVEL UP, OVERLAY
 
2.319 2576274.62 61869.10 2890732.41 99.9
Work Order 03-30-15
Work Began 08-05-15
Work Completed  
Time Computed 04-15-15
Contract Working Days 165
Addl Days Granted 31
Working Days Charged 195
Percent Time Used 99
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 1015-01-022
PEACHTREE CONSTRUCTION, LTD. ( 14.69%)
K & S UTILITY CONTRACTORS, INC.(9.85%)
ALTUS TRAFFIC MANAGEMENT LLC (0.36%)
USA SWPPP INSPECTIONS, INC.(2.61%)
STRIPING TECHNOLOGY, L.P.(1.47%)
BAHENA CONSTRUCTION CO.,INC. (0.28%)
RAMBO CONTRACTING, INC.(2.41%)
Contract # 02153221
Totals 2576274.62 61869.10 2890732.41 99.9

CountyROCKWALL
Highway FM 551
From NORTH OF IH 30
To SH 66
CSJ 1016-01-027
Proj ID STP 2014(766)
Work Type BASE REPAIR, LEVEL UP, OVERLAY
 
2.479 5349450.72 457384.74 3827802.66 71.5
Work Order 08-07-14
Work Began 06-15-15
Work Completed  
Time Computed 02-03-15
Contract Working Days 126
Addl Days Granted 62
Working Days Charged 185
Percent Time Used 98
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1016-01-027
DUSTROL, INC.(4.85%)
PREMIER PAVING, LTD. ( 12.35%)
USA SWPPP INSPECTIONS, INC.(1.91%)
FORTSON CONTRACTING, INC.(1.26%)
STRIPING TECHNOLOGY, L.P.(0.71%)
HAYWOOD BAKER(1.24%)
SYNERGY SIGNS & SERVICES, LLC(0.86%)
BRENDA PRICE TRUCKING(1.08%)
FANNIN TREE FARM, LTD(0.13%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.42%)
NE-TEX CONSTRUCTION, LTD.(2.81%)
Contract # 06143232
Totals 5349450.72 457384.74 3827802.66 71.5

CountyROCKWALL
Highway FM 1138
From SH 66
To COLLIN COUNTY LINE
CSJ 1016-03-013
Proj ID STP 1602(216)
Work Type BASE REPAIR, LEVEL UP, OVERLAY
 
1.065 1329420.20 0.00 0.00 0.0
CountyROCKWALL
Highway FM 35
From IH 30
To HUNT COUNTY LINE
CSJ 1017-02-012
Proj ID STP 1602(216)
Work Type MILL, BS REP, OV
 
1.539 627099.96 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-01-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1016-03-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163033
Totals 1956520.16 0.00 0.00 0.0

CountyELLIS
Highway FM 85
From IH 45
To FM 1182
CSJ 1050-01-017
Proj ID STP 2016(146)
Work Type ACP OVERLAY, GR, STR, PVMT MKGS
 
8.401 12874396.21 249424.93 1849350.29 14.3
Work Order 12-21-15
Work Began 03-14-16
Work Completed  
Time Computed 03-14-16
Contract Working Days 490
Addl Days Granted 5
Working Days Charged 75
Percent Time Used 15
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1050-01-017
FARR FOUNDATION, INC.(0.78%)
LONE STAR BARRIER SERVICES, LLC(0.82%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.18%)
SHALOM SERVICES CORPORATION(1.22%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.24%)
WOLFE CONSTRUCTION GROUP, INC. (0.30%)
STRIPING TECHNOLOGY, L.P.(0.81%)
PROJECT 2015, LLC(3.53%)
UNDER CONSTRUCTION INC.(0.00%)
GLL CORPORATION DBA MG TRUCKING(0.01%)
NIXON ENGINEERING(0.00%)
Contract # 10153212
Totals 12874396.21 249424.93 1849350.29 14.3