Letting Schedule for June, 2012 (FY 2012)

 
 
Last Update: Monday, September 24, 2012
June, 2012 (FY 2012) (see Links)
SEP 2011 | OCT 2011 | NOV 2011 | DEC 2011 | JAN 2012 | FEB 2012 | MAR 2012 | APR 2012 | MAY 2012 | JUN 2012 | JUL 2012 | AUG 2012
CCSJ County/
District
Highway Let Status Contract
Cost
Fund
Cat
Description
0176-02-090 Angelina/
Lufkin
US 59 Actual $52,179,226 8 REPLACE RAILROAD UNDERPASS
1738-02-013 Atascosa/
San Antonio
FM 2504 Actual $4,904,745 3 REHAB AND WIDEN TO ADD SHOULDERS
0156-06-039 Baylor/
Wichita Falls
US 277 Actual $10,550,963 3 UPGRADE TO 4 LANE DIVIDED FACILITY
0320-06-001 Bell/
Waco
LP 363 Actual $39,883,619 3 CONSTRUCT NORTHBOUND FRONTAGE ROAD TO PROVIDE INTERIM 4 - LANE
0909-36-129 Bell/
Waco
CS Actual $587,695 3 CONSTRUCT ALTERNATE TRANSPORTATION ROUTE CONSISTING OF
0909-36-134 Bell/
Waco
CS Actual $5,187,103 3 CONSTRUCT ALTERNATE TRANSPORTATION ROUTE CONSISTING OF
0217-02-034 Bowie/
Atlanta
US 59 Actual $397,377 1 RESTORE & RESURFACE EXISTING 4 - LANE DIVIDED HIGHWAY
2879-02-013 Bowie/
Atlanta
FM 2240 Actual $1,886,283 3 WIDEN EXISTING ROADWAY TO PROVIDE CONTINUOUS LEFT TURN LANE
0912-31-237 Brazoria/
Houston
CS Actual $766,157 6 REPLACE BRIDGE (NBI# (120200D01100001)
0054-07-067 Brown/
Brownwood
US 84 Actual $3,919,576 3 REHAB & UPGRADE TO AN URBAN CURB & GUTTER SECTION
0923-06-061 Brown/
Brownwood
CS Actual $726,589 3 CONSTRUCT NEW 2 LANE ROADWAY WITH CONTINUOUS LEFT TURN LANE
0921-06-212 Cameron/
Pharr
CS Actual $1,569,690 3 WIDEN TO 4 LANE
0091-03-021 Collin/
Dallas
SH 289 Actual $15,996,401 3 RECONSTRUCT AND WIDEN TWO LANE RURAL HIGHWAY TO FOUR LANE
0281-02-039 Collin/
Dallas
SH 78 Actual $21,337,008 3 WIDEN TO SIX LANE DIVIDED
0897-01-011 Colorado/
Yoakum
FM 333 Actual $589,199 6 REPLACE BRIDGE AND APPROACHES
0238-03-052 Dallam/
Amarillo
US 54 Actual $6,417,953 3 REHAB EXIST RDWY & ADD PASSING LNS
0442-02-150 Dallas/
Dallas
IH 35E Actual $6,148,724 1 OVERLAY AND FULL DEPTH REPAIR OF MAINLANES
0353-02-029 Denton/
Dallas
SH 114 Actual $28,612,477 3 WIDEN 2 TO 4 LANE DIVIDED RURAL
0924-06-368 El Paso/
El Paso
VA Actual $144,802 3 INSTALLATION OF TRAFFIC SIGNAL
0172-04-042 Ellis/
Dallas
US 287 Actual $4,420,538 1 ACP OVERLAY AND PAVEMENT MARKINGS
0261-01-037 Ellis/
Dallas
US 67 Actual $8,956,101 3 CONSTRUCT NEW FRONTAGE ROADS OVER UP RR
0500-04-125 Galveston/
Houston
IH 45 Actual $473,737 1 INSTALL LEFT TURN LANES
0913-22-040 Gonzales/
Yoakum
CR Actual $204,281 6 REPLACE BRIDGE AND APPROACHES
0901-19-134 Grayson/
Paris
CR Actual $546,773 6 REPLACE BRIDGE AND APPROACHES
0915-46-038 Guadalupe/
San Antonio
CS Actual $542,082 8 CONSTRUCT SIDEWALK, BIKE PATHS, BIKE RACKS, CROSSWALK
0541-02-030 Hall/
Childress
SH 256 Actual $667,813 3 REPLACE BRIDGERAIL
0027-13-205 Harris/
Houston
US 59 Actual $4,414,105 3 CONSTRUCT FOUTAINVIEW AUXILIARY LANE
0028-02-082 Harris/
Houston
US 90 Actual $1,119,755 1 ADD RAMP REVERSAL
0389-05-119 Harris/
Houston
SH 146 Actual $11,747,790 1 CONSTRUCT NB DIRECT CONNECTOR
0912-00-324 Harris/
Houston
VA Actual $555,317 1 INSTALL BATTERY BACK UP AND UPGRADE POWER METERS
1062-02-024 Harris/
Houston
FM 1485 Actual $987,119 1 INSTALL LEFT TURN LANE (WB - SB)
0495-08-097 Harrison/
Atlanta
IH 20 Actual $940,652 1 MICROSURFACE INTERSTATE MAINLANES TO IMPROVE SKID RESISTANCE
0495-10-082 Harrison/
Atlanta
IH 20 Actual $6,280,979 3 REPAIR PAVEMENT AND RESURFACE EXISTING INTERSTATE FACILITY
0286-01-051 Hays/
Austin
SH 80 Actual $1,702,739 3 CONSTR ADDITIONAL TURN LANES
0901-22-083 Hunt/
Paris
CR Actual $611,116 6 REPLACE BRIDGE AND APPROACHES
0920-38-237 Jefferson/
Beaumont
PW Actual $1,430,500 10 RECONSTRUCT PARK ROADS, PULLOUTS, AND PARKING LOTS
0327-02-050 Kenedy/
Pharr
US 77 Actual $10,282,199 1 CONSTRUCT OVERPASS
0133-01-043 King/
Childress
US 82 Actual $9,739,695 3 CONSTRUCT SUPER 2
0272-06-036 Lampasas/
Brownwood
US 183 Actual $2,650,391 3 ADD PASSING LANES
2786-01-010 Lampasas/
Brownwood
FM 2657 Actual $6,233,124 3 WIDEN ROADWAY
0062-05-061 Marion/
Atlanta
US 59 Actual $238,299 3 WIDEN PAVEMENT ON OUTSIDE OF CURVE
2506-01-035 McLennan/
Waco
FM 1695 Actual $2,387,270 3 RERCONSTRUCT AND WIDEN FROM TWO TO FOUR LANES WITH
0005-14-077 Midland/
Odessa
IH 20 Actual $10,773,473 3 UPGRADE TO STANDARDS FREEWAY
0054-08-026 Mills/
Brownwood
US 84 Actual $2,644,310 3 ADD PASSING LANES
1259-01-038 Montgomery/
Houston
FM 1097 Actual $302,236 1 INSTALL LEFT TURN LANES
0916-00-063 Nueces/
Corpus Christi
VA Actual $1,104,600 10 CONSTRUCT CURB RAMPS FOR ADA COMPLIANCE
0394-01-060 Panola/
Atlanta
FM 959 Actual $349,093 6 REPLACE BRIDGE AND APPROACHES
0008-03-102 Parker/
Fort Worth
IH 20 Actual $2,032,615 3 RELOCATE EXIT RAMP
0341-03-036 Polk/
Lufkin
US 287 Actual $4,948,704 3 RECONSTRUCT AND WIDEN PAVEMENT
0994-01-030 San Patricio/
Corpus Christi
SH 188 Actual $9,223,815 1 REHAB
0902-48-836 Tarrant/
Fort Worth
VA Actual $821,423 12 TRAFFIC SIGNAL TIMING
0006-06-093 Taylor/
Abilene
IH 20 Actual $12,481,302 1 RECONSTRUCT FRONTAGE ROADS, RELOCATE RAMPS, AND ADD TURN -
1578-02-026 Titus/
Atlanta
FM 1734 Actual $49,996 3 INSTALL NEW TRAFFIC SIGNAL
0044-01-094 Wichita/
Wichita Falls
US 82 Actual $2,692,739 3 REPLACE BRIDGE AND APPROACHES
0038-03-033 Zapata/
Pharr
US 83 Actual $12,959,338 1 REHAB & WIDEN PAVEMENT (SUPER 2)


Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract