Monthly State Let Construction Report For Houston District As Of Nov 10, 2024 Page 10 Of 15

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13 | page 14 | page 15

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayVA
FromVA COH SIDEWALKS SE CBD
ToPOLK, FANNIN, PIERCE, HAMILTON
CSJ0912-72-390
Proj IDF 2022(720)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1.3471389740.001373826.4698.8
Work Order06-14-23
Work Began07-27-23
Work Completed
Time Computed07-14-23
Contract Working Days166
Addl Days Granted20
Working Days Charged178
Percent Time Used95
Contractor(s)
ROMAN EMPERORS ROAD, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-390
DTI A-GROUP, LLC (4.03)
HUITT ZOLLARS,INC. (0.28)
PFEIFFER & SON LTD. (0.11)
Contract #05233222
Totals1389740.000.001373826.4698.8

CountyHARRIS
HighwayCS
FromBACA STREET AT HCFCD DITCH
To.
CSJ0912-72-405
Proj IDBR 2021(347)
Work TypeBRIDGE REPLACEMENT
 
0.037745291.25725286.0597.3
Work Order10-12-23
Work Began11-14-23
Work Completed
Time Computed11-09-23
Contract Working Days142
Addl Days Granted0
Working Days Charged142
Percent Time Used100
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-405
TRAFFIC SIGNS & LINES, LLC (1.68)
MESA ROD BUSTERS, INC. (0.81)
Contract #09233041
Totals745291.25534.80725286.0597.3

CountyHARRIS
HighwayCS
FromSOUTH DIAMONDHEAD BLVD AT GUM GULLY
To.
CSJ0912-72-406
Proj IDBR 2020(124)
Work TypeBRIDGE REPLACEMENT
 
0.1004303857.752580128.9859.9
Work Order04-26-23
Work Began05-18-23
Work Completed
Time Computed05-26-23
Contract Working Days269
Addl Days Granted0
Working Days Charged152
Percent Time Used56
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-406
BELL BOTTOM FOUNDATION CO. (3.45)
TRAF-TEX, INC. (1.40)
Contract #02233023
Totals4303857.75180755.212580128.9859.9

CountyHARRIS
HighwayCS
FromNASA RD 1 BYPASS: FROM FM 528
ToLANDING BLVD ROUNDABOUT
CSJ0912-72-541
Proj IDSTP 2020(724)MM
Work TypeNEW LOCATION NON-FREEWAY
 
0.66510385128.670.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days305
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-541
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10243009
Totals10385128.670.000.000.0

CountyBRAZORIA
HighwayCS
FromCOUNTRY CLUB DR AT CLEAR CREEK
To.
CSJ0912-72-558
Proj IDBR 2022(517)
Work TypeBRIDGE REPLACEMENT
 
0.1052503743.902409459.2296.2
Work Order05-17-23
Work Began03-13-24
Work Completed
Time Computed06-16-23
Contract Working Days171
Addl Days Granted0
Working Days Charged150
Percent Time Used87
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-558
BELL BOTTOM FOUNDATION CO. (1.52)
DORAN STEEL, INC. (0.17)
CURB PLANET INC. (0.03)
HOUSTON SAWING & DRILLING (0.13)
Contract #02233025
Totals2503743.90147222.322409459.2296.2

CountyHARRIS
HighwayCS
FromS. BRAESWOOD BLVD AT HCFCD DITCH
To.
CSJ0912-72-559
Proj IDBR 2022(705)
Work TypeBRIDGE REPLACEMENT
 
0.2406980350.31542045.177.7
Work Order07-24-24
Work Began10-04-24
Work Completed
Time Computed09-22-24
Contract Working Days255
Addl Days Granted0
Working Days Charged20
Percent Time Used7
Contractor(s)
R CONSTRUCTION CIVIL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-559
HIGHWAY 1 LLC (1.46)
CURB PLANET INC. (0.04)
HOUSTON SAWING & DRILLING (0.13)
LARRY YOUNG PAVING, INC. (1.99)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.91)
SEMARCK LANDSCAPE SERVICES, INC. (0.21)
HERMANOS STEEL, LLC (0.64)
BPR OPERATING, LLC (0.06)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.00)
Contract #06243010
Totals6980350.31457867.70542045.177.7

CountyHARRIS
HighwayCS
FromBEECHNUT AT MAPLECREST DRIVE
To.
CSJ0912-72-634
Proj IDSTP 2B23(158)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.110336149.36162842.0848.4
CountyHARRIS
HighwayCS
FromMEMORIAL DRIVE AT ADDICKS HOWELL ROAD
To.
CSJ0912-72-638
Proj IDSTP 2B23(159)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.120235690.72152904.1764.8
CountyHARRIS
HighwayCS
FromSMITH STREET AT TUAM STREET
To.
CSJ0912-72-642
Proj IDSTP 2B23(158)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.100433582.00356727.1382.2
CountyHARRIS
HighwayCS
FromWEST TIDWELL ROAD AT GUHN ROAD
To.
CSJ0912-72-645
Proj IDSTP 2B23(159)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.150229470.33299552.1099.9
Work Order09-19-23
Work Began01-04-24
Work Completed
Time Computed10-19-23
Contract Working Days120
Addl Days Granted0
Working Days Charged104
Percent Time Used86
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-634
SAFETEX,INC. (5.76)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (34.95)
CHERRY MOVING COMPANY, INC. (2.13)
AGGREGATE TECHNOLOGIES, INC. (0.27)
CASTEC CONSTRUCTION LLC (11.95)
ROYAL TRAFFIC SIGN CO. (0.30)
Contract #08233053
Totals1234892.41155390.87972025.4878.7

CountyHARRIS
HighwayCS
FromIRVINGTON BLVD AT PATTON STREET
To.
CSJ0912-72-637
Proj IDSTP 2B23(157)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.270395092.59398947.3999.9
CountyHARRIS
HighwayCS
FromRENWICK DRIVE AT DASHWOOD DRIVE
To.
CSJ0912-72-639
Proj IDSTP 2B23(157)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.380406977.31853865.0799.9
CountyHARRIS
HighwayCS
FromRICHMOND AVE AT HAYES RD
To.
CSJ0912-72-641
Proj IDSTP 2B23(157)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.150601165.05843359.6599.9
CountyHARRIS
HighwayCS
FromYALE STREET AT CENTER STREET
To.
CSJ0912-72-646
Proj IDSTP 2B23(157)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.160576751.0252867.009.1
Work Order12-05-23
Work Began01-30-24
Work Completed
Time Computed01-04-24
Contract Working Days255
Addl Days Granted0
Working Days Charged149
Percent Time Used58
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-637
AGGREGATE TECHNOLOGIES, INC. (0.67)
STRIPE LINES, INC. (6.71)
THIRD COAST SERVICES LLC (26.57)
CASTEC CONSTRUCTION LLC (4.89)
Contract #08233246
Totals1979985.9764338.002149039.1199.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS ON IH 610 & SL 8
To.
CSJ0912-72-650
Proj IDF 2022(876)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5909097.893852460.7765.1
Work Order09-15-22
Work Began04-26-23
Work Completed
Time Computed10-15-22
Contract Working Days693
Addl Days Granted0
Working Days Charged275
Percent Time Used39
Contractor(s)
SELECT MAINTENANCE, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-650
TRAFFIC SIGNS & LINES, LLC (49.37)
BAY CITY TRAFFIC (15.32)
Contract #08223011
Totals5909097.890.003852460.7765.1

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN TIRZ 1
ToST. GEORGE PLACE REDEVELOPMENT AUTHORITY
CSJ0912-72-661
Proj IDSTP 2B23(160)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.480349286.303738.001.0
CountyHARRIS
HighwayVA
FromVARIOUS
To.
CSJ0912-72-662
Proj IDSTP 2B23(160)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.7701388316.03808775.5858.2
CountyHARRIS
HighwayCS
FromBINGLE RD AT TIDWELL RD
To.
CSJ0912-72-663
Proj IDSTP 2B23(160)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.230309523.98405.000.1
CountyHARRIS
HighwayCS
FromWHEELER AVENUE
ToS MACGREGOR WAY
CSJ0912-72-674
Proj IDSTP 2B23(160)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.970331322.620.000.0
Work Order02-15-24
Work Began06-18-24
Work Completed
Time Computed03-16-24
Contract Working Days189
Addl Days Granted0
Working Days Charged104
Percent Time Used55
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-661
PROFESSIONAL TRAFFIC CONTROL LLC (1.43)
Contract #12233030
Totals2378448.93350952.54812918.5834.1

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN HARRIS COUNTY
To.
CSJ0912-72-745
Proj IDC 912-72-745
Work TypeTRAFFIC CONTROL DEVICES
 
8.845397218.180.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-10-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days62
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRP INFRASTRUCTURE SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-745
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07243021
Totals397218.180.000.000.0

CountyHARRIS
HighwayVA
FromVAR LOCATIONS IN SE HARRIS AO BOUNDARY
To.
CSJ0912-72-746
Proj IDC 912-72-746
Work TypeBRIDGE WIDENING OR REHABILITATION
 
4990800.712189864.0043.8
Work Order02-08-24
Work Began05-28-24
Work Completed
Time Computed05-08-24
Contract Working Days150
Addl Days Granted0
Working Days Charged103
Percent Time Used68
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-746
HAZMAT INTERNATIONAL, INC. (15.00)
PROFESSIONAL TRAFFIC CONTROL LLC (2.53)
SCOTT DERR PAINTING CO, LLC (0.38)
WHO-B TRUCKING, INC. (0.01)
Contract #12233014
Totals4990800.71508969.192189864.0043.8

CountyHARRIS
HighwayVA
FromVARIOUS BRIDGES ON IH 45 FROM IH 610
ToCYPRESSWOOD DRIVE
CSJ0912-72-749
Proj IDC 912-72-749
Work TypeBRIDGE WIDENING OR REHABILITATION
 
2695934.983086110.6499.9
Work Order02-02-24
Work Began03-04-24
Work Completed
Time Computed03-03-24
Contract Working Days64
Addl Days Granted0
Working Days Charged104
Percent Time Used162
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-749
HOLES INCORPORATED (0.29)
S & S BRIDGE PAINTING, INC. (2.16)
Contract #01243226
Totals2695934.98115749.493086110.6499.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN SOUTH HARRIS AREA
To.
CSJ0912-72-771
Proj IDF 2B24(235)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
2164229.930.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-22-24
Work Began00-00-00
Work Completed
Time Computed11-20-24
Contract Working Days153
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-771
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07243222
Totals2164229.930.000.000.0

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN THE METRO AREA
To.
CSJ0912-72-772
Proj IDF 2B24(351)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
4753276.240.000.0
Work Order09-06-24
Work Began00-00-00
Work Completed
Time Computed10-06-24
Contract Working Days635
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-772
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08243220
Totals4753276.240.000.000.0

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN NORTH HARRIS
To.
CSJ0912-72-801
Proj IDC 912-72-801
Work TypeBRIDGE WIDENING OR REHABILITATION
 
3348460.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days298
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-801
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11243213
Totals3348460.000.000.000.0

CountyGALVESTON
HighwayVA
FromON SH 96 FROM FM 270 TO SH 146
ToAND ON FM 270 FROM FM 2094 TO SH 96
CSJ0912-73-215
Proj IDSTP 2024(163)TP
Work TypeBICYCLE INFRASTRUCTURE IMPROVEMENTS
 
5.8307167628.345588409.7877.9
Work Order12-21-23
Work Began03-18-24
Work Completed
Time Computed01-20-24
Contract Working Days320
Addl Days Granted0
Working Days Charged148
Percent Time Used46
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-215
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.00)
SEMPER STRIPING LLC (1.19)
DEPENDABLE FENCE (0.22)
THIRD COAST SERVICES LLC (1.73)
CPAVE, INC. (0.00)
LUCAS CONSTRUCTION COMPANY (28.46)
WILLOW CITY SIGN & RAIL, INC. (0.19)
TEXAS DRAINAGE INC. (0.86)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (10.20)
CPAVE, INC. (0.06)
C.M. NUNEZ TRUCKING COMPANY (2.72)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (1.30)
Contract #11233014
Totals7167628.34638099.315588409.7877.9

CountyGALVESTON
HighwayVA
FromSH 87 AT GALVESTON FERRY
To.
CSJ0912-73-220
Proj IDF 2021(384)
Work TypeFERRY BOAT
 
22468330.0015782200.5770.6
Work Order08-02-22
Work Began09-14-22
Work Completed
Time Computed09-14-22
Contract Working Days700
Addl Days Granted31
Working Days Charged769
Percent Time Used105
Contractor(s)
SOUTHWEST SHIPYARD, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-220
RIO MARINE, INC. (0.00)
THE SHEARER GROUP, INC. (0.00)
SIEMENS ENERGY, INC. (0.00)
SKF USA INC. (0.00)
MUSTANG CAT (4.24)
Contract #06223606
Totals22468330.0093210.5115782200.5770.6

CountyGALVESTON
HighwayVA
FromVARIOUS LOCATIONS IN GALVESTON COUNTY
To.
CSJ0912-73-232
Proj IDC 912-73-232
Work TypeBRIDGE WIDENING OR REHABILITATION
 
0.0871093187.76914750.7383.6
Work Order02-02-24
Work Began05-06-24
Work Completed
Time Computed03-03-24
Contract Working Days70
Addl Days Granted0
Working Days Charged61
Percent Time Used87
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-232
HOLES INCORPORATED (1.55)
Contract #01243238
Totals1093187.760.00914750.7383.6

CountyHARRIS
HighwayFM 865
FromUA 90
ToBRAZORIA C/L
CSJ0976-01-044
Proj IDC 976-1-44
Work TypeTRAFFIC CONTROL DEVICES
 
8.310398115.1766285.8616.6
Work Order09-06-24
Work Began10-20-24
Work Completed
Time Computed10-06-24
Contract Working Days68
Addl Days Granted0
Working Days Charged17
Percent Time Used25
Contractor(s)
STRIPE LINES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0976-01-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08243032
Totals398115.1766285.8666285.8616.6

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13 | page 14 | page 15