Monthly State Let Construction Report For Houston District As Of Nov 10, 2024 Page 2 Of 15

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13 | page 14 | page 15

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayUS 90
FromIH 610 E
ToBW 8
CSJ0028-02-092
Proj IDNH 2018(415)
Work TypeINSTALL ITS EQUIPMENT & INFRASTRUC
 
6.4731782760.651941788.1599.9
Work Order05-29-18
Work Began06-28-18
Work Completed
Time Computed06-28-18
Contract Working Days375
Addl Days Granted0
Working Days Charged349
Percent Time Used93
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0028-02-092
SPECIALTY DRILLING, LLC (1.67)
Contract #04183016
Totals1782760.650.001941788.1599.9

CountyHARRIS
HighwayUS 90
FromEAST OF FM 2100
ToWEST OF LIBERTY COUNTY LINE
CSJ0028-02-098
Proj IDF 2024(675)
Work TypeOVERLAY
 
7.69211754262.009963138.0584.7
CountyHARRIS
HighwayUS 90
From0.1 MILES WEST OF BOHEMIAN HALL RD.
To0.1 MILES EAST OF BOHEMIAN HALL RD.
CSJ0028-02-105
Proj IDSTP 2B24(104)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200236907.7950537.0421.3
Work Order05-22-24
Work Began06-17-24
Work Completed
Time Computed06-21-24
Contract Working Days134
Addl Days Granted0
Working Days Charged86
Percent Time Used64
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0028-02-098
STRIPE LINES, INC. (0.09)
BATTERSON, LLP (4.84)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (3.42)
WILLOW CITY SIGN & RAIL, INC. (2.84)
PROFESSIONAL TRAFFIC CONTROL LLC (0.19)
KINGZ INDUSTRIAL LLC (3.86)
Contract #04243006
Totals11991169.792570938.4110013675.0983.5

CountyHARRIS
HighwayUS 90
From0.42 MILES EAST OF BW 8
To0.03 MILES EAST OF FM 2100
CSJ0028-02-099
Proj IDC 28-2-99
Work TypeOVERLAY
 
7.39710229817.0715446089.3099.9
Work Order03-07-24
Work Began04-30-24
Work Completed
Time Computed04-06-24
Contract Working Days134
Addl Days Granted0
Working Days Charged128
Percent Time Used95
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0028-02-099
SEMPER STRIPING LLC (3.72)
MC2 CIVIL, LLC (19.92)
AMERICAN REMEDIATION OPTIONS, INC. (3.95)
KINGZ INDUSTRIAL LLC (1.30)
DECO CONTRACTORS, INC. (0.15)
Contract #01243007
Totals10229817.074799842.3915446089.3099.9

CountyWALLER
HighwayBU 290H
FromSH 6
ToHARRIS COUNTY LINE
CSJ0050-05-067
Proj IDSTP 2020(593)
Work TypeOVERLAY
 
10.9995433536.706193298.4199.9
Work Order04-28-20
Work Began09-09-20
Work Completed
Time Computed06-29-20
Contract Working Days135
Addl Days Granted20
Working Days Charged155
Percent Time Used100
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0050-05-067
TOTAL HIGHWAY MAINTENANCE, LLC (6.25)
LONESTAR TRAFFIC SAFETY, LLC (0.26)
BATTERSON, LLP (0.30)
THIRD COAST SERVICES LLC (4.05)
WILLOW CITY SIGN & RAIL, INC. (6.06)
TEXOP CONSTRUCTION (3.36)
R & A TRANSPORT, INC. (2.13)
AVILES CONSTRUCTION SERVICE, INC (1.23)
Contract #02203007
Totals5433536.700.006193298.4199.9

CountyWALLER
HighwayBU 290H
FromAT 5TH ST
To.
CSJ0050-05-069
Proj IDSTP 2025(040)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
299331.860.000.0
CountyWALLER
HighwayBU 290H
FromAT FM 359
To.
CSJ0050-05-070
Proj IDSTP 2025(040)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
272523.340.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days140
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0050-05-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243040
Totals571855.200.000.000.0

CountyHARRIS
HighwayUS 290
FromWEST OF BADTKE
ToMUESCHKE
CSJ0050-06-089
Proj IDC 50-6-89
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
1371760.051061779.6477.4
CountyHARRIS
HighwayUS 290
FromWALLER COUNTY LINE
ToWEST OF BADTKE RD
CSJ0114-12-014
Proj IDC 114-12-14
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
935785.26121669.6313.0
Work Order09-15-22
Work Began00-00-00
Work Completed
Time Computed10-15-22
Contract Working Days270
Addl Days Granted0
Working Days Charged21
Percent Time Used7
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0050-06-089
LONESTAR TRAFFIC SAFETY, LLC (0.55)
MULHOLLAND ENERGY SERVICES, LLC (0.11)
BATTEN DRILLING, INC. (1.21)
Contract #08223211
Totals2307545.31219266.201183449.2751.2

CountyHARRIS
HighwaySH 3
FromSOUTH RICHEY STREET
ToGALVESTON COUNTY LINE
CSJ0051-02-108
Proj IDSTP 2022(405)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
14.5865450259.593952025.0477.8
Work Order04-19-22
Work Began08-03-22
Work Completed
Time Computed05-19-22
Contract Working Days223
Addl Days Granted0
Working Days Charged481
Percent Time Used215
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0051-02-108
GMJ PAVING CO. (17.46)
TRAFFIC SIGNS & LINES, LLC (14.02)
SOUTHERN EROSION, LLC (2.54)
CURB PLANET INC. (2.03)
PROFESSIONAL TRAFFIC CONTROL LLC (0.13)
TRM SERVICES LLC (0.19)
Contract #03223204
Totals5450259.59103978.783952025.0477.8

CountyGALVESTON
HighwaySH 3
FromN OF FM 1765
ToSH 146
CSJ0051-03-117
Proj IDC 51-3-117
Work TypeOVERLAY
 
2.9804384915.814091277.6393.3
Work Order03-24-22
Work Began05-14-22
Work Completed
Time Computed05-14-22
Contract Working Days150
Addl Days Granted0
Working Days Charged139
Percent Time Used92
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0051-03-117
QUALITY TURF FARMS, L.C. (0.26)
STRIPE LINES, INC. (4.27)
TRAF-TEX, INC. (11.28)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (0.87)
Contract #02223210
Totals4384915.8140000.004091277.6393.3

CountyGALVESTON
HighwaySH 3
FromHARRIS C/L
ToFM 646
CSJ0051-03-119
Proj IDSTP 2022(919)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.7001131153.801065724.7294.2
Work Order09-20-22
Work Began03-23-23
Work Completed
Time Computed10-20-22
Contract Working Days357
Addl Days Granted0
Working Days Charged229
Percent Time Used64
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0051-03-119
REPUBLIC TRAFFIC SAFETY, INC. (4.06)
LONESTAR TRAFFIC SAFETY, LLC (1.22)
TEXAS REEXCAVATION (1.87)
J.KRU LAND SERVICES, LLC (4.87)
TEXAS DRAINAGE INC. (7.48)
Contract #08223023
Totals1131153.800.001065724.7294.2

CountyGALVESTON
HighwaySH 3
From0.1 MILE WEST OF FM 517
To0.1 MILE EAST OF FM 517
CSJ0051-03-120
Proj IDSTP 2B24(341)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200315582.230.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-24
Work Began00-00-00
Work Completed
Time Computed01-16-25
Contract Working Days66
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0051-03-120
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08243045
Totals315582.230.000.000.0

CountyGALVESTON
HighwaySS 342
FromAT HEARDS LANE
To.
CSJ0051-08-019
Proj IDSTP 2021(260)HES
Work TypeTRAFFIC CONTROL DEVICES
 
2.000243649.85196978.3580.8
CountyBRAZORIA
HighwaySH 35
FromAT FM 524
To.
CSJ0179-11-004
Proj IDSTP 2021(260)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200145343.20263702.9099.9
CountyBRAZORIA
HighwaySH 332
FromAT FM 523
To.
CSJ0586-01-068
Proj IDSTP 2021(260)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.20019680.000.000.0
CountyGALVESTON
HighwayFM 2004
From0.5 MI N OF TACQUARD RANCH ROAD
To0.5 MI S OF TACQUARD RANCH ROAD
CSJ2523-01-027
Proj IDSTP 2021(260)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.00049795.000.000.0
Work Order03-01-21
Work Began03-18-22
Work Completed
Time Computed06-29-21
Contract Working Days61
Addl Days Granted0
Working Days Charged26
Percent Time Used42
Contractor(s)
CITYLYNX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0051-08-019
SPECIALTY DRILLING (5.58)
H & N CONTRACTOR MANAGEMENT SERVICES LLC (0.00)
REDLINE CONSTRUCTION SERVICES LLC (8.93)
Contract #01213222
Totals458468.0519290.35460681.2599.9

CountyGALVESTON
HighwayFM 3005
FromAT 89TH ST
To.
CSJ0051-09-126
Proj IDSTP 2022(920)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.600848580.69541806.6863.8
Work Order09-15-22
Work Began00-00-00
Work Completed
Time Computed01-13-23
Contract Working Days86
Addl Days Granted0
Working Days Charged33
Percent Time Used38
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0051-09-126
LONESTAR TRAFFIC SAFETY, LLC (0.58)
Contract #08223242
Totals848580.6943351.70541806.6863.8

CountyFORT BEND
HighwayUS 59
FromWEST OF HAMLINK ROAD
ToWEST OF SPUR 10
CSJ0089-09-058
Proj IDC 89-9-58
Work TypeGR, STRS, BS & SURF
 
8.004100144090.32101029717.4399.9
Work Order01-06-16
Work Began01-18-16
Work Completed
Time Computed01-18-16
Contract Working Days919
Addl Days Granted201
Working Days Charged1,120
Percent Time Used100
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0089-09-058
BASE CONSTRUCTION (9.99)
CPAVE, INC. (0.24)
CREACOM, INC. (3.26)
ESSARY, HART & MACWILIAM,INC. (6.93)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
INTERSTATE BARRICADES & MARKINGS, INC. (0.96)
QUALITY TURF FARMS, LC (2.08)
SCOTT DERR PAINTING CO, LLC (0.01)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.13)
BORTUNCO (0.23)
WASTE PARTNERS OF TEXAS, INC (0.07)
ANTIGO CONSTRUCTION, INC. (0.03)
RAY"S THREADING AND FAB SHOP (0.72)
STEEL EFFECTS (0.08)
WEST TEXAS ROCK RESOURCES, LLC (0.10)
CURB PLANET INC. (0.02)
PINNACLE GRINDING AND GROOVING LLC (0.00)
Contract #12153001
Totals100144090.3230189.83101029717.4399.9

CountyMONTGOMERY
HighwayIH 45
FromS OF SHENANDOAH PARK DR
ToSH 242
CSJ0110-04-202
Proj IDSTP 2023(491)MM
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
1.12325562343.350.000.0
CountyMONTGOMERY
HighwayIH 45
FromAT SH 242
To.
CSJ0110-04-205
Proj IDCC 110-4-205
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
0.01917068407.880.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-02-24
Work Began00-00-00
Work Completed
Time Computed11-01-24
Contract Working Days683
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0110-04-202
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08243202
Totals42630751.230.000.000.0

CountyMONTGOMERY ETC
HighwayIH 45
FromHARRIS COUNTY LINE
ToSL 336 (SOUTH)
CSJ0110-04-208
Proj IDF 2B24(055)
Work TypeTRAFFIC CONTROL DEVICES
 
43.9709044581.7054709.860.6
Work Order08-22-24
Work Began00-00-00
Work Completed
Time Computed09-21-24
Contract Working Days491
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0110-04-208
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07243206
Totals9044581.7054709.8654709.860.6

CountyMONTGOMERY
HighwayIH 45
FromNORTH OF FM 1488
ToSL 336 (SOUTH)
CSJ0110-04-209
Proj IDC 110-4-209
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
2.2161297846.950.000.0
Work Order08-22-24
Work Began00-00-00
Work Completed
Time Computed09-21-24
Contract Working Days78
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MC2 CIVIL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0110-04-209
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07243012
Totals1297846.950.000.000.0

CountyMONTGOMERY ETC
HighwayIH 45 ETC
FromSL 336 SOUTH
ToHARRIS COUNTY LINE
CSJ0110-04-219
Proj IDC 110-4-219
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
54.1032579831.802190064.5184.9
Work Order02-14-23
Work Began03-16-23
Work Completed
Time Computed03-16-23
Contract Working Days135
Addl Days Granted0
Working Days Charged136
Percent Time Used100
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0110-04-219
R & A DIRECTIONAL BORING (0.15)
SCOTT DERR PAINTING CO, LLC (0.17)
Contract #01233219
Totals2579831.8029884.402190064.5184.9

CountyHARRIS
HighwayIH 45
FromAT FM 1960
To.
CSJ0110-05-130
Proj IDSTP 2021(259)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.200474658.72567091.2199.9
Work Order03-05-21
Work Began06-30-23
Work Completed
Time Computed07-03-21
Contract Working Days93
Addl Days Granted0
Working Days Charged84
Percent Time Used90
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0110-05-130
STRIPE LINES, INC. (4.29)
Contract #01213024
Totals474658.723630.78567091.2199.9

CountyHARRIS
HighwayIH 45
FromKUYKENDAHL
ToFM 1960
CSJ0110-05-140
Proj IDC 110-5-140
Work TypeTRAFFIC CONTROL DEVICES
 
5.677423534.75455503.3099.9
Work Order02-27-23
Work Began04-27-23
Work Completed
Time Computed03-29-23
Contract Working Days69
Addl Days Granted0
Working Days Charged47
Percent Time Used68
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0110-05-140
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01233232
Totals423534.750.00455503.3099.9

CountyHARRIS
HighwayIH 45
FromAT WEST ROAD
To.
CSJ0110-06-143
Proj IDSTP 2020(204)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.200485208.48683511.0999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-19-19
Work Began04-17-20
Work Completed
Time Computed00-00-00
Contract Working Days59
Addl Days Granted0
Working Days Charged56
Percent Time Used94
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0110-06-143
MENADE, INC. (13.63)
SEMPER STRIPING LLC (5.35)
Contract #11193021
Totals485208.482823.18683511.0999.9