Monthly State Let Construction Report For Houston District As Of Nov 10, 2024 Page 15 Of 15
Last Update: Sunday, November 10, 2024
 |
|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | HARRIS |
Highway | MH |
From | ON HEMPSTEAD RD, 0.059 MI W OF 12 |
To | ST TO E OF WASHINGTON-KATY SPLIT |
CSJ | 8170-12-001 |
Proj ID | STP 2013(567) |
Work Type | GR, STRS & SURF |
|
| 1.023 | 49926139.96 | | 47598323.55 | 97.4 |
Work Order | 11-02-17 |
Work Began | 02-20-18 |
Work Completed | |
Time Computed | 01-31-18 |
Contract Working Days | 1,225 |
Addl Days Granted | 42 |
Working Days Charged | 1,854 |
Percent Time Used | 146 |
Contractor(s) |
JAMES CONSTRUCTION GROUP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 8170-12-001 AR DANIEL CONSTRUCTION SERVICES, INC. (2.15) J.H. PAINTING COMPANY (0.15) PELTIER BROTHERS CONSTRUCTION, LTD. (13.86) PRIMATE CONSTRUCTION, INC. (0.11) R & R CONCRETE CONTRACTORS, INC. (7.39) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.28) THIRD COAST SERVICES LLC (1.64) WILLOW CITY SIGN & RAIL, INC. (0.07) ROSALES TRUCKING (2.07) W. W. FOUNDATION DRILLING, LTD. (8.72) CHOCTAW ERECTORS, INC. (7.50) HIGHWAY 1, LLC (0.26) LONESTAR TRAFFIC SAFETY, LLC (0.10) DORAN STEEL, INC. (0.49) HARBOUR CONTRACTORS, INC. (7.42) MB WESTERN INDUSTRIAL CONTRACTING (5.21) EUBANK EXCAVATION, L.L.C. (0.09) SEMARCK LANDSCAPE SERVICES, INC. (0.66) SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.42) CHERRY CRUSHED CONCRETE (0.20) BOOT CONSTRUCTION, LLC (0.00) HOWARD PILE DRIVING COMPANY, INC. (0.99) TEXAS MOISTURE PROTECTION COMPANY (0.49) CURB PLANET INC. (0.02) SOWELLS CONSULTING ENGINEERS, LLC (0.23) ELECTRIC CONTROL & SERVICE, INC. (0.71) ISJ UNDERGROUND UTILITIES LLC (0.28) BUYERS BARRICADES HOUSTON, LLC (0.03) TEXAS MATERIALS GROUP, INC. (0.59)
|
Contract # | 05173201 |
| Totals | 49926139.96 | 12917.77 | 47598323.55 | 97.4 |
|