Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | HARRIS |
Highway | IH 610 |
From | SH 225 |
To | IH 45 S |
CSJ | 0502-01-232 |
Proj ID | C 502-1-232 |
Work Type | TRAFFIC CONTROL DEVICES |
|
| 1.570 | 288348.04 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 10-10-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 17 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
TRP INFRASTRUCTURE SERVICES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-232 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05243245 |
| Totals | 288348.04 | 0.00 | 0.00 | 0.0 |
|
County | HARRIS |
Highway | SH 225 |
From | IH 610 EAST |
To | SH 146 |
CSJ | 0502-01-235 |
Proj ID | C 502-1-235 |
Work Type | TRAFFIC CONTROL DEVICES |
|
| 2.607 | 1262658.44 | | 455070.31 | 36.0 |
Work Order | 03-14-24 |
Work Began | 06-03-24 |
Work Completed | |
Time Computed | 04-13-24 |
Contract Working Days | 133 |
Addl Days Granted | 0 |
Working Days Charged | 62 |
Percent Time Used | 46 |
Contractor(s) |
PROFESSIONAL TRAFFIC CONTROL LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-235 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12233017 |
| Totals | 1262658.44 | 115111.20 | 455070.31 | 36.0 |
|
County | HARRIS |
Highway | SH 225 |
From | SENS RD |
To | ROBIN ST |
CSJ | 0502-01-237 |
Proj ID | STP 2B24(345)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 658352.03 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 11-07-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 152 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
TRAF-TEX, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-237 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08243233 |
| Totals | 658352.03 | 0.00 | 0.00 | 0.0 |
|
County | HARRIS |
Highway | IH 10 |
From | GARTH ROAD |
To | CHAMBERS C/L |
CSJ | 0508-01-356 |
Proj ID | NH 2018(760) |
Work Type | INSTALL ITS EQUIPMENT & INFRASTRCTR |
|
| 8.030 | 4844982.30 | | 5588185.75 | 99.9 |
Work Order | 08-02-18 |
Work Began | 09-01-18 |
Work Completed | |
Time Computed | 09-01-18 |
Contract Working Days | 450 |
Addl Days Granted | 0 |
Working Days Charged | 445 |
Percent Time Used | 98 |
Contractor(s) |
TRAF-TEX, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-356 SPECIALTY DRILLING, LLC (1.20) BTM SERVICES, LLC (1.43)
|
Contract # | 04183019 |
| Totals | 4844982.30 | 0.00 | 5588185.75 | 99.9 |
|
County | HARRIS |
Highway | IH 10 |
From | AT LOCKWOOD DR |
To | . |
CSJ | 0508-01-385 |
Proj ID | STP 2B24(346)VRU |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 0.200 | 753027.04 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 09-18-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 01-16-25 |
Contract Working Days | 195 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
THIRD COAST SERVICES LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-385 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08243031 |
| Totals | 753027.04 | 0.00 | 0.00 | 0.0 |
|
County | HARRIS |
Highway | IH 10 |
From | IH 610 |
To | CEDAR BAYOU/CHAMBERS COUNTY LINE |
CSJ | 0508-01-391 |
Proj ID | C 508-1-391 |
Work Type | OVERLAY |
|
| 21.430 | 18279582.41 | | 0.00 | 0.0 |
Work Order | 09-26-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 10-26-24 |
Contract Working Days | 137 |
Addl Days Granted | 0 |
Working Days Charged | 2 |
Percent Time Used | 1 |
Contractor(s) |
TEXAS MATERIALS GROUP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-391 BATTERSON, LLP (11.91) MC2 CIVIL, LLC (15.30) LONESTAR TRAFFIC SAFETY, LLC (0.14) KINGZ INDUSTRIAL LLC (1.46) SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (1.29)
|
Contract # | 08243208 |
| Totals | 18279582.41 | 0.00 | 0.00 | 0.0 |
|
County | HARRIS ETC |
Highway | IH 10 ETC |
From | IH 45 |
To | CHAMBERS COUNTY LINE |
CSJ | 0508-01-394 |
Proj ID | C 508-1-394 |
Work Type | LANDSCAPE & SCENIC ENHANCEMENT |
|
| 92.773 | 2043682.41 | | 1344299.70 | 65.7 |
Work Order | 03-21-24 |
Work Began | 04-22-24 |
Work Completed | |
Time Computed | 04-20-24 |
Contract Working Days | 120 |
Addl Days Granted | 0 |
Working Days Charged | 96 |
Percent Time Used | 80 |
Contractor(s) |
YELLOWSTONE LANDSCAPE - CENTRAL, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-394 BLUE SKY RIGHT OF WAY, LLC (11.74)
|
Contract # | 02243028 |
| Totals | 2043682.41 | 198938.52 | 1344299.70 | 65.7 |
|
County | WALLER |
Highway | FM 362 |
From | BU 290H |
To | 0.25 MI SOUTH OF DAVIS ROAD |
CSJ | 0523-02-051 |
Proj ID | C 523-2-51 |
Work Type | OVERLAY |
|
| 8.096 | 4087471.73 | | 3942833.47 | 96.4 |
Work Order | 02-02-24 |
Work Began | 03-04-24 |
Work Completed | |
Time Computed | 03-03-24 |
Contract Working Days | 76 |
Addl Days Granted | 0 |
Working Days Charged | 76 |
Percent Time Used | 100 |
Contractor(s) |
DURWOOD GREENE CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0523-02-051 TRAFFIC SIGNS & LINES, LLC (8.11) PROFESSIONAL TRAFFIC CONTROL LLC (0.33) CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (2.85) TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.40) BATTERSON, LLP (3.98) INTERSTATE BARRICADES & MARKINGS, INC. (0.37)
|
Contract # | 01243246 |
| Totals | 4087471.73 | 0.00 | 3942833.47 | 96.4 |
|
County | MONTGOMERY |
Highway | FM 1488 |
From | WALLER COUNTY LINE |
To | FM 1774 IN MAGNOLIA |
CSJ | 0523-08-007 |
Proj ID | C 523-8-7 |
Work Type | WIDEN NON-FREEWAY |
|
| 3.788 | 29031633.34 | | 32748484.94 | 99.9 |
County | MONTGOMERY |
Highway | FM 1488 |
From | WALLER COUNTY LINE |
To | FM 1774 IN MAGNOLIA |
CSJ | 0523-08-010 |
Proj ID | ROW 523-8-10 |
Work Type | RIGHT OF WAY |
|
| 3.788 | 755774.55 | | 654466.00 | 86.5 |
Work Order | 09-03-20 |
Work Began | 11-23-20 |
Work Completed | |
Time Computed | 12-02-20 |
Contract Working Days | 555 |
Addl Days Granted | 0 |
Working Days Charged | 493 |
Percent Time Used | 88 |
Contractor(s) |
LINDSEY CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0523-08-007 A1 EROSION CONTROL (2.33) CITYLYNX, INC. (1.47) CPAVE, INC. (0.30) HIGHWAY 1 LLC (1.22) STORM WATER SOLUTIONS, LP (0.68) SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.60) CURB PLANET INC. (0.00) TROY ATKINSON (0.26) JMHP, INC. (0.49) VULCAN CONSTRUCTION MATERIALS, LP (6.79) MESA ROD BUSTERS, INC. (1.26) VULCAN CONSTRUCTION (6.79) G & D DIRECCIONAL (0.24) LARRY YOUNG PAVING, INC. (51.70) DORAN STEEL, INC. (1.75) AG & OIL 365 ENERGY LLC (0.07) MEMCO (0.50) WILLOW CITY SIGN & RAIL, INC. (0.22) SARVICUS LLC (1.37)
|
Contract # | 07203005 |
| Totals | 29787407.89 | 485890.20 | 33402950.94 | 99.9 |
|
County | MONTGOMERY |
Highway | FM 1488 |
From | FM 1774 IN MAGNOLIA |
To | WEST OF FM 149 |
CSJ | 0523-09-009 |
Proj ID | C 523-9-9 |
Work Type | WIDEN NON-FREEWAY |
|
| 4.030 | 45997097.64 | | 24978386.88 | 54.3 |
County | MONTGOMERY |
Highway | FM 1488 |
From | FM 1774 IN MAGNOLIA |
To | WEST OF FM 149 |
CSJ | 0523-09-017 |
Proj ID | ROW 523-9-17 |
Work Type | RIGHT OF WAY |
|
| 4.030 | 2288466.32 | | 1256343.71 | 54.8 |
Work Order | 03-16-22 |
Work Began | 06-14-22 |
Work Completed | |
Time Computed | 06-30-22 |
Contract Working Days | 622 |
Addl Days Granted | 0 |
Working Days Charged | 522 |
Percent Time Used | 83 |
Contractor(s) |
JAMES CONSTRUCTION GROUP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0523-09-009 HIGHWAY 1 LLC (1.30) DUSTROL, INC. (0.49) HB FARMER FOUNDATION, LLC (1.71) THIRD COAST SERVICES LLC (2.00) WILLOW CITY SIGN & RAIL, INC. (0.44) MESA ROD BUSTERS, INC. (0.81) BUYERS BARRICADES, INC. (0.00) CEN TEX HYDROSEED, INC. (1.69) ISJ UNDERGROUND UTILITIES LLC (1.98) CHERRY DEMOLITION (0.17) PRIMATE CONSTRUCTION, LP (0.20) BUYERS BARRICADES HOUSTON, LLC (0.09) VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC (5.27) CPAVE, INC. (0.08) CONSOLIDATED CRANE & RIGGING (0.10) MICKIE SERVICE, INC. (0.29) CURB PLANET INC. (0.20)
|
Contract # | 08213204 |
| Totals | 48285563.96 | 1042870.04 | 26234730.59 | 54.3 |
|
County | MONTGOMERY |
Highway | FM 1488 |
From | IH 45 |
To | MOSTYN DRIVE |
CSJ | 0523-10-047 |
Proj ID | STP 2022(307)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 12.435 | 10225881.20 | | 6832948.66 | 66.8 |
Work Order | 05-10-22 |
Work Began | 07-06-23 |
Work Completed | |
Time Computed | 07-11-22 |
Contract Working Days | 426 |
Addl Days Granted | 125 |
Working Days Charged | 517 |
Percent Time Used | 93 |
Contractor(s) |
ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0523-10-047 TRAFFIC SIGNS & LINES, LLC (1.19) THIRD COAST SERVICES LLC (7.48) CURB PLANET INC. (1.15) PIPE WHOLESALERS OF TEXAS, INC. (1.07) GEORGE MEEKS LANDPRO, INC. (1.55) A&J REBAR LLC (0.09) ROSALES TRUCKING (5.13) SK CONCRETE SERVICES LLC (0.54) HIGHWAY 1 LLC (8.24)
|
Contract # | 04223205 |
| Totals | 10225881.20 | 353106.84 | 6832948.66 | 66.8 |
|
County | FORT BEND |
Highway | FM 1875 |
From | UA 90 |
To | SL 540 |
CSJ | 0527-05-012 |
Proj ID | C 527-5-12 |
Work Type | OVERLAY |
|
| 4.594 | 1497972.35 | | 2288924.39 | 99.9 |
Work Order | 05-03-24 |
Work Began | 06-17-24 |
Work Completed | |
Time Computed | 06-17-24 |
Contract Working Days | 45 |
Addl Days Granted | 0 |
Working Days Charged | 45 |
Percent Time Used | 100 |
Contractor(s) |
DURWOOD GREENE CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0527-05-012 TRAFFIC SIGNS & LINES, LLC (4.65) PROFESSIONAL TRAFFIC CONTROL LLC (0.59) INTERSTATE BARRICADES & MARKINGS, INC. (0.72) BATTERSON, LLP (4.49)
|
Contract # | 03243219 |
| Totals | 1497972.35 | 372.00 | 2288924.39 | 99.9 |
|
County | BRAZORIA |
Highway | FM 1495 |
From | E BROAD ST |
To | SH 36 |
CSJ | 0587-01-064 |
Proj ID | C 587-1-64 |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 0.779 | 7143864.17 | | 4009511.10 | 56.1 |
Work Order | 06-22-22 |
Work Began | 02-06-23 |
Work Completed | |
Time Computed | 08-22-22 |
Contract Working Days | 375 |
Addl Days Granted | 194 |
Working Days Charged | 434 |
Percent Time Used | 76 |
Contractor(s) |
TRIPLE B SERVICES LLP |
SUBCONTRACTOR(S) FOR CCSJ: 0587-01-064 HIGHWAY 1 LLC (2.77) SORRELL CONSTRUCTION, EQUIPMENT & MATERIALS, LLC (1.97) STRIPES & STOPS COMPANY, INC. (1.59) AIMS COMPANIES (0.44) SAW & SEAL OF TEXAS LLC (1.99) TEXAS ENVIRONMENTAL CONTROL, INC. (0.23) DOUBLE OAK EROSION, INC. (0.49) QUALITY TURF FARMS, L.C. (1.38) TRAF-TEX, INC. (0.08) DUSTROL, INC. (1.15) MEMCO STAFFING, LLC (2.09) HERMANOS STEEL, LLC (0.96) C. M. NUNEZ TRUCKING, INC. (0.00) HASS HORIZONTAL, LLC (0.00) GMJ PAVING COMPANY LLC (3.61) C.M. NUNEZ TRUCKING COMPANY (0.88) HASS CO, LLC (0.36) INLAND ENVIRONMENTS, LTD. (0.23) SMYRNA READY MIX CONCRETE, LLC (1.59) MASTER CURB, LLC (0.10) CONARMET LLC (1.88) M AND J CONSTRUCTION SAWING (0.04) HODGES BROTHERS, INC. (0.11) TRAFFIC SIGNS & LINES, LLC (0.22)
|
Contract # | 05223005 |
| Totals | 7143864.17 | 120558.20 | 4009511.10 | 56.1 |
|
County | HARRIS |
Highway | SH 288 |
From | IH 69 |
To | IH 610 SOUTH |
CSJ | 0598-01-104 |
Proj ID | C 598-1-104 |
Work Type | TRAFFIC CONTROL DEVICES |
|
| 3.821 | 509263.67 | | 52817.95 | 10.3 |
Work Order | 02-27-23 |
Work Began | 08-25-24 |
Work Completed | |
Time Computed | 03-29-23 |
Contract Working Days | 62 |
Addl Days Granted | 0 |
Working Days Charged | 11 |
Percent Time Used | 17 |
Contractor(s) |
BATTERSON, LLP |
SUBCONTRACTOR(S) FOR CCSJ: 0598-01-104 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01233028 |
| Totals | 509263.67 | 0.00 | 52817.95 | 10.3 |
|
County | HARRIS |
Highway | SH 288 |
From | NORTH MACGREGOR WAY |
To | IH 69 |
CSJ | 0598-01-105 |
Proj ID | C 598-1-105 |
Work Type | CULVERT & STORM DRAINAGE WORK |
|
| | 32300513.80 | | 13156744.23 | 40.7 |
County | HARRIS |
Highway | SH 288 |
From | NORTH MACGREGOR WAY |
To | IH 69 |
CSJ | 0598-01-107 |
Proj ID | ROW 0598-01-107 |
Work Type | RIGHT OF WAY |
|
| | 1494704.00 | | 124620.00 | 8.3 |
Work Order | 07-26-23 |
Work Began | 01-17-24 |
Work Completed | |
Time Computed | 10-24-23 |
Contract Working Days | 735 |
Addl Days Granted | 1 |
Working Days Charged | 180 |
Percent Time Used | 24 |
Contractor(s) |
MAIN LANE INDUSTRIES LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0598-01-105 LONESTAR TRAFFIC SAFETY, LLC (0.13) QUALITY TURF FARMS, L.C. (0.49) HIGHWAY 1 LLC (0.38) RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC (1.76) A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (7.87) CHERRY MOVING COMPANY, INC. (0.25) HUNTER WELLPOINT, INC. (2.68) CASTEC CONSTRUCTION LLC (1.11) SK CONCRETE SERVICES LLC (0.12) DOUBLE OAK EROSION, INC. (0.06) MESA ROD BUSTERS, INC. (0.19) MICKIE SERVICE, INC. (0.06) DIXIE FOUNDATION DRILLING CO. (0.00) ROYAL TRAFFIC SIGN CO. (0.04) C. & C.S., INC. (0.23) CAPSTONE DEVELOPMENT GROUP LLC (0.95)
|
Contract # | 06233403 |
| Totals | 33795217.80 | 1688184.99 | 13281364.23 | 39.2 |
|
County | HARRIS |
Highway | SH 288 |
From | SIMS BAYOU |
To | AIRPORT BLVD |
CSJ | 0598-01-108 |
Proj ID | CC 598-1-108 |
Work Type | NEW LOCATION FREEWAY |
|
| | 3336063.59 | | 4739494.32 | 99.9 |
Work Order | 06-28-23 |
Work Began | 08-16-23 |
Work Completed | |
Time Computed | 07-28-23 |
Contract Working Days | 165 |
Addl Days Granted | 0 |
Working Days Charged | 156 |
Percent Time Used | 94 |
Contractor(s) |
R CONSTRUCTION CIVIL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0598-01-108 HIGHWAY 1 LLC (1.31) TRAF-TEX, INC. (7.52) CURB PLANET INC. (0.05) QUALITY TURF FARMS, L.C. (4.84) GMJ PAVING COMPANY LLC (2.88) A&J REBAR LLC (0.67) SEAMARCK LANDSCAPE SERVICES, INC (0.75) SPECIALTY DRILLING, LLC (0.35) TERRACON CONSULTANTS, INC. (0.06) A-1 CONSTRUCTION SERVICES (0.69) WILLOW CITY SIGN & RAIL, INC. (1.65)
|
Contract # | 05233029 |
| Totals | 3336063.59 | 0.00 | 4739494.32 | 99.9 |
|
County | BRAZORIA |
Highway | SH 288 |
From | NORTH OF SH 6 |
To | RODEO PALMS PKWY |
CSJ | 0598-02-111 |
Proj ID | STP 2022(575)MM |
Work Type | INTERCHANGE (NEW OR RECONSTRUCTED) |
|
| 1.513 | 50829745.55 | | 41373813.01 | 81.3 |
Work Order | 09-15-22 |
Work Began | 10-31-22 |
Work Completed | |
Time Computed | 10-15-22 |
Contract Working Days | 702 |
Addl Days Granted | 0 |
Working Days Charged | 578 |
Percent Time Used | 82 |
Contractor(s) |
JAMES CONSTRUCTION GROUP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-111 HB FARMER FOUNDATION, LLC (2.82) MILSTEAD HIGHWAY SERVICES, LLC (0.57) INTERSTATE BARRICADES & MARKINGS, INC. (0.07) SCOTT DERR PAINTING CO, LLC (0.21) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.17) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.96) PRIMATE CONSTRUCTION, LP (0.01) A&J REBAR LLC (3.25) ALLSTATE SIGNAL & CONSTRUCTION, LLC (2.88) PROFESSIONAL TRAFFIC CONTROL LLC (0.42) CHERRY CRUSHED CONCRETE (1.31) JASSO"S SAWING & SEALING (0.16) CURB PLANET INC. (0.01) SOUTHEAST GRINDING AND GROOVING LLC (0.06) LAWNSCAPES UNLIMITED (0.07) BLS SERVICES (0.06) WILLOW CITY SIGN & RAIL, INC. (0.15) DORAN STEEL, INC. (0.12) SPECIALTY DRILLING, LLC (0.03) CHIRON COMMUNICATION SERVICES, LLC (0.09) YELLOWSTONE LANDSCAPE - CENTRAL, INC. (0.06) VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC (5.64) ASHTON SAWING AND DRILLING LLC (0.03)
|
Contract # | 08223204 |
| Totals | 50829745.55 | 1558219.03 | 41373813.01 | 81.3 |
|
County | BRAZORIA |
Highway | SH 288 |
From | AT CR 48 (IOWA COLONY BLVD) |
To | . |
CSJ | 0598-02-112 |
Proj ID | C 598-2-112 |
Work Type | INTERCHANGE (NEW OR RECONSTRUCTED) |
|
| 0.050 | 38504600.15 | | 36250551.04 | 94.1 |
Work Order | 08-02-22 |
Work Began | 11-08-22 |
Work Completed | |
Time Computed | 09-01-22 |
Contract Working Days | 409 |
Addl Days Granted | 0 |
Working Days Charged | 395 |
Percent Time Used | 96 |
Contractor(s) |
GRANITE CONSTRUCTION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-112 HB FARMER FOUNDATION, LLC (2.16) REPUBLIC TRAFFIC SAFETY, INC. (0.41) QUALITY TURF FARMS, L.C. (1.88) C.G. ANTHONY DELIVERIES, LLC (0.37) DUSTROL, INC. (3.84) PROFESSIONAL TRAFFIC CONTROL LLC (0.30) A&J REBAR LLC (0.11) MILSTEAD HIGHWAY SERVICES, LLC (0.55) ANTIGO CONSTRUCTION, INC. (0.10) A&J REBAR LLC (0.58) CREACOM, INC. (1.22) JAMES CONSTRUCTION GROUP, LLC (5.53) JRB ENGINEERING, LLC (0.15) SB FLEET - LUBE, LLC (0.22) PRIMATE CONSTRUCTION, LP (0.20) ROMAR UNLIMITED, INC. (0.82) CURB PLANET INC. (0.02) FORDE CONSTRUCTION COMPANY, INC. (0.27) ALLSTATE SIGNAL & CONSTRUCTION, LLC (0.32) DORAN STEEL, INC. (0.13) AARON CONCRETE CONTRACTORS, LLC (1.09) ROADWAY SPECIALTIES, INC. (0.30) YELLOWSTONE LANDSCAPE - CENTRAL, INC. (0.04) VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC (5.53) WILLOW CITY SIGN & RAIL, INC. (0.10) ROYAL REBAR (0.12) CLEAN-CO SYSTEMS, INC. (0.04)
|
Contract # | 06223404 |
| Totals | 38504600.15 | 2681173.37 | 36250551.04 | 94.1 |
|
County | BRAZORIA |
Highway | SH 288 |
From | AT CR 57 (CEDAR RAPIDS PARKWAY) |
To | . |
CSJ | 0598-02-113 |
Proj ID | C 598-2-113 |
Work Type | INTERCHANGE (NEW OR RECONSTRUCTED) |
|
| 1.085 | 21548238.48 | | 16290605.22 | 75.6 |
County | BRAZORIA |
Highway | SH 288 |
From | AT CR 64 (DAVENPORT PARKWAY) |
To | . |
CSJ | 0598-02-114 |
Proj ID | C 598-2-114 |
Work Type | INTERCHANGE (NEW OR RECONSTRUCTED) |
|
| 0.987 | 21418853.49 | | 15870433.63 | 74.0 |
County | BRAZORIA |
Highway | SH 288 |
From | AT CR 56 (MERIDIANA PARKWAY) |
To | . |
CSJ | 0598-02-125 |
Proj ID | F 2022(574) |
Work Type | BRIDGE WIDENING OR REHABILITATION |
|
| 1.020 | 14519659.33 | | 13549246.32 | 93.3 |
Work Order | 09-15-22 |
Work Began | 11-14-22 |
Work Completed | |
Time Computed | 11-14-22 |
Contract Working Days | 796 |
Addl Days Granted | 27 |
Working Days Charged | 569 |
Percent Time Used | 69 |
Contractor(s) |
GRANITE CONSTRUCTION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-113 HB FARMER FOUNDATION, LLC (4.39) QUALITY TURF FARMS, L.C. (2.89) REPUBLIC TRAFFIC SAFETY, INC. (0.56) C.G. ANTHONY DELIVERIES, LLC (0.95) PROFESSIONAL TRAFFIC CONTROL LLC (0.72) A&J REBAR LLC (0.21) MILSTEAD HIGHWAY SERVICES, LLC (0.74) A BROTHERS MILLING, LLC (0.42) A&J REBAR LLC (0.82) ALLSTATE SIGNAL & CONSTRUCTION, LLC (2.74) BLS SERVICES (0.14) KLP COMMERCIAL, L.L.C. (3.92) JAMES CONSTRUCTION GROUP, LLC (3.32) JRB ENGINEERING, LLC (0.10) SB FLEET - LUBE, LLC (0.00) PRIMATE CONSTRUCTION, LP (0.19) ROMAR UNLIMITED, INC. (0.53) CURB PLANET INC. (0.02) SB FLEET - LUBE, LLC (0.21) AARON CONCRETE CONTRACTORS, LLC (0.43) USW-MENARD, INC. (0.15) ROADWAY SPECIALTIES, INC. (0.32) YELLOWSTONE LANDSCAPE - CENTRAL, INC. (0.09) VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC (1.44) WILLOW CITY SIGN & RAIL, INC. (0.14)
|
Contract # | 08223004 |
| Totals | 57486751.30 | 1083356.74 | 45710285.17 | 79.5 |
|
County | BRAZORIA |
Highway | SH 288 |
From | AT CR 63 (DUBUQUE PARKWAY) |
To | . |
CSJ | 0598-02-115 |
Proj ID | C 598-2-115 |
Work Type | INTERCHANGE (NEW OR RECONSTRUCTED) |
|
| 1.382 | 22518415.39 | | 19679044.17 | 87.3 |
County | BRAZORIA |
Highway | SH 288 |
From | AT CR 60 |
To | . |
CSJ | 0598-02-116 |
Proj ID | F 2022(929) |
Work Type | INTERCHANGE (NEW OR RECONSTRUCTED) |
|
| 1.605 | 26850064.02 | | 19233694.41 | 71.6 |
Work Order | 09-15-22 |
Work Began | 11-14-22 |
Work Completed | |
Time Computed | 11-14-22 |
Contract Working Days | 629 |
Addl Days Granted | 0 |
Working Days Charged | 571 |
Percent Time Used | 90 |
Contractor(s) |
GRANITE CONSTRUCTION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-115 HB FARMER FOUNDATION, LLC (2.94) QUALITY TURF FARMS, L.C. (2.38) REPUBLIC TRAFFIC SAFETY, INC. (0.39) C.G. ANTHONY DELIVERIES, LLC (1.73) PROFESSIONAL TRAFFIC CONTROL LLC (0.91) A&J REBAR LLC (0.12) MILSTEAD HIGHWAY SERVICES, LLC (0.99) ANTIGO CONSTRUCTION, INC. (0.05) A BROTHERS MILLING, LLC (0.59) A&J REBAR LLC (0.69) CREACOM, INC. (0.43) BLS SERVICES (0.27) KLP COMMERCIAL, L.L.C. (0.82) JAMES CONSTRUCTION GROUP, LLC (6.89) JRB ENGINEERING, LLC (0.11) SB FLEET - LUBE, LLC (0.00) PRIMATE CONSTRUCTION, LP (0.22) ROMAR UNLIMITED, INC. (0.77) FORDE CONSTRUCTION COMPANY, INC. (0.29) SB FLEET - LUBE, LLC (0.32) AARON CONCRETE CONTRACTORS, LLC (0.63) YELLOWSTONE LANDSCAPE - CENTRAL, INC. (0.09) ROADWAY SPECIALTIES, INC. (0.26) ROYAL REBAR (0.05) VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC (0.68) WILLOW CITY SIGN & RAIL, INC. (0.23) GMJ PAVING COMPANY LLC (1.57) ALLSTATE SIGNAL & CONSTRUCTION, LLC (0.64)
|
Contract # | 08223205 |
| Totals | 49368479.41 | 820706.65 | 38912738.58 | 78.8 |
|