Monthly State Let Construction Report For Houston District As Of Nov 10, 2024 Page 7 Of 15

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13 | page 14 | page 15

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayIH 610
FromSH 225
ToIH 45 S
CSJ0502-01-232
Proj IDC 502-1-232
Work TypeTRAFFIC CONTROL DEVICES
 
1.570288348.040.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-10-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days17
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRP INFRASTRUCTURE SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-232
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05243245
Totals288348.040.000.000.0

CountyHARRIS
HighwaySH 225
FromIH 610 EAST
ToSH 146
CSJ0502-01-235
Proj IDC 502-1-235
Work TypeTRAFFIC CONTROL DEVICES
 
2.6071262658.44455070.3136.0
Work Order03-14-24
Work Began06-03-24
Work Completed
Time Computed04-13-24
Contract Working Days133
Addl Days Granted0
Working Days Charged62
Percent Time Used46
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-235
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12233017
Totals1262658.44115111.20455070.3136.0

CountyHARRIS
HighwaySH 225
FromSENS RD
ToROBIN ST
CSJ0502-01-237
Proj IDSTP 2B24(345)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
658352.030.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-07-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days152
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-237
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08243233
Totals658352.030.000.000.0

CountyHARRIS
HighwayIH 10
FromGARTH ROAD
ToCHAMBERS C/L
CSJ0508-01-356
Proj IDNH 2018(760)
Work TypeINSTALL ITS EQUIPMENT & INFRASTRCTR
 
8.0304844982.305588185.7599.9
Work Order08-02-18
Work Began09-01-18
Work Completed
Time Computed09-01-18
Contract Working Days450
Addl Days Granted0
Working Days Charged445
Percent Time Used98
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-356
SPECIALTY DRILLING, LLC (1.20)
BTM SERVICES, LLC (1.43)
Contract #04183019
Totals4844982.300.005588185.7599.9

CountyHARRIS
HighwayIH 10
FromAT LOCKWOOD DR
To.
CSJ0508-01-385
Proj IDSTP 2B24(346)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200753027.040.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-24
Work Began00-00-00
Work Completed
Time Computed01-16-25
Contract Working Days195
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-385
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08243031
Totals753027.040.000.000.0

CountyHARRIS
HighwayIH 10
FromIH 610
ToCEDAR BAYOU/CHAMBERS COUNTY LINE
CSJ0508-01-391
Proj IDC 508-1-391
Work TypeOVERLAY
 
21.43018279582.410.000.0
Work Order09-26-24
Work Began00-00-00
Work Completed
Time Computed10-26-24
Contract Working Days137
Addl Days Granted0
Working Days Charged2
Percent Time Used1
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-391
BATTERSON, LLP (11.91)
MC2 CIVIL, LLC (15.30)
LONESTAR TRAFFIC SAFETY, LLC (0.14)
KINGZ INDUSTRIAL LLC (1.46)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (1.29)
Contract #08243208
Totals18279582.410.000.000.0

CountyHARRIS ETC
HighwayIH 10 ETC
FromIH 45
ToCHAMBERS COUNTY LINE
CSJ0508-01-394
Proj IDC 508-1-394
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
92.7732043682.411344299.7065.7
Work Order03-21-24
Work Began04-22-24
Work Completed
Time Computed04-20-24
Contract Working Days120
Addl Days Granted0
Working Days Charged96
Percent Time Used80
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-394
BLUE SKY RIGHT OF WAY, LLC (11.74)
Contract #02243028
Totals2043682.41198938.521344299.7065.7

CountyWALLER
HighwayFM 362
FromBU 290H
To0.25 MI SOUTH OF DAVIS ROAD
CSJ0523-02-051
Proj IDC 523-2-51
Work TypeOVERLAY
 
8.0964087471.733942833.4796.4
Work Order02-02-24
Work Began03-04-24
Work Completed
Time Computed03-03-24
Contract Working Days76
Addl Days Granted0
Working Days Charged76
Percent Time Used100
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0523-02-051
TRAFFIC SIGNS & LINES, LLC (8.11)
PROFESSIONAL TRAFFIC CONTROL LLC (0.33)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (2.85)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.40)
BATTERSON, LLP (3.98)
INTERSTATE BARRICADES & MARKINGS, INC. (0.37)
Contract #01243246
Totals4087471.730.003942833.4796.4

CountyMONTGOMERY
HighwayFM 1488
FromWALLER COUNTY LINE
ToFM 1774 IN MAGNOLIA
CSJ0523-08-007
Proj IDC 523-8-7
Work TypeWIDEN NON-FREEWAY
 
3.78829031633.3432748484.9499.9
CountyMONTGOMERY
HighwayFM 1488
FromWALLER COUNTY LINE
ToFM 1774 IN MAGNOLIA
CSJ0523-08-010
Proj IDROW 523-8-10
Work TypeRIGHT OF WAY
 
3.788755774.55654466.0086.5
Work Order09-03-20
Work Began11-23-20
Work Completed
Time Computed12-02-20
Contract Working Days555
Addl Days Granted0
Working Days Charged493
Percent Time Used88
Contractor(s)
LINDSEY CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0523-08-007
A1 EROSION CONTROL (2.33)
CITYLYNX, INC. (1.47)
CPAVE, INC. (0.30)
HIGHWAY 1 LLC (1.22)
STORM WATER SOLUTIONS, LP (0.68)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.60)
CURB PLANET INC. (0.00)
TROY ATKINSON (0.26)
JMHP, INC. (0.49)
VULCAN CONSTRUCTION MATERIALS, LP (6.79)
MESA ROD BUSTERS, INC. (1.26)
VULCAN CONSTRUCTION (6.79)
G & D DIRECCIONAL (0.24)
LARRY YOUNG PAVING, INC. (51.70)
DORAN STEEL, INC. (1.75)
AG & OIL 365 ENERGY LLC (0.07)
MEMCO (0.50)
WILLOW CITY SIGN & RAIL, INC. (0.22)
SARVICUS LLC (1.37)
Contract #07203005
Totals29787407.89485890.2033402950.9499.9

CountyMONTGOMERY
HighwayFM 1488
FromFM 1774 IN MAGNOLIA
ToWEST OF FM 149
CSJ0523-09-009
Proj IDC 523-9-9
Work TypeWIDEN NON-FREEWAY
 
4.03045997097.6424978386.8854.3
CountyMONTGOMERY
HighwayFM 1488
FromFM 1774 IN MAGNOLIA
ToWEST OF FM 149
CSJ0523-09-017
Proj IDROW 523-9-17
Work TypeRIGHT OF WAY
 
4.0302288466.321256343.7154.8
Work Order03-16-22
Work Began06-14-22
Work Completed
Time Computed06-30-22
Contract Working Days622
Addl Days Granted0
Working Days Charged522
Percent Time Used83
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0523-09-009
HIGHWAY 1 LLC (1.30)
DUSTROL, INC. (0.49)
HB FARMER FOUNDATION, LLC (1.71)
THIRD COAST SERVICES LLC (2.00)
WILLOW CITY SIGN & RAIL, INC. (0.44)
MESA ROD BUSTERS, INC. (0.81)
BUYERS BARRICADES, INC. (0.00)
CEN TEX HYDROSEED, INC. (1.69)
ISJ UNDERGROUND UTILITIES LLC (1.98)
CHERRY DEMOLITION (0.17)
PRIMATE CONSTRUCTION, LP (0.20)
BUYERS BARRICADES HOUSTON, LLC (0.09)
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC (5.27)
CPAVE, INC. (0.08)
CONSOLIDATED CRANE & RIGGING (0.10)
MICKIE SERVICE, INC. (0.29)
CURB PLANET INC. (0.20)
Contract #08213204
Totals48285563.961042870.0426234730.5954.3

CountyMONTGOMERY
HighwayFM 1488
FromIH 45
ToMOSTYN DRIVE
CSJ0523-10-047
Proj IDSTP 2022(307)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
12.43510225881.206832948.6666.8
Work Order05-10-22
Work Began07-06-23
Work Completed
Time Computed07-11-22
Contract Working Days426
Addl Days Granted125
Working Days Charged517
Percent Time Used93
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0523-10-047
TRAFFIC SIGNS & LINES, LLC (1.19)
THIRD COAST SERVICES LLC (7.48)
CURB PLANET INC. (1.15)
PIPE WHOLESALERS OF TEXAS, INC. (1.07)
GEORGE MEEKS LANDPRO, INC. (1.55)
A&J REBAR LLC (0.09)
ROSALES TRUCKING (5.13)
SK CONCRETE SERVICES LLC (0.54)
HIGHWAY 1 LLC (8.24)
Contract #04223205
Totals10225881.20353106.846832948.6666.8

CountyFORT BEND
HighwayFM 1875
FromUA 90
ToSL 540
CSJ0527-05-012
Proj IDC 527-5-12
Work TypeOVERLAY
 
4.5941497972.352288924.3999.9
Work Order05-03-24
Work Began06-17-24
Work Completed
Time Computed06-17-24
Contract Working Days45
Addl Days Granted0
Working Days Charged45
Percent Time Used100
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0527-05-012
TRAFFIC SIGNS & LINES, LLC (4.65)
PROFESSIONAL TRAFFIC CONTROL LLC (0.59)
INTERSTATE BARRICADES & MARKINGS, INC. (0.72)
BATTERSON, LLP (4.49)
Contract #03243219
Totals1497972.35372.002288924.3999.9

CountyBRAZORIA
HighwayFM 1495
FromE BROAD ST
ToSH 36
CSJ0587-01-064
Proj IDC 587-1-64
Work TypeREHABILITATION OF EXISTING ROAD
 
0.7797143864.174009511.1056.1
Work Order06-22-22
Work Began02-06-23
Work Completed
Time Computed08-22-22
Contract Working Days375
Addl Days Granted194
Working Days Charged434
Percent Time Used76
Contractor(s)
TRIPLE B SERVICES LLP
SUBCONTRACTOR(S) FOR CCSJ: 0587-01-064
HIGHWAY 1 LLC (2.77)
SORRELL CONSTRUCTION, EQUIPMENT & MATERIALS, LLC (1.97)
STRIPES & STOPS COMPANY, INC. (1.59)
AIMS COMPANIES (0.44)
SAW & SEAL OF TEXAS LLC (1.99)
TEXAS ENVIRONMENTAL CONTROL, INC. (0.23)
DOUBLE OAK EROSION, INC. (0.49)
QUALITY TURF FARMS, L.C. (1.38)
TRAF-TEX, INC. (0.08)
DUSTROL, INC. (1.15)
MEMCO STAFFING, LLC (2.09)
HERMANOS STEEL, LLC (0.96)
C. M. NUNEZ TRUCKING, INC. (0.00)
HASS HORIZONTAL, LLC (0.00)
GMJ PAVING COMPANY LLC (3.61)
C.M. NUNEZ TRUCKING COMPANY (0.88)
HASS CO, LLC (0.36)
INLAND ENVIRONMENTS, LTD. (0.23)
SMYRNA READY MIX CONCRETE, LLC (1.59)
MASTER CURB, LLC (0.10)
CONARMET LLC (1.88)
M AND J CONSTRUCTION SAWING (0.04)
HODGES BROTHERS, INC. (0.11)
TRAFFIC SIGNS & LINES, LLC (0.22)
Contract #05223005
Totals7143864.17120558.204009511.1056.1

CountyHARRIS
HighwaySH 288
FromIH 69
ToIH 610 SOUTH
CSJ0598-01-104
Proj IDC 598-1-104
Work TypeTRAFFIC CONTROL DEVICES
 
3.821509263.6752817.9510.3
Work Order02-27-23
Work Began08-25-24
Work Completed
Time Computed03-29-23
Contract Working Days62
Addl Days Granted0
Working Days Charged11
Percent Time Used17
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 0598-01-104
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01233028
Totals509263.670.0052817.9510.3

CountyHARRIS
HighwaySH 288
FromNORTH MACGREGOR WAY
ToIH 69
CSJ0598-01-105
Proj IDC 598-1-105
Work TypeCULVERT & STORM DRAINAGE WORK
 
32300513.8013156744.2340.7
CountyHARRIS
HighwaySH 288
FromNORTH MACGREGOR WAY
ToIH 69
CSJ0598-01-107
Proj IDROW 0598-01-107
Work TypeRIGHT OF WAY
 
1494704.00124620.008.3
Work Order07-26-23
Work Began01-17-24
Work Completed
Time Computed10-24-23
Contract Working Days735
Addl Days Granted1
Working Days Charged180
Percent Time Used24
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0598-01-105
LONESTAR TRAFFIC SAFETY, LLC (0.13)
QUALITY TURF FARMS, L.C. (0.49)
HIGHWAY 1 LLC (0.38)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC (1.76)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (7.87)
CHERRY MOVING COMPANY, INC. (0.25)
HUNTER WELLPOINT, INC. (2.68)
CASTEC CONSTRUCTION LLC (1.11)
SK CONCRETE SERVICES LLC (0.12)
DOUBLE OAK EROSION, INC. (0.06)
MESA ROD BUSTERS, INC. (0.19)
MICKIE SERVICE, INC. (0.06)
DIXIE FOUNDATION DRILLING CO. (0.00)
ROYAL TRAFFIC SIGN CO. (0.04)
C. & C.S., INC. (0.23)
CAPSTONE DEVELOPMENT GROUP LLC (0.95)
Contract #06233403
Totals33795217.801688184.9913281364.2339.2

CountyHARRIS
HighwaySH 288
FromSIMS BAYOU
ToAIRPORT BLVD
CSJ0598-01-108
Proj IDCC 598-1-108
Work TypeNEW LOCATION FREEWAY
 
3336063.594739494.3299.9
Work Order06-28-23
Work Began08-16-23
Work Completed
Time Computed07-28-23
Contract Working Days165
Addl Days Granted0
Working Days Charged156
Percent Time Used94
Contractor(s)
R CONSTRUCTION CIVIL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0598-01-108
HIGHWAY 1 LLC (1.31)
TRAF-TEX, INC. (7.52)
CURB PLANET INC. (0.05)
QUALITY TURF FARMS, L.C. (4.84)
GMJ PAVING COMPANY LLC (2.88)
A&J REBAR LLC (0.67)
SEAMARCK LANDSCAPE SERVICES, INC (0.75)
SPECIALTY DRILLING, LLC (0.35)
TERRACON CONSULTANTS, INC. (0.06)
A-1 CONSTRUCTION SERVICES (0.69)
WILLOW CITY SIGN & RAIL, INC. (1.65)
Contract #05233029
Totals3336063.590.004739494.3299.9

CountyBRAZORIA
HighwaySH 288
FromNORTH OF SH 6
ToRODEO PALMS PKWY
CSJ0598-02-111
Proj IDSTP 2022(575)MM
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
1.51350829745.5541373813.0181.3
Work Order09-15-22
Work Began10-31-22
Work Completed
Time Computed10-15-22
Contract Working Days702
Addl Days Granted0
Working Days Charged578
Percent Time Used82
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-111
HB FARMER FOUNDATION, LLC (2.82)
MILSTEAD HIGHWAY SERVICES, LLC (0.57)
INTERSTATE BARRICADES & MARKINGS, INC. (0.07)
SCOTT DERR PAINTING CO, LLC (0.21)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.17)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.96)
PRIMATE CONSTRUCTION, LP (0.01)
A&J REBAR LLC (3.25)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (2.88)
PROFESSIONAL TRAFFIC CONTROL LLC (0.42)
CHERRY CRUSHED CONCRETE (1.31)
JASSO"S SAWING & SEALING (0.16)
CURB PLANET INC. (0.01)
SOUTHEAST GRINDING AND GROOVING LLC (0.06)
LAWNSCAPES UNLIMITED (0.07)
BLS SERVICES (0.06)
WILLOW CITY SIGN & RAIL, INC. (0.15)
DORAN STEEL, INC. (0.12)
SPECIALTY DRILLING, LLC (0.03)
CHIRON COMMUNICATION SERVICES, LLC (0.09)
YELLOWSTONE LANDSCAPE - CENTRAL, INC. (0.06)
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC (5.64)
ASHTON SAWING AND DRILLING LLC (0.03)
Contract #08223204
Totals50829745.551558219.0341373813.0181.3

CountyBRAZORIA
HighwaySH 288
FromAT CR 48 (IOWA COLONY BLVD)
To.
CSJ0598-02-112
Proj IDC 598-2-112
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
0.05038504600.1536250551.0494.1
Work Order08-02-22
Work Began11-08-22
Work Completed
Time Computed09-01-22
Contract Working Days409
Addl Days Granted0
Working Days Charged395
Percent Time Used96
Contractor(s)
GRANITE CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-112
HB FARMER FOUNDATION, LLC (2.16)
REPUBLIC TRAFFIC SAFETY, INC. (0.41)
QUALITY TURF FARMS, L.C. (1.88)
C.G. ANTHONY DELIVERIES, LLC (0.37)
DUSTROL, INC. (3.84)
PROFESSIONAL TRAFFIC CONTROL LLC (0.30)
A&J REBAR LLC (0.11)
MILSTEAD HIGHWAY SERVICES, LLC (0.55)
ANTIGO CONSTRUCTION, INC. (0.10)
A&J REBAR LLC (0.58)
CREACOM, INC. (1.22)
JAMES CONSTRUCTION GROUP, LLC (5.53)
JRB ENGINEERING, LLC (0.15)
SB FLEET - LUBE, LLC (0.22)
PRIMATE CONSTRUCTION, LP (0.20)
ROMAR UNLIMITED, INC. (0.82)
CURB PLANET INC. (0.02)
FORDE CONSTRUCTION COMPANY, INC. (0.27)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (0.32)
DORAN STEEL, INC. (0.13)
AARON CONCRETE CONTRACTORS, LLC (1.09)
ROADWAY SPECIALTIES, INC. (0.30)
YELLOWSTONE LANDSCAPE - CENTRAL, INC. (0.04)
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC (5.53)
WILLOW CITY SIGN & RAIL, INC. (0.10)
ROYAL REBAR (0.12)
CLEAN-CO SYSTEMS, INC. (0.04)
Contract #06223404
Totals38504600.152681173.3736250551.0494.1

CountyBRAZORIA
HighwaySH 288
FromAT CR 57 (CEDAR RAPIDS PARKWAY)
To.
CSJ0598-02-113
Proj IDC 598-2-113
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
1.08521548238.4816290605.2275.6
CountyBRAZORIA
HighwaySH 288
FromAT CR 64 (DAVENPORT PARKWAY)
To.
CSJ0598-02-114
Proj IDC 598-2-114
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
0.98721418853.4915870433.6374.0
CountyBRAZORIA
HighwaySH 288
FromAT CR 56 (MERIDIANA PARKWAY)
To.
CSJ0598-02-125
Proj IDF 2022(574)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
1.02014519659.3313549246.3293.3
Work Order09-15-22
Work Began11-14-22
Work Completed
Time Computed11-14-22
Contract Working Days796
Addl Days Granted27
Working Days Charged569
Percent Time Used69
Contractor(s)
GRANITE CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-113
HB FARMER FOUNDATION, LLC (4.39)
QUALITY TURF FARMS, L.C. (2.89)
REPUBLIC TRAFFIC SAFETY, INC. (0.56)
C.G. ANTHONY DELIVERIES, LLC (0.95)
PROFESSIONAL TRAFFIC CONTROL LLC (0.72)
A&J REBAR LLC (0.21)
MILSTEAD HIGHWAY SERVICES, LLC (0.74)
A BROTHERS MILLING, LLC (0.42)
A&J REBAR LLC (0.82)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (2.74)
BLS SERVICES (0.14)
KLP COMMERCIAL, L.L.C. (3.92)
JAMES CONSTRUCTION GROUP, LLC (3.32)
JRB ENGINEERING, LLC (0.10)
SB FLEET - LUBE, LLC (0.00)
PRIMATE CONSTRUCTION, LP (0.19)
ROMAR UNLIMITED, INC. (0.53)
CURB PLANET INC. (0.02)
SB FLEET - LUBE, LLC (0.21)
AARON CONCRETE CONTRACTORS, LLC (0.43)
USW-MENARD, INC. (0.15)
ROADWAY SPECIALTIES, INC. (0.32)
YELLOWSTONE LANDSCAPE - CENTRAL, INC. (0.09)
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC (1.44)
WILLOW CITY SIGN & RAIL, INC. (0.14)
Contract #08223004
Totals57486751.301083356.7445710285.1779.5

CountyBRAZORIA
HighwaySH 288
FromAT CR 63 (DUBUQUE PARKWAY)
To.
CSJ0598-02-115
Proj IDC 598-2-115
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
1.38222518415.3919679044.1787.3
CountyBRAZORIA
HighwaySH 288
FromAT CR 60
To.
CSJ0598-02-116
Proj IDF 2022(929)
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
1.60526850064.0219233694.4171.6
Work Order09-15-22
Work Began11-14-22
Work Completed
Time Computed11-14-22
Contract Working Days629
Addl Days Granted0
Working Days Charged571
Percent Time Used90
Contractor(s)
GRANITE CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-115
HB FARMER FOUNDATION, LLC (2.94)
QUALITY TURF FARMS, L.C. (2.38)
REPUBLIC TRAFFIC SAFETY, INC. (0.39)
C.G. ANTHONY DELIVERIES, LLC (1.73)
PROFESSIONAL TRAFFIC CONTROL LLC (0.91)
A&J REBAR LLC (0.12)
MILSTEAD HIGHWAY SERVICES, LLC (0.99)
ANTIGO CONSTRUCTION, INC. (0.05)
A BROTHERS MILLING, LLC (0.59)
A&J REBAR LLC (0.69)
CREACOM, INC. (0.43)
BLS SERVICES (0.27)
KLP COMMERCIAL, L.L.C. (0.82)
JAMES CONSTRUCTION GROUP, LLC (6.89)
JRB ENGINEERING, LLC (0.11)
SB FLEET - LUBE, LLC (0.00)
PRIMATE CONSTRUCTION, LP (0.22)
ROMAR UNLIMITED, INC. (0.77)
FORDE CONSTRUCTION COMPANY, INC. (0.29)
SB FLEET - LUBE, LLC (0.32)
AARON CONCRETE CONTRACTORS, LLC (0.63)
YELLOWSTONE LANDSCAPE - CENTRAL, INC. (0.09)
ROADWAY SPECIALTIES, INC. (0.26)
ROYAL REBAR (0.05)
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC (0.68)
WILLOW CITY SIGN & RAIL, INC. (0.23)
GMJ PAVING COMPANY LLC (1.57)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (0.64)
Contract #08223205
Totals49368479.41820706.6538912738.5878.8