Monthly State Let Construction Report For Houston District As Of Nov 10, 2024 Page 6 Of 15

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13 | page 14 | page 15

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGALVESTON
HighwaySH 87
FromAT GALVESTON FERRY
To.
CSJ0367-06-066
Proj IDF 2022(350)
Work TypeFERRY BOAT
 
10981668.0010958228.7699.7
Work Order09-20-22
Work Began11-28-22
Work Completed
Time Computed10-20-22
Contract Working Days225
Addl Days Granted132
Working Days Charged357
Percent Time Used100
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0367-06-066
STRIPE LINES, INC. (0.70)
MITCHELL CHUOKE PLUMBING, INC. (3.55)
BROOME WELDING & MACHINE CO. (2.87)
PFEIFFER & SON LTD. (6.55)
CONSTRUCTION ECO SERVICES (0.10)
HOLES INCORPORATED (0.04)
4-S MANUFACTURING TEXAS LIMITED LIABILITY COMPANY (19.55)
SCHINDLER ELEVATOR CORPORATION (0.91)
R A GROUP, LLC (1.48)
CHERRY DEMOLITION (0.22)
GRADY"S LABOR SERVICE, INC. (0.09)
MESA MECHANICAL (0.66)
DORAN STEEL, INC. (0.13)
NATIONAL SECURITY & FIRE LLC (0.77)
CHAMBERLIN HOUSTON, LLC (0.56)
GULF SHORE ERECTORS, LLC (3.34)
HAYDEN PAVING, INC. (0.92)
MCVEY PAINT AND WALLCOVERING, INC. (7.33)
Contract #08223056
Totals10981668.0025644.2510958228.7699.7

CountyGALVESTON
HighwaySL 108
FromSL 108 AT HORSESHOE LAKE
To.
CSJ0367-07-009
Proj IDBR 2023(926)
Work TypeBRIDGE REPLACEMENT
 
0.1362472329.001910025.5977.2
Work Order10-12-23
Work Began02-07-24
Work Completed
Time Computed11-11-23
Contract Working Days116
Addl Days Granted0
Working Days Charged114
Percent Time Used98
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0367-07-009
TRAFFIC SIGNS & LINES, LLC (2.36)
MESA ROD BUSTERS, INC. (0.34)
Contract #09233225
Totals2472329.0072225.121910025.5977.2

CountyHARRIS
HighwaySH 146
FromCHAMBERS C/L
ToBS 146-E
CSJ0389-03-039
Proj IDC 389-3-39
Work TypeTRAFFIC CONTROL DEVICES
 
0.98280639.840.000.0
CountyHARRIS
HighwaySH 146
FromBS 146-E
ToSS 330
CSJ0389-13-065
Proj IDF 2025(145)
Work TypeTRAFFIC CONTROL DEVICES
 
3.681213772.580.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 0389-03-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10243224
Totals294412.420.000.000.0

CountyHARRIS
HighwaySH 146
FromN OF FAIRMONT PARKWAY
ToS OF RED BLUFF
CSJ0389-05-087
Proj IDC 389-5-87
Work TypeWIDEN FREEWAY
 
11.521110766237.7344806842.0540.4
Work Order09-13-21
Work Began09-20-21
Work Completed
Time Computed09-30-21
Contract Working Days1,229
Addl Days Granted188
Working Days Charged521
Percent Time Used36
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0389-05-087
SCOTT DERR PAINTING CO, LLC (0.04)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.20)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (5.91)
PROFESSIONAL TRAFFIC CONTROL LLC (0.68)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (1.48)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P. (0.10)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.37)
MESA ROD BUSTERS, INC. (6.38)
BASE CONSTRUCTION L.L.P. (11.29)
SK CONCRETE SERVICES LLC (0.53)
BATTEN DRILLING, INC. (0.32)
TCH DIRECTIONAL DRILLING (0.02)
Contract #08213201
Totals110766237.73840756.1644806842.0540.4

CountyHARRIS
HighwaySH 146
FromNASA 1
ToHARRIS/GALVESTON COUNTY LINE
CSJ0389-05-116
Proj IDNH 2018(852)
Work TypeGR, STRS & SURFACE
 
3.883201835272.66225802540.6699.9
Work Order08-17-18
Work Began02-13-19
Work Completed
Time Computed02-13-19
Contract Working Days1,549
Addl Days Granted258
Working Days Charged1,508
Percent Time Used83
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0389-05-116
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.30)
SCOTT DERR PAINTING CO, LLC (0.20)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.05)
GMJ PAVING CO. (0.82)
HOUSTON SAWING & DRILLING (0.06)
SPEEDY PAVING (0.26)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.16)
ROYAL REBAR (3.15)
BOH BROS. CONSTRUCTION CO., L.L.C. (0.96)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (4.33)
RDI FOUNDATION DRILLING (7.08)
FRANCO BUILDERS, INC. (1.02)
SCI MARINE ENTERPRISES, LLC (1.53)
JOSLIN CONSTRUCTION TEXAS, LLC (1.55)
MAGNOLIA SERVICES INCORPORATED (0.15)
SOUTHERN CRUSHED CONCRETE LLC (0.31)
STRUCTURAL TECHNOLOGIES, LLC (0.27)
LEGACY OFFSHORE, LLC (0.03)
RODNEY GREEN DBA GREEN INTERNATIONAL (0.02)
MTAM CORPORATION (0.05)
GOULD INDUSTRIES LLC (0.69)
ENVIRONMENTAL ALLIES, L.P. (0.05)
PENHALL COMPANY (0.03)
AGGREGATE TECHNOLOGIES, INC. (0.04)
CONSOR ENGINEERS, LLC (0.01)
PROFESSIONAL SERVICE INDUSTRIES, INC. (0.00)
INDUS ROAD & BRIDGE, INC (2.34)
E & R WELDING (0.05)
A. H. BECK FOUNDATION CO., INC. (1.47)
PROFESSIONAL TRAFFIC CONTROL LLC (0.00)
RUSSELL MARINE, LLC (0.10)
TOTAL HIGHWAY MAINTENANCE, LLC (0.16)
MARTIN MARIETTA MATERIALS, INC. (0.31)
CURB PLANET INC. (0.01)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.39)
ASHTON SAWING AND DRILLING LLC (0.03)
SK CONCRETE SERVICES LLC (0.02)
SPECIALTY DRILLING, LLC (0.02)
EPOXY DESIGN SYSTEMS, INC. (0.02)
BADGER DAYLIGHTING CORP. (0.24)
MPIRE INDUSTRIES COMMERCIAL DIVING SERVICES LLC (0.00)
AVILES CONSTRUCTION SERVICE, INC (0.08)
CHIRON COMMUNICATION SERVICES, LLC (0.03)
J & D TEX SERV, INCORPORATED (0.13)
DELENA CONSTRUCTION SERVICES LLC (0.07)
Contract #05183201
Totals201835272.66574495.34225802540.6699.9

CountyHARRIS
HighwaySH 146
FromRED BLUFF ROAD
ToGALVESTON COUNTY LINE
CSJ0389-05-133
Proj IDC 389-5-133
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
4.4561457505.10775433.8353.2
Work Order04-18-24
Work Began08-01-24
Work Completed
Time Computed05-18-24
Contract Working Days90
Addl Days Granted0
Working Days Charged39
Percent Time Used43
Contractor(s)
GREEN SAGE SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0389-05-133
TRAFFIC SIGNS & LINES, LLC (1.98)
R & A DIRECTIONAL BORING (1.02)
Contract #03243029
Totals1457505.1085468.81775433.8353.2

CountyGALVESTON
HighwaySH 146
FromFM 518
ToDICKINSON BAYOU
CSJ0389-06-088
Proj IDC 389-6-88
Work TypeWIDEN FREEWAY
 
5.574196438454.8825793767.9513.1
CountyGALVESTON
HighwaySH 146
FromFM 518
ToDICKINSON BAYOU
CSJ0389-06-092
Proj IDROW 389-6-92
Work TypeRIGHT OF WAY
 
5.5741416946.910.000.0
Work Order06-07-23
Work Began02-01-24
Work Completed
Time Computed10-05-23
Contract Working Days1,098
Addl Days Granted0
Working Days Charged123
Percent Time Used11
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0389-06-088
HIGHWAY 1 LLC (0.06)
CURB PLANET INC. (0.01)
SCOTT DERR PAINTING CO, LLC (0.04)
CHERRY MOVING COMPANY, INC. (0.04)
QUALITY TURF FARMS, L.C. (2.03)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (3.84)
MTAM CORPORATION (0.01)
VERA INDUSTRIES, LLC (0.29)
PROFESSIONAL TRAFFIC CONTROL LLC (0.48)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.69)
R & B GROUP, INC. (1.16)
A BROTHERS MILLING, LLC (0.80)
B&D MAINTENANCE (0.04)
C.G. ANTHONY DELIVERIES, LLC (0.04)
HERMANOS STEEL, LLC (0.43)
AVILES CONSTRUCTION SERVICE, INC (0.11)
HB FARMER FOUNDATION, LLC (4.03)
B & D MAINTENANCE LLC (0.04)
SK CONCRETE SERVICES LLC (0.11)
PRIMATE CONSTRUCTION, LP (0.00)
TETRA TECH CONSTRUCTION SERVICES, INC. (0.03)
SPEEDY PAVING (0.10)
IKON ENVIRONMENTAL SOLUTIONS, LP (0.02)
BADGER DAYLIGHTING CORP. (0.00)
J.KRU LAND SERVICES, LLC (0.03)
PROSCAPE DEVELOPMENT LLC (0.00)
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC (8.67)
Contract #05233201
Totals197855401.796556309.1525793767.9513.0

CountyGALVESTON
HighwaySH 146
FromFM 519
ToN OF SL 197
CSJ0389-07-025
Proj IDBR 2022(576)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
1.83585237068.9519678273.3823.0
CountyGALVESTON
HighwaySH 146
FromFM 519
ToN OF SL 197
CSJ0389-07-036
Proj IDROW 389-7-36
Work TypeRIGHT OF WAY
 
1.835352462.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-05-23
Work Began05-18-23
Work Completed
Time Computed00-00-00
Contract Working Days810
Addl Days Granted594
Working Days Charged17
Percent Time Used1
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0389-07-025
ROYAL REBAR (6.51)
WILLOW CITY SIGN & RAIL, INC. (0.32)
BASE CONSTRUCTION L.L.P. (5.47)
AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC (0.08)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.82)
SCOTT DERR PAINTING CO, LLC (0.33)
RDI FOUNDATION DRILLING (6.35)
SK CONCRETE SERVICES LLC (0.12)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.77)
TERRA CONSTRUCTION LLC (0.84)
LONG LEGACY ENTERPRISES, LLC (0.00)
REPUBLIC TRAFFIC SAFETY, INC. (1.07)
KELLER NORTH AMERICA, INC. (1.40)
Contract #04233002
Totals85589530.951053165.0019678273.3822.9

CountyHARRIS
HighwaySH 146
FromFERRY RD
ToBS 146E
CSJ0389-13-039
Proj IDC 389-13-39
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
24851806.2524040107.4296.7
Work Order08-02-22
Work Began09-06-22
Work Completed
Time Computed09-01-22
Contract Working Days469
Addl Days Granted0
Working Days Charged467
Percent Time Used99
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0389-13-039
HIGHWAY 1 LLC (0.47)
MESA ROD BUSTERS, INC. (0.79)
GMJ PAVING CO. (1.42)
SCOTT DERR PAINTING CO, LLC (0.20)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.40)
RDI FOUNDATION DRILLING (4.06)
FLORIDA TRAFFIC CONTROL DEVICES, INC. (1.91)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.19)
VALLEY PLACERS, LLC (0.24)
HOUSTON SAWING & DRILLING (0.05)
JASSO"S SAWING & SEALING (0.16)
TOM-MAC, INC. (0.21)
BELLA PAVING, INC. (0.14)
AARON CONCRETE CONTRACTORS, LLC (0.81)
WEST TEXAS ROCK RESOURCES, LLC (0.11)
Contract #06223406
Totals24851806.252605.0024040107.4296.7

CountyWALLER
HighwaySH 159
FromBRAZOS RIVER
ToBU 290H
CSJ0409-02-030
Proj IDF 2024(949)
Work TypeOVERLAY
 
4.3172461983.970.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days54
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0409-02-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243221
Totals2461983.970.000.000.0

CountyGALVESTON
HighwayIH 45
FromS OF TEXAS CITY WYE
ToN OF CAUSEWAY
CSJ0500-01-107
Proj IDNH 2B20(048)
Work TypeWIDEN FREEWAY
 
1.57489225679.0852064252.2558.3
CountyGALVESTON
HighwayIH 45
FromIH 45 NB AT BNSF RR
To.
CSJ0500-01-144
Proj IDBR 2B20(049)
Work TypeBRIDGE REPLACEMENT
 
0.46814025777.601991588.2714.1
Work Order09-01-20
Work Began10-21-20
Work Completed
Time Computed10-21-20
Contract Working Days1,470
Addl Days Granted374
Working Days Charged840
Percent Time Used45
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-01-107
ROYAL REBAR (8.39)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (2.25)
BASE CONSTRUCTION L.L.P. (5.55)
SCOTT DERR PAINTING CO, LLC (0.02)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.12)
QUALITY TURF FARMS, L.C. (0.53)
PAVEMENT MARKINGS INC. (0.57)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.70)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P. (0.04)
PMI PAVEMENT MARKING, LLC (0.57)
BATTERSON, LLP (0.56)
SK CONCRETE SERVICES LLC (0.33)
HIGHWAY 1 LLC (0.00)
Contract #08203202
Totals103251456.68992907.2654055840.5252.3

CountyHARRIS
HighwayIH 45
FromS OF NASA 1 BYPASS
ToGALVESTON COUNTY LINE
CSJ0500-03-107
Proj IDNH 2017(906)
Work TypeGR, STRS, BASE, AND PAVE
 
1.91899164261.39104255262.1399.9
CountyHARRIS
HighwayIH 45
FromS OF BAY AREA BLVD
ToS OF KOBAYASHI DRIVE
CSJ0500-03-578
Proj IDNH 2017(906)
Work TypeRESTRIPING AND SIGNING
 
1.146282079.40216223.4176.6
CountyGALVESTON
HighwayFM 518
FromAT HOBBS ROAD/LAFAYETTE LANE
To.
CSJ0976-03-102
Proj IDSTP 2017(969)HES
Work TypeTS IMPRVMTS
 
0.250337135.90415050.7699.9
Work Order05-02-17
Work Began05-15-17
Work Completed
Time Computed05-15-17
Contract Working Days1,427
Addl Days Granted336
Working Days Charged1,763
Percent Time Used100
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-107
VACA UNDERGROUND UTILITIES INC (1.41)
ESSARY, HART & MACWILIAM,INC. (5.39)
ROADWAY CONSTRUCTION, LLC (0.77)
GEORGE MEEKS LANDPRO, INC. (0.19)
(INACTIVE)A & A CONSTRUCTION (0.33)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.47)
TRAF-TEX, INC. (4.07)
HAYWARD BAKER, INC. (0.44)
SAFETEX,INC. (0.53)
MP TECHNOLOGIES, LLC (0.13)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.17)
SCOTT DERR PAINTING CO, LLC (0.02)
PROFESSIONAL TRAFFIC CONTROL LLC (0.58)
CEN-TEX IRRIGATION SYSTEMS, INC. (0.19)
MESA ROD BUSTERS, INC. (2.33)
KELLER NORTH AMERICA, INC. (0.44)
SK CONCRETE SERVICES LLC (0.05)
WEST TEXAS ROCK RESOURCES, LLC (0.05)
PINNACLE GRINDING AND GROOVING LLC (0.01)
Contract #04173001
Totals99783476.6937576.00104886536.3099.9

CountyHARRIS
HighwayIH 45
FromBEATTY ST
ToCULLEN BLVD
CSJ0500-03-625
Proj IDC 500-3-625
Work TypeTRAFFIC CONTROL DEVICES
 
2822019.393297214.0099.9
Work Order03-18-21
Work Began04-14-22
Work Completed
Time Computed07-16-21
Contract Working Days176
Addl Days Granted0
Working Days Charged149
Percent Time Used84
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-625
RANSOM DRILLING SERVICES, LLC (10.87)
DOUBLE S CONSTRUCTION (2.97)
BARRICADES UNLIMITED (1.01)
Contract #12203010
Totals2822019.390.003297214.0099.9

CountyHARRIS
HighwayIH 45
FromSL 8 SOUTH
ToALMEDA GENOA RD
CSJ0500-03-635
Proj IDC 500-3-635
Work TypeOVERLAY
 
1.2004137770.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-06-24
Work Began00-00-00
Work Completed
Time Computed11-05-24
Contract Working Days118
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-635
INTERSTATE BARRICADES & MARKINGS, INC. (0.44)
Contract #08243007
Totals4137770.750.000.000.0

CountyHARRIS
Highway0000000
FromAT CULLEN BLVD
To.
CSJ0500-03-644
Proj IDC 500-3-644
Work TypeCULVERT & STORM DRAINAGE WORK
 
20354967.270.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days549
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MC2 CIVIL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-644
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11243008
Totals20354967.270.000.000.0

CountyHARRIS
HighwayIH 45 ETC
FromIH 10
ToGALVESTON COUNTY LINE
CSJ0500-03-650
Proj IDC 500-3-650
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
72.1835862272.202607538.5344.4
Work Order06-19-23
Work Began07-31-23
Work Completed
Time Computed07-19-23
Contract Working Days180
Addl Days Granted80
Working Days Charged238
Percent Time Used91
Contractor(s)
TEXAS WALL & LANDSCAPE
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-650
HARPER BROTHERS CONSTRUCTION LLC (0.51)
CANALES TRUCKING INC. (0.35)
Contract #05233216
Totals5862272.20574642.202607538.5344.4

CountyGALVESTON
HighwayIH 45
From0.452 MI S. OF FM 518
ToN OF FM 517
CSJ0500-04-096
Proj IDC 500-4-96
Work TypeGR,WIDEN STRS, BASE & PAVEMENT
 
3.394121744991.34125973672.1699.9
Work Order10-28-16
Work Began11-14-16
Work Completed
Time Computed11-27-16
Contract Working Days1,234
Addl Days Granted537
Working Days Charged1,506
Percent Time Used85
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-04-096
A & A CONSTRUCTION (0.23)
BASE CONSTRUCTION (10.83)
ESSARY, HART & MACWILIAM,INC. (0.76)
GEORGE MEEKS LANDPRO, INC. (2.00)
HAYWARD BAKER, INC. (1.18)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.19)
INTERSTATE BARRICADES & MARKINGS, INC. (1.33)
SCOTT DERR PAINTING CO, LLC (0.02)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.74)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (4.44)
BORTUNCO (0.38)
MICKIE SERVICE, INC. (0.02)
CEN-TEX IRRIGATION SYSTEMS (0.16)
MAGNOLIA SERVICES INCORPORATED (0.01)
STEEL EFFECTS (0.00)
MESA ROD BUSTERS, INC. (0.42)
KELLER NORTH AMERICA, INC. (1.18)
SK CONCRETE SERVICES LLC (0.02)
WEST TEXAS ROCK RESOURCES, LLC (0.04)
PINNACLE GRINDING AND GROOVING LLC (0.01)
Contract #10163201
Totals121744991.3460366.62125973672.1699.9

CountyGALVESTON
HighwayIH 45
FromN OF TEXAS CITY WYE
ToS OF TEXAS CITY WYE
CSJ0500-04-103
Proj IDC 500-4-103
Work TypeWIDEN FREEWAY
 
5.291220597228.3797311402.2144.1
CountyGALVESTON
HighwayIH 45
FromN OF TEXAS CITY WYE
ToS OF TEXAS CITY WYE
CSJ0500-04-138
Proj IDROW 500-4-138
Work TypeRIGHT OF WAY
 
2.0081598637.601625373.6099.9
CountyGALVESTON
HighwayIH 45
FromN OF FM 519
ToN OF TEXAS CITY WYE
CSJ0500-04-139
Proj IDROW 500-4-139
Work TypeRIGHT OF WAY
 
3.2833649948.454058064.4999.9
Work Order09-01-20
Work Began09-17-20
Work Completed
Time Computed09-17-20
Contract Working Days1,667
Addl Days Granted0
Working Days Charged789
Percent Time Used47
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-04-103
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.78)
INTERSTATE BARRICADES & MARKINGS, INC. (0.60)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (4.18)
SCOTT DERR PAINTING CO, LLC (0.02)
(INACTIVE)A & A CONSTRUCTION (0.00)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.17)
BASE CONSTRUCTION L.L.P. (14.48)
MESA ROD BUSTERS, INC. (3.52)
QUALITY TURF FARMS, L.C. (0.78)
MR. DIRT (0.01)
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (0.30)
A & A CONSTRUCTION COMPANY (0.21)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (1.19)
SK CONCRETE SERVICES LLC (0.38)
TEXAS CURB CUT (0.00)
ROADWAY CONSTRUCTION, LLC (0.18)
Contract #08203001
Totals225845814.422177051.25102994840.3045.6

CountyGALVESTON
HighwayIH 45
FromSOUTH OF FM 1764
ToNORTH OF FM 519
CSJ0500-04-105
Proj IDNH 1902(105)
Work TypeWIDEN FREEWAY
 
3.395162914777.70119695371.9073.1
CountyGALVESTON
HighwayIH 45
FromSOUTH OF FM 1764
ToNORTH OF FM 519
CSJ0500-04-137
Proj IDROW 500-4-137
Work TypeRIGHT OF WAY
 
3.3952910229.303764518.8099.9
Work Order09-16-19
Work Began09-23-19
Work Completed
Time Computed09-23-19
Contract Working Days1,500
Addl Days Granted0
Working Days Charged1,408
Percent Time Used93
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-04-105
A & A CONSTRUCTION (0.28)
A&J REBAR LLC (2.59)
BROOKLYN SWEEPS, INCORPORATED (0.24)
PROFESSIONAL TRAFFIC CONTROL LLC (0.66)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.42)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.14)
SCOTT DERR PAINTING CO, LLC (0.01)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.60)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (4.11)
BASE CONSTRUCTION L.L.P. (14.25)
BORTUNCO (0.78)
RAY"S THREADING AND FAB SHOP (0.52)
ROADWAY CONSTRUCTION, LLC (0.21)
A & A CONSTRUCTION COMPANY (0.28)
SWEEPING CORPORATION OF AMERICA, LLC (0.05)
SK CONCRETE SERVICES LLC (0.25)
HIGHWAY 1 LLC (0.00)
Contract #08193201
Totals165825007.002907691.19123459890.7074.0

CountyGALVESTON
HighwayIH 45
FromN OF FM 517
ToS OF FM 1764
CSJ0500-04-106
Proj IDNH 2018(963)
Work TypeGR, WIDEN STRS, BASE & PAVEMENT
 
5.070228823555.41175960347.1576.8
CountyGALVESTON
HighwayIH 45
FromN OF FM 517
ToS OF FM 1764
CSJ0500-04-136
Proj IDROW 500-4-136
Work TypeROW ACQUISITION
 
0.0011653965.10552772.3233.4
Work Order07-02-18
Work Began07-26-18
Work Completed
Time Computed07-26-18
Contract Working Days1,288
Addl Days Granted580
Working Days Charged1,587
Percent Time Used84
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-04-106
BASE CONSTRUCTION, L.L.P. (10.46)
(INACTIVE)HAYWARD BAKER, INC. (0.32)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.16)
MESA ROD BUSTERS, INC. (8.07)
PROFESSIONAL TRAFFIC CONTROL LLC (0.61)
SCOTT DERR PAINTING CO, LLC (0.03)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.43)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.68)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (4.04)
RAY"S THREADING AND FAB SHOP (0.64)
STEEL EFFECTS (0.11)
CEN-TEX IRRIGATION SYSTEMS, INC. (0.21)
ONLINE DIRECTIONAL BORING, LP (0.02)
BASE CONSTRUCTION L.L.P. (0.82)
BORTUNCO (0.10)
ASHTON SAWING AND DRILLING LLC (0.00)
CPAVE, INC. (0.00)
LONG LEGACY ENTERPRISES, LLC (0.00)
KELLER NORTH AMERICA, INC. (0.00)
SK CONCRETE SERVICES LLC (0.24)
ROADWAY CONSTRUCTION, LLC (0.23)
Contract #06183001
Totals230477520.511197854.75176513119.4776.5