Bowie County  | ||||||
| CCSJ | Highway | Let Status | Letting Date  | 
Contract Cost  | 
Fund Cat  | 
Description | 
|---|---|---|---|---|---|---|
| 0010-12-063 | US 67 | Actual | JUL 2010 | $2,285,063 | 6 | REHABILITATE BRIDGES AND APPROACHES | 
| 0010-13-084 | US 67 | Actual | JAN 2010 | $713,639 | 8 | IMPROVE TRAFFIC SIGNAL | 
| 0046-03-036 | US 82 | Actual | OCT 2009 | $5,236,456 | 1 | SEAL COAT | 
| 0046-06-073 | US 82 | Actual | DEC 2009 | $303,444 | 3 | UPGRADE EXISTING TRAFFIC SIGNALS | 
| 0046-06-074 | US 82 | Actual | FEB 2010 | $625,745 | 11 | RESURFACE EXISTING HIGHWAY | 
| 0061-01-022 | SH 8 | Actual | AUG 2010 | $2,041,219 | 1 | RESURFACE EXISTING 2 - LANE HIGHWAY WITH ASPHALTIC CONCRETE | 
| 0062-01-037 | SH 8 | Actual | MAR 2010 | $1,682,977 | 8 | INSTALL LEFT TURN LANE | 
| 0218-01-070 | SH 93 | Actual | SEP 2009 | $4,668,869 | 3 | CONSTRUCT RAILROAD GRADE SEPARATION STRUCTURE AND APPROACHES | 
| 0330-01-030 | FM 1840 | Actual | JUL 2010 | $1,928,828 | 8 | SAFETY TREAT FIXED OBJECTS | 
| 0610-06-076 | IH 30 | Actual | AUG 2010 | $15,994,500 | 12 | CONSTRUCT INTERCHANGE AT WEST HOOKS COUNTY ROAD & CONSTRUCT | 
| 0919-19-051 | CR | Actual | JUL 2010 | $1,622,732 | 6 | REPLACE BRIDGE AND APPROACHES_ON CR 4319 AT ANDERSON CREEK | 
| 0919-19-060 | CS | Actual | JUL 2010 | $342,513 | 6 | REPLACE BRIDGE AND APPROACHES_ON 4TH STREET AT SWAMPOODLE | 
| 0919-19-061 | CS | Actual | SEP 2009 | $254,303 | 6 | REPLACE BRIDGE AND APPROACHES_ON DAY STREET AT NIX CREEK | 
| 0945-01-036 | SH 93 | Actual | SEP 2009 | $134,751 | 11 | UPGRADE EXISTING TRAFFIC SIGNALS | 
| 0945-01-037 | FM 1397 | Actual | AUG 2010 | $118,433 | 11 | UPGRADE EXISTING TRAFFIC SIGNALS | 
| 1214-01-017 | FM 992 | Actual | DEC 2009 | $3,849,689 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH | 
Camp County  | ||||||
| CCSJ | Highway | Let Status | Letting Date  | 
Contract Cost  | 
Fund Cat  | 
Description | 
| 1019-01-016 | FM 556 | Actual | JUL 2010 | $1,822,516 | 11 | REPLACE BRIDGE AND APPROACHES ON 2 LANE HIGHWAY | 
| 1019-02-030 | FM 557 | Actual | NOV 2009 | $672,758 | 1 | RESTORE SECTION AND RESURFACE 2 LANE HIGHWAY | 
Cass County  | ||||||
| CCSJ | Highway | Let Status | Letting Date  | 
Contract Cost  | 
Fund Cat  | 
Description | 
| 0919-00-064 | VA | Actual | SEP 2009 | $399,252 | 11 | INSTALLATION AND UPGRADE OF TRAFFIC CONTROL DEVICES | 
| 0919-14-020 | VA | Actual | MAR 2010 | $638,196 | 10 | REMOVE BARRIERS TO COMPLY WITH ADA | 
| 0919-14-021 | VA | Actual | JUL 2010 | $212,121 | 8 | SIDEWALKS & CROSSWALKS | 
| 1573-01-016 | FM 130 | Actual | SEP 2009 | $1,331,671 | 8 | WIDEN LANES ON EXISTING ROADWAY | 
| 3195-01-010 | FM 3129 | Actual | FEB 2010 | $3,898,849 | 6 | RAILROAD GRADE SEPARATION | 
Harrison County  | ||||||
| CCSJ | Highway | Let Status | Letting Date  | 
Contract Cost  | 
Fund Cat  | 
Description | 
| 0208-04-012 | FM 2198 | Actual | JUL 2010 | $720,534 | 8 | SAFETY TREAT FIXED OBJECTS | 
| 0495-08-093 | IH 20 | Actual | FEB 2010 | $4,469,235 | 1 | RESURFACE EXISTING INTERSTATE FACILITY | 
| 0843-09-020 | FM 2199 | Actual | FEB 2010 | $1,570,140 | 1 | REHABILITATE PAVEMENT ON EXISTING 2 LANE RURAL HIGHWAY | 
| 2642-02-022 | LP 281 | Actual | FEB 2010 | $4,656,180 | 1 | REHABILITATE PAVEMENT ON EXISTING 4 LANE HIGHWAY | 
Marion County  | ||||||
| CCSJ | Highway | Let Status | Letting Date  | 
Contract Cost  | 
Fund Cat  | 
Description | 
| 0138-12-021 | FM 2208 | Actual | DEC 2009 | $3,593,963 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH | 
| 0632-01-028 | FM 134 | Actual | SEP 2009 | $267,595 | 11 | RESTORE SECTION AND RESURFACE 2 LANE HIGHWAY | 
Morris County  | ||||||
| CCSJ | Highway | Let Status | Letting Date  | 
Contract Cost  | 
Fund Cat  | 
Description | 
| 0919-20-020 | CR | Actual | JUL 2010 | $376,568 | 6 | REPLACE BRIDGES AND APPROACHES_ON CR 2231 AT BIG CYPRESS | 
Panola County  | ||||||
| CCSJ | Highway | Let Status | Letting Date  | 
Contract Cost  | 
Fund Cat  | 
Description | 
| 0063-05-033 | US 59 | Actual | DEC 2009 | $2,090,534 | 1 | RESURFACE EXISTING 4 - LANE HIGHWAY WITH ASPHALTIC CONCRETE | 
Titus County  | ||||||
| CCSJ | Highway | Let Status | Letting Date  | 
Contract Cost  | 
Fund Cat  | 
Description | 
| 0248-09-003 | US 271 | Actual | AUG 2010 | $778,145 | 12 | PREPARING ROW | 
| 0546-01-034 | FM 71 | Actual | DEC 2009 | $2,999,009 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH | 
| 0919-30-051 | CR | Actual | AUG 2010 | $521,575 | 6 | REPLACE BRIDGE AND APPROACHES_ON CR 3120 AT HORSE CREEK | 
| 3404-01-011 | FM 3417 | Actual | JUL 2010 | $789,872 | 6 | REHABILITATE BRIDGE AND APPROACHES | 
Upshur County  | ||||||
| CCSJ | Highway | Let Status | Letting Date  | 
Contract Cost  | 
Fund Cat  | 
Description | 
| 0392-02-080 | US 259 | Actual | SEP 2009 | $928,367 | 11 | REPAIR PAVEMENT ON EXISTING 4 LANE HIGHWAY | 
| 0402-02-027 | SH 154 | Actual | JUL 2010 | $615,915 | 8 | SAFETY TREAT FIXED OBJECTS | 
  | 
|   |