Monthly State Let Construction Report For Austin District As Of Apr 7, 2016 Page 14 Of 14

Last Update: Thursday, April 7, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13 | page 14

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTRAVIS
Highway FM 734
From 0.166 MI. NW OF DESSAU ROAD
To 0.280 MI. SE OF DESSAU ROAD
CSJ 3417-03-017
Proj ID C 3417-3-17
Work Type ADD LEFT AND RIGHT TURN LANES
 
0.446 1481100.48 0.00 1576436.33 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-19-13
Work Began 09-27-13
Work Completed 04-27-15
Time Computed 09-04-13
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 96
Percent Time Used 96
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3417-03-017
ROADWAY SPECIALTIES, INC.(1.67%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. ( 19.58%)
WHEELER COATINGS ASPHALT, INC. ( 34.98%)
FLASHER EQUIPMENT COMPANY( 15.34%)
KRL CONSTRUCTION INC.(1.15%)
Contract # 04133027
Totals 1481100.48 0.00 1576436.33 100.0