Monthly State Let Construction Report For Houston District As Of Dec 10, 2014 Page 3 Of 11

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRIS
Highway IH 610
From W OF W 34TH ST ON US 290 (SEG 3)
To ON IH 610
CSJ 0271-14-213
Proj ID CM 2013(991)
Work Type GR, STRS, BASE AND PAVE
 
0.198 151543734.14 3451283.89 39092787.22 25.7
Work Order 12-11-13
Work Began 12-31-13
Work Completed  
Time Computed 07-07-14
Contract Working Days 1,095
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-213
CPAVE, INC.(0.07%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.37%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.75%)
SCOTT DERR PAINTING CO, LLC(0.21%)
HOUSTON SAWING & DRILLING(0.07%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(0.28%)
ESSARY, HART & MACWILIAM,INC.(9.64%)
BORTUNCO (0.53%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.57%)
RAY"S THREADING AND FAB SHOP (0.39%)
Contract # 11133201
Totals 151543734.14 3451283.89 39092787.22 25.7

CountyHARRIS
Highway IH 610
From TC JESTER TO N OF IH 10 ON IH 610
To AND TO 34TH ST ON US 290
CSJ 0271-14-217
Proj ID STP 2011(998)MM
Work Type GR, STRS, BASE AND PAVE
 
5.604 151578391.02 867218.52 144338482.01 93.0
Work Order 06-15-11
Work Began 06-20-11
Work Completed  
Time Computed 07-11-11
Contract Working Days 1,124
Addl Days Granted 106
Working Days Charged 1,050
Percent Time Used 85
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-217
INTERSTATE BARRICADES & MARKINGS, INC. (0.54%)
FLORIDA TRAFFIC CONTROL DEVICES, INC.(5.43%)
ESSARY, HART & MACWILIAM,INC.( 11.06%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.21%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.19%)
SCOTT DERR PAINTING CO (0.58%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.77%)
BORTUNCO (0.29%)
SPECIALTY DRILLING (0.39%)
AMERICAN TRAFFIC CONTROL, INC. (0.01%)
TREVCON, INC.(0.09%)
BROOKLYN SWEEPS(0.24%)
MAGNOLIA SERVICES INCORPORATED (0.04%)
CHERRY DEMOLITION(0.07%)
Contract # 05113015
Totals 151578391.02 867218.52 144338482.01 93.0

CountyHARRIS
Highway IH 610
From AT IH 45(N) INTERCHANGE
To .
CSJ 0271-14-224
Proj ID IM 6107(438)
Work Type ACP O / L
 
0.520 1766700.70 155957.20 1629436.80 92.2
Work Order 09-16-13
Work Began 08-09-14
Work Completed  
Time Computed 03-01-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 31
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-224
BATTERSON,LLP(4.84%)
MAIN LANE INDUSTRIES, LTD. ( 18.20%)
Contract # 08133230
Totals 1766700.70 155957.20 1629436.80 92.2

CountyHARRIS
Highway IH 610
From W OF W 34TH ST ON US 290 (SEG 3)
To ON IH 610
CSJ 0271-14-225
Proj ID RW 271-14-225
Work Type ROW ACQ., UTL. ADJ.; RELOC ASSIST.
 
2.640 1670105.95 0.00 1594268.79 95.4
CountyHARRIS
Highway IH 610
From W OF W 34TH ST ON US 290 (SEG 3)
To N AND S OF US 290 ON IH 610
CSJ 0271-14-228
Proj ID STP 2013(136)MM
Work Type GR, STRS, BASE AND PAVE
 
1.661 105376730.46 2412491.49 55510621.54 52.6
Work Order 11-09-12
Work Began 11-20-12
Work Completed  
Time Computed 02-04-13
Contract Working Days 1,030
Addl Days Granted 0
Working Days Charged 555
Percent Time Used 53
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-228
BATTERSON,LLP(0.69%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.35%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(0.17%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.16%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.36%)
ESSARY, HART & MACWILIAM,INC.(9.54%)
SCOTT DERR PAINTING CO, LLC(0.23%)
MAGNOLIA SERVICES INCORPORATED (0.17%)
CURB PLANET INC. (0.02%)
EROSION PREVENTION PRODUCTS(0.15%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (4.74%)
W. W. FOUNDATION DRILLING, LTD.(0.21%)
TEJAS UNDERGROUND UTILITIES, LLC (0.00%)
Contract # 10123001
Totals 107046836.41 2412491.49 57104890.33 53.3

CountyHARRIS
Highway IH 610
From AT IH 10 (E) INTERCHANGE
To .
CSJ 0271-15-086
Proj ID NH 2015(239)
Work Type SLDR REP, PV REP, FULL DEPTH REP, ETC
 
3.793 4114146.51 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 210
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0271-15-086
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143008
Totals 4114146.51 0.00 0.00 0.0

CountyHARRIS
Highway IH 610
From .228 MILES WEST OF LONG DRIVE
To .241 MILES EAST OF SH 288
CSJ 0271-16-130
Proj ID IM 6107(440)
Work Type HIGH MAST ILLUMINATION
 
3.237 1733013.17 0.00 1681886.31 97.2
Work Order 08-29-13
Work Began 12-27-13
Work Completed  
Time Computed 12-27-13
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 125
Percent Time Used 104
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-16-130
VACA UNDERGROUND UTILITIES INC (4.27%)
YORK & YORK FOUNDATION DRILLING, INC.( 12.49%)
INTERSTATE STEEL (BIG SPRING)(1.31%)
THOMPSON CONSTRUCTION(0.80%)
RICE ENVIRONMENTAL SERVICES(1.99%)
BAY CITY TRAFFIC (2.42%)
Contract # 07133231
Totals 1733013.17 0.00 1681886.31 97.2

CountyHARRIS
Highway IH 610
From AT CRESTMONT STREET
To .
CSJ 0271-16-134
Proj ID STP 2014(484)HES
Work Type IMPROVE TS
 
0.404 699002.00 0.00 0.00 0.0
Work Order 05-01-14
Work Began 10-28-14
Work Completed  
Time Computed 10-28-14
Contract Working Days 123
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0271-16-134
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143016
Totals 699002.00 0.00 0.00 0.0

CountyMONTGOMERY
Highway SH 105
From 0.25 MI W OF GRIMES C/L
To PLANTERSVILLE RD
CSJ 0338-02-041
Proj ID NH 2015(157)
Work Type BASE REPAIR AND ACP O / L
 
7.085 2574451.88 420960.09 432760.09 16.8
Work Order 10-01-14
Work Began 10-31-14
Work Completed  
Time Computed 10-31-14
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 21
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0338-02-041
STRIPE-A-LINE, INC.(3.86%)
J & M CONTRACTING, COMPANY (2.95%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (4.35%)
Contract # 09143227
Totals 2574451.88 420960.09 432760.09 16.8

CountyMONTGOMERY
Highway SH 105
From WALDEN ROAD
To OLD RIVER ROAD
CSJ 0338-03-087
Proj ID NH 2012(372)
Work Type WIDEN WB FROM 2 TO 3 LANES
 
0.870 1127783.80 107111.82 997562.95 88.4
Work Order 08-21-13
Work Began 01-02-14
Work Completed  
Time Computed 11-19-13
Contract Working Days 45
Addl Days Granted 16
Working Days Charged 55
Percent Time Used 90
Contractor(s)
HASSELL CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0338-03-087
BATTERSON,LLP(4.36%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. ( 16.28%)
GMJ PAVING CO. (3.87%)
CPAVE, INC.(2.84%)
CHERRY CONCRETE REMOVAL(0.95%)
Contract # 06133019
Totals 1127783.80 107111.82 997562.95 88.4

CountyMONTGOMERY
Highway LP 336
From FM 2854
To IH 45
CSJ 0338-11-051
Proj ID STP 2013(992)
Work Type WIDEN TO 4 LANES
 
3.826 7593341.62 411622.56 6411664.51 84.8
Work Order 10-15-13
Work Began 11-18-13
Work Completed  
Time Computed 10-31-13
Contract Working Days 143
Addl Days Granted 37
Working Days Charged 209
Percent Time Used 116
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0338-11-051
CPAVE, INC.(0.79%)
J & M CONTRACTING, COMPANY ( 35.90%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.07%)
SIEMENS INDUSTRY, INC. (2.74%)
WEST TEXAS RUMBLE STRIP(0.18%)
WILLOW CITY SIGN & RAIL, INC.(1.37%)
BORTUNCO (0.41%)
CEN TEX HYDROSEED, INC.(4.21%)
HEMPHILL PILE DRIVING CO., A CORP. (1.91%)
THIRD COAST SERVICES LLC (2.82%)
BELKNAP CONCRETE, CUTTING & DRILLING, INC. (0.67%)
TOM-MAC, INC.(0.68%)
PRIMATE CONSTRUCTION, INC. (0.19%)
WEBBER BARRIER SERVICES, LLC.(0.34%)
HASSELL CONSTRUCTION COMPANY, INC. (1.18%)
Contract # 08133245
Totals 7593341.62 411622.56 6411664.51 84.8

CountyMONTGOMERY
Highway LP 336
From SH 105 SOUTH
To 0.473 MILES NORTH OF FM 2854
CSJ 0338-11-055
Proj ID NH 2014(638)
Work Type INSTALL CTWLTL
 
0.489 1161105.76 15623.19 1128275.89 97.1
Work Order 05-29-14
Work Began 08-01-14
Work Completed  
Time Computed 07-28-14
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 70
Percent Time Used 58
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0338-11-055
LONESTAR TRAFFIC SAFETY, LLC (0.54%)
CEN TEX HYDROSEED, INC.(2.76%)
BATTERSON,LLP(2.21%)
J & M CONTRACTING, COMPANY (6.65%)
CPAVE, INC.(0.64%)
Contract # 04143239
Totals 1161105.76 15623.19 1128275.89 97.1

CountyGALVESTON
Highway SH 124
From SH 87
To CHAMBERS COUNTY LINE
CSJ 0367-02-077
Proj ID STP 2014(459)
Work Type ACP O / L
 
2.982 1685779.05 27962.53 1625802.45 100.0
Work Order 05-23-14
Work Began 06-09-14
Work Completed 11-12-14
Time Computed 06-09-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 93
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0367-02-077
ROADSAFE TRAFFIC SYSTEMS, INC. (3.67%)
JMHP, INC. ( 10.08%)
Contract # 04143222
Totals 1685779.05 27962.53 1625802.45 100.0

CountyHARRIS
Highway SH 146
From AT BNSF RR/PORT ROAD
To .
CSJ 0389-05-119
Proj ID HP 2012(220)
Work Type CONSTRUCT DIRECT CONNECTOR
 
0.540 11747790.36 127770.77 10822944.65 92.1
Work Order 07-16-12
Work Began 07-24-12
Work Completed  
Time Computed 07-24-12
Contract Working Days 273
Addl Days Granted 5
Working Days Charged 146
Percent Time Used 52
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0389-05-119
MESA ROD BUSTERS, INC. (7.06%)
BATTERSON,LLP(0.23%)
JMHP, INC. (0.47%)
BASE CONSTRUCTION, L.L.P.(1.57%)
ROADWAY CONSTRUCTION, INC. (7.22%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.08%)
KOSSMAN CONTRACTING CO., INC.(0.31%)
TRAF-TEX, INC. (1.10%)
Contract # 06123227
Totals 11747790.36 127770.77 10822944.65 92.1

CountyGALVESTON
Highway SH 146
From AT FM 646
To .
CSJ 0389-06-103
Proj ID STP 2015(244)HES
Work Type IMPROVE TS
 
0.652 369995.94 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-10-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 63
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0389-06-103
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143005
Totals 369995.94 0.00 0.00 0.0

CountyHARRIS
Highway SH 146
From AT FRED HARTMAN BRIDGE
To .
CSJ 0389-12-090
Proj ID NH 1402(100)
Work Type STAY CABLE MAINTENANCE
 
0.001 5139060.00 0.00 0.00 0.0
Work Order 09-22-14
Work Began 00-00-00
Work Completed  
Time Computed 11-21-14
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0389-12-090
LONESTAR TRAFFIC SAFETY, LLC (0.46%)
Contract # 08143030
Totals 5139060.00 0.00 0.00 0.0

CountyHARRIS
Highway SH 146
From AT SPUR 330
To .
CSJ 0389-13-056
Proj ID DMO 2013(178)
Work Type CONSTRUCT DIRECT CONNECTOR
 
0.020 6585237.93 0.00 6659288.77 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-15-13
Work Began 02-14-13
Work Completed 10-03-14
Time Computed 01-31-13
Contract Working Days 195
Addl Days Granted 28
Working Days Charged 308
Percent Time Used 138
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0389-13-056
SCOTT DERR PAINTING CO, LLC(0.30%)
WEBBER-BALKE FOUNDATION COMPANY, INC.( 13.91%)
HIGHWAY TECHNOLOGIES, INC. (0.46%)
HOUSTON SAWING & DRILLING(0.13%)
KOSSMAN CONTRACTING CO., INC.(0.19%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.36%)
MESA ROD BUSTERS, INC. (5.19%)
PROFESSIONAL TRAFFIC CONTROL, LLC(0.62%)
AQUALAWN HYDROMULCH & EROSION CONTROL(0.49%)
Contract # 11123215
Totals 6585237.93 0.00 6659288.77 100.0

CountyHARRIS
Highway SH 146
From 0.19 MILES SOUTH OF WEST MAIN
To 0.37 MILES SOUTH OF WEST TEXAS
CSJ 0389-13-057
Proj ID NH 2015(158)
Work Type MILL & O / L
 
1.130 224351.11 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-14-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0389-13-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143010
Totals 224351.11 0.00 0.00 0.0

CountyWALLER
Highway FM 1488
From BU 290H
To FM 1098
CSJ 0409-03-011
Proj ID STP 2014(611)
Work Type SL CT, W / THIN O / L & PV MRKS
 
19.334 4201121.96 283012.38 4116782.74 97.9
Work Order 05-20-14
Work Began 07-14-14
Work Completed  
Time Computed 07-14-14
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 78
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0409-03-011
WATERS CONSTRUCTION CO., INC.( 24.43%)
BATTERSON,LLP(5.25%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.21%)
C PAVE, INC. (0.71%)
Contract # 04143240
Totals 4201121.96 283012.38 4116782.74 97.9

CountyHARRIS
Highway IH 45
From 0.4808 MILES SOUTH OF EL DORADO
To SOUTH OF MEDICAL CENTER DRIVE
CSJ 0500-03-042
Proj ID NH 2013(163)
Work Type GR, WIDEN STRS & RECONSTR PV
 
2.180 92660504.64 721887.91 34088027.75 36.7
CountyHARRIS
Highway IH 45
From 0.4808 MILES SOUTH OF EL DORADO
To MEDICAL CENTER DRIVE
CSJ 0500-03-546
Proj ID RW 500-3-546
Work Type ROW ACQUISITION, RELO & UTILITIES
 
5.530 627780.60 0.00 624373.55 99.4
Work Order 12-12-12
Work Began 12-17-12
Work Completed  
Time Computed 12-17-12
Contract Working Days 1,125
Addl Days Granted 63
Working Days Charged 395
Percent Time Used 33
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-042
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.64%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.59%)
ESSARY, HART & MACWILIAM,INC.(8.94%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.25%)
SCOTT DERR PAINTING CO, LLC(0.03%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.78%)
CREACOM, INC.(4.12%)
BASE CONSTRUCTION, L.L.P.( 12.36%)
BORTUNCO (0.26%)
Contract # 11123001
Totals 93288285.24 721887.91 34712401.30 37.2

CountyHARRIS
Highway IH 45
From IH 45 NB AT WHITE OAK BAYOU
To .
CSJ 0500-03-044
Proj ID BR 2014(952)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.467 19356558.14 0.00 0.00 0.0
CountyHARRIS
Highway IH 45
From IH 45 NB AT WHITE OAK BAYOU
To .
CSJ 0500-03-589
Proj ID ROW 500-3-589
Work Type ACQUISITION AND UTILITY ADJUSTMENTS
 
0.466 281265.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-30-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 575
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BALFOUR BEATTY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143201
Totals 19637823.14 0.00 0.00 0.0