Monthly State Let Construction Report For Houston District As Of Mar 10, 2015 Page 3 Of 12

Last Update: Wednesday, March 11, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyFORT BEND
Highway IH 10
From AT PIN OAK RD
To .
CSJ 0271-05-040
Proj ID NH 2014(950)
Work Type LANDSCAPE DEVELOPMENT
 
0.004 1897990.52 188841.90 720259.62 37.9
Work Order 07-29-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 83
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-05-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143059
Totals 1897990.52 188841.90 720259.62 37.9

CountyHARRIS
Highway IH 10
From WASHINGTON AVE.
To TAYLOR ST.
CSJ 0271-07-242
Proj ID STP 2010(232)ES
Work Type RECONST & WIDEN SUBGR, PVMT & STRS
 
6.766 48579333.56 2589094.88 57528730.98 99.9
Work Order 03-26-10
Work Began 04-26-10
Work Completed  
Time Computed 04-26-10
Contract Working Days 777
Addl Days Granted 184
Working Days Charged 888
Percent Time Used 92
Contractor(s)
BALFOUR BEATTY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-07-242
BATTERSON, L.L.P.(0.60%)
BIO LANDSCAPE & MAINTENANCE, INC.(2.02%)
CRAVENS SERVICES, INC. (3.98%)
CREACOM, INC.(6.12%)
CURB PLANET INC. (0.05%)
ESSARY, HART & MACWILIAM,INC.(0.65%)
FARR FOUNDATION, INC.(0.66%)
GMJ PAVING CO. (2.17%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.17%)
J.H. PAINTING COMPANY(0.34%)
LMS, INC.(0.54%)
MERIDIAN FENCE AND SECURITY, L.P.(1.12%)
SOUTHERN CRUSHED CONCRETE INC. (1.33%)
WEBBER BARRIER SERVICES, INC.(1.55%)
WILLOW CITY SIGN & RAIL, INC.(0.72%)
W. W. FOUNDATION DRILLING, LTD.(2.99%)
MESA ROD BUSTERS, INC. (0.14%)
REINFORCED EARTH (3.27%)
JOB LINK PERSONNEL SERVICES, INC.(0.22%)
SPECIALTY DRILLING (0.42%)
MAGNUM TUNNELING, LLC(0.40%)
BEDO CONSTRUCTION PRODUCTS, INC. (6.04%)
ISBELL CONSTRUCTION(0.06%)
R & A BORING COMPANY (0.20%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(0.22%)
T & C CONSTRUCTION, INC. ( 11.18%)
S & S MASONRY,INC. (0.07%)
VAN & SONS_DRILLING SERVICE, INC.(0.05%)
MEDCALF FABRICATION, INC.(0.70%)
ENERGY ELECTRICAL SUPPLY,INC.(0.40%)
ALLSTATE GROUNDWATER CONTROL, LP (0.19%)
PFEIFFER & SON LTD.(1.75%)
TOM-MAC, INC.(0.44%)
J. W. RENEAU ROOFING CO. (0.03%)
UNIVERSAL COATING SPECIALISTS(0.03%)
W.W. OVERHEAD DOOR COMPANY (0.00%)
MAGNUM TUNNELING, LLC(0.06%)
SCOTT DERR PAINTING CO (0.20%)
Contract # 01103201
Totals 48579333.56 2589094.88 57528730.98 99.9

CountyHARRIS
Highway IH 10
From AT WHITE OAK BAYOU
To .
CSJ 0271-07-292
Proj ID STP 2011(025)MM
Work Type DRAINAGE AND DETENTION FACILITIES
 
0.001 3594471.44 5546.56 4067412.67 99.9
Work Order 10-20-10
Work Began 01-05-11
Work Completed  
Time Computed 01-05-11
Contract Working Days 156
Addl Days Granted 0
Working Days Charged 156
Percent Time Used 100
Contractor(s)
BALFOUR BEATTY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-07-292
APCON SERVICES, LLC(1.60%)
SOUTHERN CRUSHED CONCRETE INC. (2.52%)
BOYER, INC.( 10.09%)
ENVIRONMENTAL ALLIES, L.P. (1.00%)
EROSION CONTROL, INC.(2.42%)
EROSION PREVENTION PRODUCTS( 13.41%)
MAGNUM TUNNELING, LLC(0.19%)
GUS TRUCKING SERVICES( 36.75%)
PRIME TREES, INC.(0.91%)
DOUG"S TREE SERVICES (0.91%)
Contract # 08103205
Totals 3594471.44 5546.56 4067412.67 99.9

CountyHARRIS
Highway IH 10
From TC JESTER
To TAYLOR STREET
CSJ 0271-07-304
Proj ID IM 0107(433)
Work Type DRAINAGE AND DETENTION FACILITIES
 
2.133 2096611.52 3100.00 2150900.26 99.9
Work Order 06-18-12
Work Began 04-02-13
Work Completed  
Time Computed 12-15-12
Contract Working Days 186
Addl Days Granted 0
Working Days Charged 183
Percent Time Used 98
Contractor(s)
LECON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-07-304
BIO LANDSCAPE & MAINTENANCE, INC.( 28.20%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(6.15%)
EROSION PREVENTION PRODUCTS(9.35%)
STRIPES & STOPS COMPANY, INC.(0.10%)
WM TRUCKING & EXCAVATING INC.(6.20%)
Contract # 04123215
Totals 2096611.52 3100.00 2150900.26 99.9

CountyWALLER
Highway US 90
From AT FM 359
To .
CSJ 0271-09-021
Proj ID STP 2014(924)
Work Type INSTALL LEFT TURN LANE
 
0.566 671947.83 24290.00 428831.82 63.8
Work Order 09-11-14
Work Began 09-22-14
Work Completed  
Time Computed 09-22-14
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 21
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0271-09-021
BATTERSON,LLP(5.36%)
THIRD COAST SERVICES LLC ( 17.52%)
EROSION CONTROL, INC.(2.64%)
JMHP, INC. (1.54%)
CENTRAL CONSTRUCTION SERVICES, INC.(0.18%)
Contract # 07143037
Totals 671947.83 24290.00 428831.82 63.8

CountyHARRIS
Highway IH 610
From W OF W 34TH ST ON US 290 (SEG 3)
To ON IH 610
CSJ 0271-14-213
Proj ID CM 2013(991)
Work Type GR, STRS, BASE AND PAVE
 
0.198 151543734.14 2790813.93 46206047.65 30.4
Work Order 12-11-13
Work Began 12-31-13
Work Completed  
Time Computed 07-07-14
Contract Working Days 1,095
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-213
CPAVE, INC.(0.07%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.37%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.75%)
SCOTT DERR PAINTING CO, LLC(0.21%)
HOUSTON SAWING & DRILLING(0.07%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(0.28%)
ESSARY, HART & MACWILIAM,INC.(9.64%)
BORTUNCO (0.53%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.57%)
RAY"S THREADING AND FAB SHOP (0.39%)
Contract # 11133201
Totals 151543734.14 2790813.93 46206047.65 30.4

CountyHARRIS
Highway IH 610
From TC JESTER TO N OF IH 10 ON IH 610
To AND TO 34TH ST ON US 290
CSJ 0271-14-217
Proj ID STP 2011(998)MM
Work Type GR, STRS, BASE AND PAVE
 
5.604 151578391.02 1338907.82 148833117.06 95.7
Work Order 06-15-11
Work Began 06-20-11
Work Completed  
Time Computed 07-11-11
Contract Working Days 1,124
Addl Days Granted 106
Working Days Charged 1,113
Percent Time Used 90
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-217
INTERSTATE BARRICADES & MARKINGS, INC. (0.54%)
FLORIDA TRAFFIC CONTROL DEVICES, INC.(5.43%)
ESSARY, HART & MACWILIAM,INC.( 11.06%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.21%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.19%)
SCOTT DERR PAINTING CO (0.58%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.77%)
BORTUNCO (0.29%)
SPECIALTY DRILLING (0.39%)
AMERICAN TRAFFIC CONTROL, INC. (0.01%)
TREVCON, INC.(0.09%)
BROOKLYN SWEEPS(0.24%)
MAGNOLIA SERVICES INCORPORATED (0.04%)
CHERRY DEMOLITION(0.07%)
Contract # 05113015
Totals 151578391.02 1338907.82 148833117.06 95.7

CountyHARRIS
Highway IH 610
From AT IH 45(N) INTERCHANGE
To .
CSJ 0271-14-224
Proj ID IM 6107(438)
Work Type ACP O / L
 
0.520 1766700.70 48341.18 1740408.86 98.5
Work Order 09-16-13
Work Began 08-09-14
Work Completed  
Time Computed 03-01-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 35
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-224
BATTERSON,LLP(4.84%)
MAIN LANE INDUSTRIES, LTD. ( 18.20%)
Contract # 08133230
Totals 1766700.70 48341.18 1740408.86 98.5

CountyHARRIS
Highway IH 610
From W OF W 34TH ST ON US 290 (SEG 3)
To ON IH 610
CSJ 0271-14-225
Proj ID RW 271-14-225
Work Type ROW ACQ., UTL. ADJ.; RELOC ASSIST.
 
2.640 1670105.95 0.00 1594268.79 95.4
CountyHARRIS
Highway IH 610
From W OF W 34TH ST ON US 290 (SEG 3)
To N AND S OF US 290 ON IH 610
CSJ 0271-14-228
Proj ID STP 2013(136)MM
Work Type GR, STRS, BASE AND PAVE
 
1.661 105376730.46 621015.48 60460327.55 57.3
Work Order 11-09-12
Work Began 11-20-12
Work Completed  
Time Computed 02-04-13
Contract Working Days 1,030
Addl Days Granted 0
Working Days Charged 618
Percent Time Used 60
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-228
BATTERSON,LLP(0.69%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.35%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(0.17%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.16%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.36%)
ESSARY, HART & MACWILIAM,INC.(9.54%)
SCOTT DERR PAINTING CO, LLC(0.23%)
MAGNOLIA SERVICES INCORPORATED (0.17%)
CURB PLANET INC. (0.02%)
EROSION PREVENTION PRODUCTS(0.15%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (4.74%)
W. W. FOUNDATION DRILLING, LTD.(0.21%)
TEJAS UNDERGROUND UTILITIES, LLC (0.00%)
Contract # 10123001
Totals 107046836.41 621015.48 62054596.34 57.9

CountyHARRIS
Highway IH 610
From AT IH 10 (E) INTERCHANGE
To .
CSJ 0271-15-086
Proj ID NH 2015(239)
Work Type SLDR REP, PV REP, FULL DEPTH REP, ETC
 
3.793 4114146.51 0.00 0.00 0.0
Work Order 01-05-15
Work Began 00-00-00
Work Completed  
Time Computed 01-21-15
Contract Working Days 210
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0271-15-086
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143008
Totals 4114146.51 0.00 0.00 0.0

CountyHARRIS
Highway IH 610
From .228 MILES WEST OF LONG DRIVE
To .241 MILES EAST OF SH 288
CSJ 0271-16-130
Proj ID IM 6107(440)
Work Type HIGH MAST ILLUMINATION
 
3.237 1733013.17 391.92 1751911.13 100.0
Work Order 08-29-13
Work Began 12-27-13
Work Completed 02-03-15
Time Computed 12-27-13
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 125
Percent Time Used 104
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-16-130
VACA UNDERGROUND UTILITIES INC (4.27%)
YORK & YORK FOUNDATION DRILLING, INC.( 12.49%)
INTERSTATE STEEL (BIG SPRING)(1.31%)
THOMPSON CONSTRUCTION(0.80%)
RICE ENVIRONMENTAL SERVICES(1.99%)
BAY CITY TRAFFIC (2.42%)
Contract # 07133231
Totals 1733013.17 391.92 1751911.13 100.0

CountyHARRIS
Highway IH 610
From AT CRESTMONT STREET
To .
CSJ 0271-16-134
Proj ID STP 2014(484)HES
Work Type IMPROVE TS
 
0.404 699002.00 67108.02 107356.55 15.3
Work Order 05-01-14
Work Began 10-28-14
Work Completed  
Time Computed 10-28-14
Contract Working Days 123
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 43
Contractor(s)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0271-16-134
KAM CONSTRUCTION, INC. ( 10.17%)
REGIONAL TRAFFIC SERVICES LLC(3.05%)
VASQUEZ CONCRETE COMPANY (6.43%)
Contract # 03143016
Totals 699002.00 67108.02 107356.55 15.3

CountyMONTGOMERY
Highway SH 105
From 0.25 MI W OF GRIMES C/L
To PLANTERSVILLE RD
CSJ 0338-02-041
Proj ID NH 2015(157)
Work Type BASE REPAIR AND ACP O / L
 
7.085 2574451.88 217471.31 2389905.58 92.8
Work Order 10-01-14
Work Began 10-31-14
Work Completed  
Time Computed 10-31-14
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 82
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0338-02-041
STRIPE-A-LINE, INC.(3.86%)
J & M CONTRACTING, COMPANY (2.95%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (4.35%)
Contract # 09143227
Totals 2574451.88 217471.31 2389905.58 92.8

CountyMONTGOMERY
Highway SH 105
From WALDEN ROAD
To OLD RIVER ROAD
CSJ 0338-03-087
Proj ID NH 2012(372)
Work Type WIDEN WB FROM 2 TO 3 LANES
 
0.870 1127783.80 94707.66 1414269.02 99.9
Work Order 08-21-13
Work Began 01-02-14
Work Completed  
Time Computed 11-19-13
Contract Working Days 45
Addl Days Granted 21
Working Days Charged 65
Percent Time Used 98
Contractor(s)
HASSELL CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0338-03-087
BATTERSON,LLP(4.36%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. ( 16.28%)
GMJ PAVING CO. (3.87%)
CPAVE, INC.(2.84%)
CHERRY CONCRETE REMOVAL(0.95%)
Contract # 06133019
Totals 1127783.80 94707.66 1414269.02 99.9

CountyMONTGOMERY
Highway LP 336
From FM 2854
To IH 45
CSJ 0338-11-051
Proj ID STP 2013(992)
Work Type WIDEN TO 4 LANES
 
3.826 7593341.62 338040.12 7867870.66 99.9
Work Order 10-15-13
Work Began 11-18-13
Work Completed  
Time Computed 10-31-13
Contract Working Days 143
Addl Days Granted 37
Working Days Charged 254
Percent Time Used 141
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0338-11-051
CPAVE, INC.(0.79%)
J & M CONTRACTING, COMPANY ( 35.90%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.07%)
SIEMENS INDUSTRY, INC. (2.74%)
WEST TEXAS RUMBLE STRIP(0.18%)
WILLOW CITY SIGN & RAIL, INC.(1.37%)
BORTUNCO (0.41%)
CEN TEX HYDROSEED, INC.(4.21%)
HEMPHILL PILE DRIVING CO., A CORP. (1.91%)
THIRD COAST SERVICES LLC (2.82%)
BELKNAP CONCRETE, CUTTING & DRILLING, INC. (0.67%)
TOM-MAC, INC.(0.68%)
PRIMATE CONSTRUCTION, INC. (0.19%)
WEBBER BARRIER SERVICES, LLC.(0.34%)
HASSELL CONSTRUCTION COMPANY, INC. (1.18%)
Contract # 08133245
Totals 7593341.62 338040.12 7867870.66 99.9

CountyMONTGOMERY
Highway LP 336
From SH 105 SOUTH
To 0.473 MILES NORTH OF FM 2854
CSJ 0338-11-055
Proj ID NH 2014(638)
Work Type INSTALL CTWLTL
 
0.489 1161105.76 47895.02 1266789.84 100.0
Work Order 05-29-14
Work Began 08-01-14
Work Completed 02-18-15
Time Computed 07-28-14
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 99
Percent Time Used 82
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0338-11-055
LONESTAR TRAFFIC SAFETY, LLC (0.54%)
CEN TEX HYDROSEED, INC.(2.76%)
BATTERSON,LLP(2.21%)
J & M CONTRACTING, COMPANY (6.65%)
CPAVE, INC.(0.64%)
Contract # 04143239
Totals 1161105.76 47895.02 1266789.84 100.0

CountyGALVESTON
Highway SH 124
From SH 87
To CHAMBERS COUNTY LINE
CSJ 0367-02-077
Proj ID STP 2014(459)
Work Type ACP O / L
 
2.982 1685779.05 0.00 1625802.45 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-23-14
Work Began 06-09-14
Work Completed 11-12-14
Time Computed 06-09-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 93
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0367-02-077
ROADSAFE TRAFFIC SYSTEMS, INC. (3.67%)
JMHP, INC. ( 10.08%)
Contract # 04143222
Totals 1685779.05 0.00 1625802.45 100.0

CountyHARRIS
Highway SH 146
From AT BNSF RR/PORT ROAD
To .
CSJ 0389-05-119
Proj ID HP 2012(220)
Work Type CONSTRUCT DIRECT CONNECTOR
 
0.540 11747790.36 39599.49 10900451.91 92.7
Work Order 07-16-12
Work Began 07-24-12
Work Completed  
Time Computed 07-24-12
Contract Working Days 273
Addl Days Granted 5
Working Days Charged 146
Percent Time Used 52
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0389-05-119
MESA ROD BUSTERS, INC. (7.06%)
BATTERSON,LLP(0.23%)
JMHP, INC. (0.47%)
BASE CONSTRUCTION, L.L.P.(1.57%)
ROADWAY CONSTRUCTION, INC. (7.22%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.08%)
KOSSMAN CONTRACTING CO., INC.(0.31%)
TRAF-TEX, INC. (1.10%)
Contract # 06123227
Totals 11747790.36 39599.49 10900451.91 92.7

CountyGALVESTON
Highway SH 146
From AT FM 646
To .
CSJ 0389-06-103
Proj ID STP 2015(244)HES
Work Type IMPROVE TS
 
0.652 369995.94 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-10-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 63
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0389-06-103
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143005
Totals 369995.94 0.00 0.00 0.0

CountyHARRIS
Highway SH 146
From AT FRED HARTMAN BRIDGE
To .
CSJ 0389-12-090
Proj ID NH 1402(100)
Work Type STAY CABLE MAINTENANCE
 
0.001 5139060.00 2111370.28 3249104.84 63.2
Work Order 09-22-14
Work Began 12-01-14
Work Completed  
Time Computed 11-21-14
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 39
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0389-12-090
LONESTAR TRAFFIC SAFETY, LLC (0.46%)
ALPIN TECHNIK UND INGENIEURSERVICE GMBH( 62.87%)
PURE TECHNOLOGIES(1.51%)
Contract # 08143030
Totals 5139060.00 2111370.28 3249104.84 63.2