Monthly State Let Construction Report For Houston District As Of Jun 10, 2015 Page 3 Of 12

Last Update: Wednesday, June 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBRAZORIA
Highway SH 35
From SOUTH OF FM 1462
To FM 2403
CSJ 0178-03-152
Proj ID NH 2015(701)
Work Type ADD AUXILIARY LANE
 
9.928 2129904.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-08-15
Work Began 00-00-00
Work Completed  
Time Computed 07-08-15
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0178-03-152
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153003
Totals 2129904.80 0.00 0.00 0.0

CountyFORT BEND
Highway SP 10
From US 59 SOUTH
To SH 36
CSJ 0187-05-050
Proj ID C 187-5-50
Work Type GR, STRS, BASE & SURF
 
4.825 19773719.86 787419.22 14557587.04 73.6
Work Order 11-14-13
Work Began 02-20-14
Work Completed  
Time Computed 05-13-14
Contract Working Days 386
Addl Days Granted 0
Working Days Charged 208
Percent Time Used 53
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0187-05-050
BATTERSON,LLP(1.21%)
RICE ENVIRONMENTAL SERVICES(1.95%)
BREDA COMPANY, INC.(7.64%)
EROSION CONTROL, INC.(2.54%)
SCOTT DERR PAINTING CO (0.05%)
CPAVE, INC.(0.36%)
HOUSTON SAWING & DRILLING(0.01%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (0.25%)
WEST TEXAS RUMBLE STRIP(0.09%)
JAMES CONSTRUCTION GROUP, L.L.C. (7.11%)
Contract # 08133205
Totals 19773719.86 787419.22 14557587.04 73.6

CountyFORT BEND
Highway SH 36
From 0.14 M S OF FM 2218
To BRAZORIA COUNTY LINE
CSJ 0188-02-042
Proj ID STP 2012(507)HES
Work Type RUMBLE STRIPS
 
0.006 215732.48 0.00 235094.04 99.9
CountyFORT BEND
Highway SH 36
From FM 2218
To BRAZORIA COUNTY LINE
CSJ 0188-02-043
Proj ID NH 2012(506)
Work Type WDN RDWY W / O / L & PV MKS
 
13.855 5439229.13 0.00 6172268.56 99.9
CountyFORT BEND
Highway SH 36
From AT BIG CREEK
To .
CSJ 0188-02-044
Proj ID BR 2012(505)
Work Type REHABILITATE BRIDGE (ADD SHOULDERS)
 
0.148 654448.31 0.00 681912.70 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-09-12
Work Began 08-27-12
Work Completed  
Time Computed 08-27-12
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 150
Percent Time Used 100
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0188-02-043
HIGHWAY TECHNOLOGIES, INC. (0.57%)
COWBELL TRAFFIC SERVICES, INC. (0.12%)
WEBBER BARRIER SERVICES, INC.(0.62%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.78%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.48%)
JMHP, INC. (4.35%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(0.67%)
BREDA COMPANY, INC.(0.20%)
BATTERSON,LLP(4.29%)
CURB PLANET INC. (0.03%)
APCON SERVICES, LLC(0.02%)
TEXAS REEXCAVATION (0.04%)
Contract # 05123004
Totals 6309409.92 0.00 7089275.30 99.9

CountyFORT BEND
Highway IH 10
From FM 1463
To WALLER C/L
CSJ 0271-05-037
Proj ID IM 0107(444)
Work Type GS, ROUNDABOUT, LOOP RDS, OVERLAY
 
2.890 10742564.74 422164.80 6477942.80 60.3
Work Order 04-15-14
Work Began 07-22-14
Work Completed  
Time Computed 07-22-14
Contract Working Days 178
Addl Days Granted 0
Working Days Charged 151
Percent Time Used 84
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0271-05-037
W. W. FOUNDATION DRILLING, LTD.(2.39%)
TRAF-TEX, INC. (4.38%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (0.41%)
SCOTT DERR PAINTING CO (0.10%)
DUSTROL, INC.(0.19%)
CPAVE, INC.(0.22%)
H & E AGGREGATE, LLC (3.75%)
BREDA COMPANY, INC.(0.87%)
ROMAR UNLIMITED, INC.(1.34%)
PROFESSIONAL TRAFFIC CONTROL, LLC(1.70%)
MESA ROD BUSTERS, INC. (0.11%)
LONE STAR BARRIER SERVICES, LLC(3.10%)
Contract # 02143011
Totals 10742564.74 422164.80 6477942.80 60.3

CountyFORT BEND
Highway IH 10
From AT PIN OAK RD
To .
CSJ 0271-05-040
Proj ID NH 2014(950)
Work Type LANDSCAPE DEVELOPMENT
 
0.004 1897990.52 72784.25 917131.07 48.3
Work Order 07-29-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 105
Addl Days Granted 44
Working Days Charged 120
Percent Time Used 80
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-05-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143059
Totals 1897990.52 72784.25 917131.07 48.3

CountyHARRIS
Highway IH 10
From WASHINGTON AVE.
To TAYLOR ST.
CSJ 0271-07-242
Proj ID STP 2010(232)ES
Work Type RECONST & WIDEN SUBGR, PVMT & STRS
 
6.766 48579333.56 10279.29 57627664.44 99.9
Work Order 03-26-10
Work Began 04-26-10
Work Completed  
Time Computed 04-26-10
Contract Working Days 777
Addl Days Granted 184
Working Days Charged 888
Percent Time Used 92
Contractor(s)
BALFOUR BEATTY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-07-242
BATTERSON, L.L.P.(0.60%)
BIO LANDSCAPE & MAINTENANCE, INC.(2.02%)
CRAVENS SERVICES, INC. (3.98%)
CREACOM, INC.(6.12%)
CURB PLANET INC. (0.05%)
ESSARY, HART & MACWILIAM,INC.(0.65%)
FARR FOUNDATION, INC.(0.66%)
GMJ PAVING CO. (2.17%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.17%)
J.H. PAINTING COMPANY(0.34%)
LMS, INC.(0.54%)
MERIDIAN FENCE AND SECURITY, L.P.(1.12%)
SOUTHERN CRUSHED CONCRETE INC. (1.33%)
WEBBER BARRIER SERVICES, INC.(1.55%)
WILLOW CITY SIGN & RAIL, INC.(0.72%)
W. W. FOUNDATION DRILLING, LTD.(2.99%)
MESA ROD BUSTERS, INC. (0.14%)
REINFORCED EARTH (3.27%)
JOB LINK PERSONNEL SERVICES, INC.(0.22%)
SPECIALTY DRILLING (0.42%)
MAGNUM TUNNELING, LLC(0.40%)
BEDO CONSTRUCTION PRODUCTS, INC. (6.04%)
ISBELL CONSTRUCTION(0.06%)
R & A BORING COMPANY (0.20%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(0.22%)
T & C CONSTRUCTION, INC. ( 11.18%)
S & S MASONRY,INC. (0.07%)
VAN & SONS_DRILLING SERVICE, INC.(0.05%)
MEDCALF FABRICATION, INC.(0.70%)
ENERGY ELECTRICAL SUPPLY,INC.(0.40%)
ALLSTATE GROUNDWATER CONTROL, LP (0.19%)
PFEIFFER & SON LTD.(1.75%)
TOM-MAC, INC.(0.44%)
J. W. RENEAU ROOFING CO. (0.03%)
UNIVERSAL COATING SPECIALISTS(0.03%)
W.W. OVERHEAD DOOR COMPANY (0.00%)
MAGNUM TUNNELING, LLC(0.06%)
SCOTT DERR PAINTING CO (0.20%)
Contract # 01103201
Totals 48579333.56 10279.29 57627664.44 99.9

CountyHARRIS
Highway IH 10
From AT WHITE OAK BAYOU
To .
CSJ 0271-07-292
Proj ID STP 2011(025)MM
Work Type DRAINAGE AND DETENTION FACILITIES
 
0.001 3594471.44 2056.70 4102928.59 99.9
Work Order 10-20-10
Work Began 01-05-11
Work Completed  
Time Computed 01-05-11
Contract Working Days 156
Addl Days Granted 0
Working Days Charged 156
Percent Time Used 100
Contractor(s)
BALFOUR BEATTY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-07-292
APCON SERVICES, LLC(1.60%)
SOUTHERN CRUSHED CONCRETE INC. (2.52%)
BOYER, INC.( 10.09%)
ENVIRONMENTAL ALLIES, L.P. (1.00%)
EROSION CONTROL, INC.(2.42%)
EROSION PREVENTION PRODUCTS( 13.41%)
MAGNUM TUNNELING, LLC(0.19%)
GUS TRUCKING SERVICES( 36.75%)
PRIME TREES, INC.(0.91%)
DOUG"S TREE SERVICES (0.91%)
Contract # 08103205
Totals 3594471.44 2056.70 4102928.59 99.9

CountyHARRIS
Highway IH 10
From TC JESTER
To TAYLOR STREET
CSJ 0271-07-304
Proj ID IM 0107(433)
Work Type DRAINAGE AND DETENTION FACILITIES
 
2.133 2096611.52 7652.53 2164752.79 99.9
Work Order 06-18-12
Work Began 04-02-13
Work Completed  
Time Computed 12-15-12
Contract Working Days 186
Addl Days Granted 0
Working Days Charged 183
Percent Time Used 98
Contractor(s)
LECON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-07-304
BIO LANDSCAPE & MAINTENANCE, INC.( 28.20%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(6.15%)
EROSION PREVENTION PRODUCTS(9.35%)
STRIPES & STOPS COMPANY, INC.(0.10%)
WM TRUCKING & EXCAVATING INC.(6.20%)
Contract # 04123215
Totals 2096611.52 7652.53 2164752.79 99.9

CountyWALLER
Highway US 90
From AT FM 359
To .
CSJ 0271-09-021
Proj ID STP 2014(924)
Work Type INSTALL LEFT TURN LANE
 
0.566 671947.83 86615.76 647061.54 96.2
Work Order 09-11-14
Work Began 09-22-14
Work Completed  
Time Computed 09-22-14
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 71
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0271-09-021
BATTERSON,LLP(5.36%)
THIRD COAST SERVICES LLC ( 17.52%)
EROSION CONTROL, INC.(2.64%)
JMHP, INC. (1.54%)
CENTRAL CONSTRUCTION SERVICES, INC.(0.18%)
Contract # 07143037
Totals 671947.83 86615.76 647061.54 96.2

CountyHARRIS
Highway IH 610
From W OF W 34TH ST ON US 290 (SEG 3)
To ON IH 610
CSJ 0271-14-213
Proj ID CM 2013(991)
Work Type GR, STRS, BASE AND PAVE
 
0.198 151543734.14 784171.48 49371539.45 32.5
Work Order 12-11-13
Work Began 12-31-13
Work Completed  
Time Computed 07-07-14
Contract Working Days 1,095
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-213
CPAVE, INC.(0.07%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.37%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.75%)
SCOTT DERR PAINTING CO, LLC(0.21%)
HOUSTON SAWING & DRILLING(0.07%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(0.28%)
ESSARY, HART & MACWILIAM,INC.(9.64%)
BORTUNCO (0.53%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.57%)
RAY"S THREADING AND FAB SHOP (0.39%)
Contract # 11133201
Totals 151543734.14 784171.48 49371539.45 32.5

CountyHARRIS
Highway IH 610
From TC JESTER TO N OF IH 10 ON IH 610
To AND TO 34TH ST ON US 290
CSJ 0271-14-217
Proj ID STP 2011(998)MM
Work Type GR, STRS, BASE AND PAVE
 
5.604 151578391.02 295300.35 150886025.93 97.0
Work Order 06-15-11
Work Began 06-20-11
Work Completed  
Time Computed 07-11-11
Contract Working Days 1,124
Addl Days Granted 106
Working Days Charged 1,189
Percent Time Used 96
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-217
INTERSTATE BARRICADES & MARKINGS, INC. (0.54%)
FLORIDA TRAFFIC CONTROL DEVICES, INC.(5.43%)
ESSARY, HART & MACWILIAM,INC.( 11.06%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.21%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.19%)
SCOTT DERR PAINTING CO (0.58%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.77%)
BORTUNCO (0.29%)
SPECIALTY DRILLING (0.39%)
AMERICAN TRAFFIC CONTROL, INC. (0.01%)
TREVCON, INC.(0.09%)
BROOKLYN SWEEPS(0.24%)
MAGNOLIA SERVICES INCORPORATED (0.04%)
CHERRY DEMOLITION(0.07%)
Contract # 05113015
Totals 151578391.02 295300.35 150886025.93 97.0

CountyHARRIS
Highway IH 610
From AT IH 45(N) INTERCHANGE
To .
CSJ 0271-14-224
Proj ID IM 6107(438)
Work Type ACP O / L
 
0.520 1766700.70 0.00 1760095.36 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-16-13
Work Began 08-09-14
Work Completed 05-11-15
Time Computed 03-01-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 35
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-224
BATTERSON,LLP(4.84%)
MAIN LANE INDUSTRIES, LTD. ( 18.20%)
Contract # 08133230
Totals 1766700.70 0.00 1760095.36 100.0

CountyHARRIS
Highway IH 610
From W OF W 34TH ST ON US 290 (SEG 3)
To ON IH 610
CSJ 0271-14-225
Proj ID RW 271-14-225
Work Type ROW ACQ., UTL. ADJ.; RELOC ASSIST.
 
2.640 1670105.95 0.00 1594268.79 95.4
CountyHARRIS
Highway IH 610
From W OF W 34TH ST ON US 290 (SEG 3)
To N AND S OF US 290 ON IH 610
CSJ 0271-14-228
Proj ID STP 2013(136)MM
Work Type GR, STRS, BASE AND PAVE
 
1.661 105376730.46 1066461.13 64079308.75 60.3
Work Order 11-09-12
Work Began 11-20-12
Work Completed  
Time Computed 02-04-13
Contract Working Days 1,030
Addl Days Granted 0
Working Days Charged 694
Percent Time Used 67
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-228
BATTERSON,LLP(0.69%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.35%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(0.17%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.16%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.36%)
ESSARY, HART & MACWILIAM,INC.(9.54%)
SCOTT DERR PAINTING CO, LLC(0.23%)
MAGNOLIA SERVICES INCORPORATED (0.17%)
CURB PLANET INC. (0.02%)
EROSION PREVENTION PRODUCTS(0.15%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (4.74%)
W. W. FOUNDATION DRILLING, LTD.(0.21%)
TEJAS UNDERGROUND UTILITIES, LLC (0.00%)
Contract # 10123001
Totals 107046836.41 1066461.13 65673577.54 60.9

CountyHARRIS
Highway IH 610
From AT IH 10 (E) INTERCHANGE
To .
CSJ 0271-15-086
Proj ID NH 2015(239)
Work Type SLDR REP, PV REP, FULL DEPTH REP, ETC
 
3.793 4114146.51 615370.15 619870.15 15.0
Work Order 01-05-15
Work Began 04-27-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 210
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 16
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0271-15-086
BATTERSON,LLP(2.23%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.(1.52%)
COX PAVING COMPANY, L.P. (4.18%)
ISI CONTRACTING, INC.( 36.12%)
R & A TRANSPORT, INC.(5.02%)
Contract # 10143008
Totals 4114146.51 615370.15 619870.15 15.0

CountyHARRIS
Highway IH 610
From .228 MILES WEST OF LONG DRIVE
To .241 MILES EAST OF SH 288
CSJ 0271-16-130
Proj ID IM 6107(440)
Work Type HIGH MAST ILLUMINATION
 
3.237 1733013.17 0.00 1752079.10 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-29-13
Work Began 12-27-13
Work Completed 02-03-15
Time Computed 12-27-13
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 125
Percent Time Used 104
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-16-130
VACA UNDERGROUND UTILITIES INC (4.27%)
YORK & YORK FOUNDATION DRILLING, INC.( 12.49%)
INTERSTATE STEEL (BIG SPRING)(1.31%)
THOMPSON CONSTRUCTION(0.80%)
RICE ENVIRONMENTAL SERVICES(1.99%)
BAY CITY TRAFFIC (2.42%)
Contract # 07133231
Totals 1733013.17 0.00 1752079.10 100.0

CountyHARRIS
Highway IH 610
From AT CRESTMONT STREET
To .
CSJ 0271-16-134
Proj ID STP 2014(484)HES
Work Type IMPROVE TS
 
0.404 699002.00 116770.88 559260.47 80.0
Work Order 05-01-14
Work Began 10-28-14
Work Completed  
Time Computed 10-28-14
Contract Working Days 123
Addl Days Granted 0
Working Days Charged 102
Percent Time Used 82
Contractor(s)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0271-16-134
KAM CONSTRUCTION, INC. ( 10.17%)
REGIONAL TRAFFIC SERVICES LLC(3.05%)
VASQUEZ CONCRETE COMPANY (6.43%)
Contract # 03143016
Totals 699002.00 116770.88 559260.47 80.0

CountyMONTGOMERY
Highway SH 105
From 0.25 MI W OF GRIMES C/L
To PLANTERSVILLE RD
CSJ 0338-02-041
Proj ID NH 2015(157)
Work Type BASE REPAIR AND ACP O / L
 
7.085 2574451.88 67810.14 2570561.30 99.9
Work Order 10-01-14
Work Began 10-31-14
Work Completed  
Time Computed 10-31-14
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 80
Percent Time Used 140
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0338-02-041
STRIPE-A-LINE, INC.(3.86%)
J & M CONTRACTING, COMPANY (2.95%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (4.35%)
Contract # 09143227
Totals 2574451.88 67810.14 2570561.30 99.9

CountyMONTGOMERY
Highway SH 105
From WALDEN ROAD
To OLD RIVER ROAD
CSJ 0338-03-087
Proj ID NH 2012(372)
Work Type WIDEN WB FROM 2 TO 3 LANES
 
0.870 1127783.80 523.67 1443781.31 99.9
Work Order 08-21-13
Work Began 01-02-14
Work Completed  
Time Computed 11-19-13
Contract Working Days 45
Addl Days Granted 21
Working Days Charged 65
Percent Time Used 98
Contractor(s)
HASSELL CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0338-03-087
BATTERSON,LLP(4.36%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. ( 16.28%)
GMJ PAVING CO. (3.87%)
CPAVE, INC.(2.84%)
CHERRY CONCRETE REMOVAL(0.95%)
Contract # 06133019
Totals 1127783.80 523.67 1443781.31 99.9

CountyMONTGOMERY
Highway LP 336
From FM 2854
To IH 45
CSJ 0338-11-051
Proj ID STP 2013(992)
Work Type WIDEN TO 4 LANES
 
3.826 7593341.62 0.00 7911688.78 99.9
Work Order 10-15-13
Work Began 11-18-13
Work Completed  
Time Computed 10-31-13
Contract Working Days 143
Addl Days Granted 37
Working Days Charged 256
Percent Time Used 142
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0338-11-051
CPAVE, INC.(0.79%)
J & M CONTRACTING, COMPANY ( 35.90%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.07%)
SIEMENS INDUSTRY, INC. (2.74%)
WEST TEXAS RUMBLE STRIP(0.18%)
WILLOW CITY SIGN & RAIL, INC.(1.37%)
BORTUNCO (0.41%)
CEN TEX HYDROSEED, INC.(4.21%)
HEMPHILL PILE DRIVING CO., A CORP. (1.91%)
THIRD COAST SERVICES LLC (2.82%)
BELKNAP CONCRETE, CUTTING & DRILLING, INC. (0.67%)
TOM-MAC, INC.(0.68%)
PRIMATE CONSTRUCTION, INC. (0.19%)
WEBBER BARRIER SERVICES, LLC.(0.34%)
HASSELL CONSTRUCTION COMPANY, INC. (1.18%)
Contract # 08133245
Totals 7593341.62 0.00 7911688.78 99.9

CountyMONTGOMERY
Highway LP 336
From SH 105 SOUTH
To 0.473 MILES NORTH OF FM 2854
CSJ 0338-11-055
Proj ID NH 2014(638)
Work Type INSTALL CTWLTL
 
0.489 1161105.76 0.00 1266789.84 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-29-14
Work Began 08-01-14
Work Completed 02-18-15
Time Computed 07-28-14
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 99
Percent Time Used 82
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0338-11-055
LONESTAR TRAFFIC SAFETY, LLC (0.54%)
CEN TEX HYDROSEED, INC.(2.76%)
BATTERSON,LLP(2.21%)
J & M CONTRACTING, COMPANY (6.65%)
CPAVE, INC.(0.64%)
Contract # 04143239
Totals 1161105.76 0.00 1266789.84 100.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12