Monthly State Let Construction Report For Houston District As Of Nov 20, 2014 Page 7 Of 10

Last Update: Thursday, November 20, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyMONTGOMERY
Highway CR
From MOUNT MARIAH AT LITTLE CANEY CREEK
To .
CSJ 0912-37-219
Proj ID BR 2011(707)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.062 454454.20 68174.50 68174.50 15.0
Work Order 08-27-14
Work Began 10-27-14
Work Completed  
Time Computed 10-26-14
Contract Working Days 62
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 3
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-37-219
HEMPHILL PILE DRIVING CO., A CORP. (6.82%)
LONESTAR TRAFFIC SAFETY, LLC (0.45%)
WILLOW CITY SIGN & RAIL, INC.(4.55%)
BATTERSON,LLP(0.34%)
WATERS CONSTRUCTION CO., INC.(1.47%)
TEXAS LAND CLEARING, INC.(1.21%)
Contract # 06143227
Totals 454454.20 68174.50 68174.50 15.0

CountyMONTGOMERY
Highway CR
From DACUS JOHNSON RD AT LAKE CREEK
To .
CSJ 0912-37-221
Proj ID BR 2012(396)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.063 1378508.86 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-06-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-37-221
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143032
Totals 1378508.86 0.00 0.00 0.0

CountyHARRIS
Highway CS
From AT BANG ELEMENTARY SCHOOL
To .
CSJ 0912-70-068
Proj ID STP 2014(745)SRS
Work Type SRTS TRAIL
 
1.473 499113.96 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-02-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-068
BATTERSON,LLP( 14.72%)
LANDPRO, INC.(4.34%)
Contract # 07143054
Totals 499113.96 0.00 0.00 0.0

CountyHARRIS
Highway VA
From BRAYS BAYOU PATH IN E HOUS(75TH ST)
To OLD SPANISH TRAIL
CSJ 0912-70-077
Proj ID STP 2011(254)TE
Work Type ENHANCEMENT PROJECT
 
2.207 1525267.27 0.00 1279286.71 83.9
Work Order 05-28-13
Work Began 07-15-13
Work Completed  
Time Computed 07-15-13
Contract Working Days 239
Addl Days Granted 0
Working Days Charged 241
Percent Time Used 100
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-077
PROFESSIONAL TRAFFIC CONTROL, LLC(1.10%)
GEORGE MEEKS LANDPRO, INC. (2.83%)
MCDONALD ELECTRIC(4.00%)
KAM CONSTRUCTION, INC. (0.32%)
REGIONAL TRAFFIC SERVICES LLC(0.20%)
Contract # 04133209
Totals 1525267.27 0.00 1279286.71 83.9

CountyHARRIS
Highway VA
From FANNIN & MN ST ESPLANADES CAMBRIDGE
To MECOM FOUNTAIN
CSJ 0912-70-078
Proj ID STP 2011(255)TE
Work Type ENHANCEMENT PROJECT
 
0.807 2581444.90 0.00 2026823.50 78.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-26-13
Work Began 10-21-13
Work Completed  
Time Computed 10-12-13
Contract Working Days 176
Addl Days Granted 32
Working Days Charged 216
Percent Time Used 103
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-078
HIGHWAY BARRICADES AND SERVICES, LLC (0.88%)
DOWN UNDER CONSTRUCTION(1.83%)
SPECIALTY DRILLING (0.02%)
BUILDER SERVICES CO. (1.50%)
LEXTEX, INC. (7.15%)
Contract # 06133013
Totals 2581444.90 0.00 2026823.50 78.7

CountyHARRIS
Highway VA
From BW 8, NORTH OF IH 10
To EAST OF SH 249
CSJ 0912-70-080
Proj ID HP 1102(309)
Work Type LANDSCAPE DEVELOPMENT
 
21.348 1437954.68 9307.20 1512241.80 100.0
Work Order 10-07-11
Work Began 11-07-11
Work Completed 10-24-14
Time Computed 10-23-11
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 100
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-080
ENVIRONMENTAL ALLIES, L.P. (0.80%)
Contract # 08113035
Totals 1437954.68 9307.20 1512241.80 100.0

CountyHARRIS
Highway VA
From BW 8, FROM HOLLISTER
To MESA
CSJ 0912-70-081
Proj ID NH 2012(345)
Work Type LANDSCAPE DEVELOPMENT
 
14.413 1200452.82 3232.00 1095094.85 91.2
Work Order 05-04-12
Work Began 11-01-12
Work Completed  
Time Computed 05-20-12
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 119
Percent Time Used 99
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-081
CONROE WOOD PRODUCTS INC.(0.93%)
CC TREE FARMS, L.L.C.(3.47%)
Contract # 03123012
Totals 1200452.82 3232.00 1095094.85 91.2

CountyHARRIS
Highway VA
From US 59
To IH 10 EAST
CSJ 0912-70-085
Proj ID HP 2013(693)
Work Type LANDSCAPE DEVELOPMENT
 
5.800 810065.64 3842.05 653413.43 80.6
Work Order 11-25-13
Work Began 02-04-14
Work Completed  
Time Computed 01-25-14
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 91
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-085
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133227
Totals 810065.64 3842.05 653413.43 80.6

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS WITHIN CENTRAL
To HOUSTON AREA
CSJ 0912-70-094
Proj ID STP 2015(317)
Work Type BRIDGE MAINTENANCE WORK
 
0.001 1698653.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 304
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-094
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143212
Totals 1698653.40 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HARRIS COUNTY
To .
CSJ 0912-70-099
Proj ID NH 2014(640)
Work Type CONST CURB RAMPS
 
0.001 2767522.72 0.00 0.00 0.0
Work Order 07-02-14
Work Began 10-27-14
Work Completed  
Time Computed 08-31-14
Contract Working Days 244
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 4
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-099
ONE WAY CONCRETE ( 11.79%)
THIRD COAST SERVICES LLC (9.66%)
STRIPE-A-LINE, INC.(2.31%)
Contract # 05143031
Totals 2767522.72 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HOUSTON
To .
CSJ 0912-71-005
Proj ID STP 2013(789)MM
Work Type TRAFFIC SIGNAL IMPROVEMENTS
 
0.001 958854.12 154.42 973349.27 99.9
Work Order 09-17-13
Work Began 01-20-14
Work Completed  
Time Computed 01-15-14
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 176
Percent Time Used 88
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-005
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08133052
Totals 958854.12 154.42 973349.27 99.9

CountyHARRIS
Highway CS
From VARIOUS LOCATION IN HARRIS COUNTY
To PRECINCT 1
CSJ 0912-71-046
Proj ID C 912-71-46
Work Type HARRIS COUNTY PRECINCT 1 RCTSS
 
0.001 4241559.87 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-28-14
Work Began 00-00-00
Work Completed  
Time Computed 11-13-14
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143027
Totals 4241559.87 0.00 0.00 0.0

CountyHARRIS
Highway VA
From BRAYS BAYOU BRIDGES AT BOB WHITE,
To ATWELL, HERMANN PARK & TIERWESTER
CSJ 0912-71-432
Proj ID STP 94(231)TE
Work Type TRANSPORTATION ENHANCEMENT
 
1.327 7458028.70 325003.52 8367322.91 99.9
Work Order 09-21-10
Work Began 11-08-10
Work Completed  
Time Computed 10-07-10
Contract Working Days 240
Addl Days Granted 148
Working Days Charged 388
Percent Time Used 100
Contractor(s)
SPAWGLASS CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-432
MARTINEZ STEEL (2.76%)
BUILDER SERVICES CO. (3.49%)
W. W. FOUNDATION DRILLING, LTD.(3.36%)
TRAF-TEX, INC. (3.11%)
STRIPES & STOPS COMPANY, INC.(0.31%)
JCF BRIDGE & CONCRETE, INC.( 10.57%)
CONSTRUCTION ECO SERVICES(0.41%)
APCON SERVICES, LLC(2.07%)
VALLEY PLACERS, LLC(0.23%)
HAYDEN PAVING, INC.(0.48%)
IRON ACCESS(0.70%)
SOUTH TEXAS PAINTING CONTRACTORS (0.41%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.77%)
SCOTT DERR PAINTING CO (0.47%)
AYG CONSTRUCTION, LTD(4.00%)
Contract # 07103255
Totals 7458028.70 325003.52 8367322.91 99.9

CountyHARRIS
Highway VA
From BUFFALO BAYOU TRAIL: FROM SHEPHERD
To SABINE
CSJ 0912-71-503
Proj ID CM 96(730)
Work Type HIKE AND BIKE TRAIL
 
4.637 4586473.80 -8759.16 4384013.34 95.5
Work Order 10-19-11
Work Began 11-14-11
Work Completed  
Time Computed 11-04-11
Contract Working Days 225
Addl Days Granted 134
Working Days Charged 356
Percent Time Used 99
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-503
LANDPRO, INC.(5.64%)
KOSSMAN CONTRACTING CO., INC.(2.68%)
ENVIRONMENTAL ALLIES, L.P. (0.81%)
REPUBLIC TRAFFIC SAFETY, INC.(0.20%)
PFEIFFER & SON LTD.( 11.76%)
HIGHWAY TECHNOLOGIES, INC. (1.07%)
DIAMOND J DRILLING (2.55%)
VALLEY PLACERS, LLC(0.41%)
SCOTT DERR PAINTING CO (0.02%)
CARMA CONSTRUCTION, LLC(3.36%)
AGGREGATE TECHNOLOGIES, INC. (0.72%)
YORK & YORK FOUNDATION DRILLING, INC.(2.55%)
ASSOCIATED STEEL FABRICATORS, INC. (0.02%)
X-RAIN IRRIGATION(0.08%)
Contract # 08113043
Totals 4586473.80 8759.16 4384013.34 95.5

CountyHARRIS
Highway VA
From KEEGANS BAYOU TRAIL: GESSNER
To KIRKWOOD
CSJ 0912-71-631
Proj ID CM 99(567)
Work Type HIKE AND BIKE TRAIL
 
4.034 5688316.22 131830.05 3451067.96 60.6
Work Order 10-18-12
Work Began 09-16-13
Work Completed  
Time Computed 01-16-13
Contract Working Days 368
Addl Days Granted 0
Working Days Charged 219
Percent Time Used 59
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-631
CARMA CONSTRUCTION, LLC( 16.32%)
HIGHWAY TECHNOLOGIES, INC. (0.18%)
REGIONAL TRAFFIC SERVICES LLC(0.15%)
THIRD COAST SERVICES LLC (3.37%)
GEORGE MEEKS LANDPRO, INC. (4.04%)
SPECIALTY DRILLING, LTD. (0.53%)
ENVIRONMENTAL ALLIES, L.P. (0.94%)
Contract # 08123008
Totals 5688316.22 131830.05 3451067.96 60.6

CountyHARRIS
Highway CS
From ON SOUTH SHAVER FROM GULF FRWY
To SH 3
CSJ 0912-71-688
Proj ID STP 99(751)MM
Work Type WIDEN TO 6 LANE DIVIDED
 
1.138 13480682.20 181988.21 8818628.18 65.4
Work Order 04-23-13
Work Began 06-24-13
Work Completed  
Time Computed 06-22-13
Contract Working Days 404
Addl Days Granted 0
Working Days Charged 253
Percent Time Used 62
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-688
CPAVE, INC.(0.54%)
WILLOW CITY SIGN & RAIL, INC.(0.17%)
INDUS CONSTRUCTION, L.P. (0.73%)
APCON SERVICES, LLC(6.16%)
GMJ PAVING CO. (5.12%)
THIRD COAST SERVICES LLC (1.85%)
EAGLE CONSTRUCTION AND ENVIRONMENTAL SERVICES, L.P.(0.70%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (1.01%)
DUSTROL, INC.(0.54%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(0.03%)
STRIPES & STOPS COMPANY, INC.(0.97%)
ENVIRONMENTAL ALLIES, L.P. (0.30%)
H & E AGGREGATE, LLC (2.77%)
MCNORTON DEWATERING, INC.(0.06%)
FIRST KATY CONSTRUCTION(1.32%)
MICKIE SERVICE, INC. (0.03%)
Contract # 02133203
Totals 13480682.20 181988.21 8818628.18 65.4

CountyHARRIS
Highway CR
From KNOBCREST DRIVE TO GREENS ROAD
To AND IMPERIAL VALLEY TO BRADFIELD RD
CSJ 0912-71-797
Proj ID STP 2002(149)TE
Work Type 10' WIDE CONCRETE TRAIL
 
2.181 1424412.72 292629.94 673924.37 47.3
Work Order 04-22-14
Work Began 07-21-14
Work Completed  
Time Computed 06-21-14
Contract Working Days 89
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 71
Contractor(s)
MENADE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-797
JE CASEY, LLC(5.00%)
DAVID GALA DBA GALAXY FENCE(1.10%)
YORK & YORK FOUNDATION DRILLING, INC.(0.98%)
BFL DEVELOPMENT, INC.(8.84%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(2.01%)
MANNA CONCRETE WORKS (3.79%)
KINGWOOD ADVANCED SOLUTIONS(1.40%)
Contract # 02143218
Totals 1424412.72 292629.94 673924.37 47.3

CountyHARRIS
Highway CR
From BEAMER RD; W OF TALL SHIPS LN
To WEST BAY AREA BOULEVARD
CSJ 0912-71-894
Proj ID C 912-71-894
Work Type CONSTRUCT 4 - LANE BOULEVARD
 
1.343 10341416.18 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-894
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143225
Totals 10341416.18 0.00 0.00 0.0

CountyHARRIS
Highway CR
From W GREENS RD FRM SH249(700'W HCFCD)
To CUTTEN RD
CSJ 0912-71-895
Proj ID STP 2011(696)MM
Work Type CONS 4 LN CONC DIV SEC W / CURB & GTR
 
0.665 7580928.84 1120.00 7738938.70 99.9
CountyHARRIS
Highway CR
From W GREENS RD FRM SH249(700'W HCFCD)
To CUTTEN RD
CSJ 0912-72-297
Proj ID CC 912-72-297
Work Type ROW UTL. ADJ.
 
0.665 205062.00 0.00 263208.22 99.9
Work Order 01-04-13
Work Began 02-08-13
Work Completed  
Time Computed 01-20-13
Contract Working Days 261
Addl Days Granted 0
Working Days Charged 258
Percent Time Used 98
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-895
ROADSAFE TRAFFIC SYSTEMS, INC. (0.31%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.78%)
THIRD COAST SERVICES LLC (1.66%)
THE ANCHOR GROUP, INC. (0.34%)
ROSALES TRUCKING (1.32%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.06%)
ARANDA BROTHERS CONSTRUCTION, INC. (1.08%)
ENVIRONMENTAL ALLIES, L.P. (0.35%)
INDUS CONSTRUCTION, L.P. (6.50%)
DOUBLE OAK CONSTRUCTION, INC.(0.43%)
EROSION CONTROL, INC.(0.47%)
CHAPA"S CONSTRUCTION (0.47%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.14%)
SCOTT DERR PAINTING CO (0.14%)
PRIMATE CONSTRUCTION, INC. (0.10%)
Contract # 11123004
Totals 7785990.84 1120.00 8002146.92 99.9

CountyHARRIS
Highway CR
From HOUSE-HAHL RD AT BIG CYPRESS CREEK
To .
CSJ 0912-72-061
Proj ID BR 2006(446)
Work Type REPLACE BRIDGE
 
0.123 736542.36 119049.10 698093.17 96.7
Work Order 09-23-13
Work Began 05-09-14
Work Completed  
Time Computed 11-22-13
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 110
Percent Time Used 127
Contractor(s)
TOM-MAC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-061
GMJ PAVING CO. (8.97%)
KOSSMAN CONTRACTING CO., INC.(2.66%)
STRIPES & STOPS COMPANY, INC.(1.08%)
FIRST KATY CONSTRUCTION(1.90%)
FORDE CONSTRUCTION COMPANY, INC. (9.93%)
Contract # 08133228
Totals 736542.36 119049.10 698093.17 96.7

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10