Monthly State Let Construction Report For Houston District As Of Jan 13, 2015 Page 7 Of 11

Last Update: Tuesday, January 13, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyFORT BEND
Highway CS
From TRAMMEL FRESNO RD, FORT BEND PKWY
To FM 521
CSJ 0912-34-144
Proj ID STP 2010(596)MM
Work Type GR, STR, BASE AND 0AVE
 
3.041 20864455.45 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 622
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-144
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143003
Totals 20864455.45 0.00 0.00 0.0

CountyFORT BEND
Highway CR
From WALKER ROAD AT TURKEY CREEK
To .
CSJ 0912-34-159
Proj ID BR 2011(853)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.060 395576.27 0.00 390339.47 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-13-13
Work Began 12-05-13
Work Completed 10-01-14
Time Computed 12-05-13
Contract Working Days 133
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 90
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-159
CENTERLINE TRAFFIC SAFETY, LLC (1.06%)
REGIONAL TRAFFIC SERVICES LLC(1.28%)
A-1 EROSION CONTROL, LLC (1.23%)
KOSSMAN CONTRACTING CO., INC.(0.63%)
JMHP, INC. (2.94%)
GARNER PAVING & CONSTRUCTION, LTD. (1.25%)
LONESTAR TRAFFIC SAFETY, LLC (1.06%)
Contract # 10133009
Totals 395576.27 0.00 390339.47 100.0

CountyFORT BEND
Highway CR
From FOSTER SCHOOL @ FAIRCHILDS CRK TRIB
To .
CSJ 0912-34-169
Proj ID BR 2011(989)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.130 978105.55 92449.90 960037.81 98.1
Work Order 03-03-14
Work Began 05-09-14
Work Completed  
Time Computed 05-02-14
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 115
Percent Time Used 95
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-169
REGIONAL TRAFFIC SERVICES LLC(1.90%)
LONESTAR TRAFFIC SAFETY, LLC (1.86%)
ODUM SERVICES, L.P.(4.16%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.38%)
ENVIRONMENTAL ALLIES, L.P. (0.49%)
GARNER CONSTRUCTION CO.(0.42%)
EROSION PREVENTION PRODUCTS(7.46%)
Contract # 01143222
Totals 978105.55 92449.90 960037.81 98.1

CountyFORT BEND
Highway CS
From STAFFORDSHIRE ROAD; 5TH ST
To SCANLIN/LEXINGTON RD
CSJ 0912-34-178
Proj ID STP 2012(734)MM
Work Type GR, STRS, BASE PV W / CURB & GUTTER
 
0.611 3589100.64 21806.18 3596745.78 99.9
Work Order 08-19-13
Work Began 11-16-13
Work Completed  
Time Computed 10-18-13
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 170
Percent Time Used 96
Contractor(s)
HASSELL CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-178
GMJ PAVING CO. (4.70%)
BREDA COMPANY, INC.(3.58%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.29%)
TRAF-TEX, INC. (0.31%)
CPAVE, INC.(0.65%)
EMBARK TREE AND LANDSCAPE SERVICES (0.24%)
CHERRY CONCRETE REMOVAL(0.03%)
CURB PLANET INC. (0.11%)
BATTERSON,LLP(1.63%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.05%)
Contract # 05133213
Totals 3589100.64 21806.18 3596745.78 99.9

CountyMONTGOMERY
Highway CR
From KUYKENDAHL RD; ALDEN BRIDGE
To CROWNRIDGE DR
CSJ 0912-37-140
Proj ID STP 2002(643)UM
Work Type CONST 2 LANE RDWY
 
0.485 2496548.44 237318.40 1093757.95 43.8
Work Order 06-30-14
Work Began 09-02-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 78
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 76
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0912-37-140
ABC EROSION CONTROL, INC.(0.66%)
LANDSCAPING CONTRACTING & IRRIGATION (1.93%)
STRIPE-A-LINE, INC.(0.21%)
THIRD COAST SERVICES LLC ( 10.75%)
W. W. FOUNDATION DRILLING, LTD.(4.79%)
EAGLE CONSTRUCTION AND ENVIRONMENTAL SERVICES, L.P.(1.21%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.33%)
BREDA COMPANY, INC.(0.70%)
MESA ROD BUSTERS, INC. (0.18%)
HOUSTON SAWING & DRILLING(0.07%)
WILLOW CITY SIGN & RAIL, INC.(0.82%)
APCON SERVICES, LLC(0.73%)
SAND HILL FOUNDATION, LLC(1.21%)
Contract # 05143027
Totals 2496548.44 237318.40 1093757.95 43.8

CountyMONTGOMERY
Highway CS
From WOODLANDS PKWY, E OF PANTHER CRK DR
To GROGAN'S MILL RD
CSJ 0912-37-199
Proj ID STP 2010(831)MM
Work Type GR, STRS, BASE AND PAVE
 
0.895 2836771.40 -19625.00 2160569.35 81.8
Work Order 10-24-12
Work Began 11-26-12
Work Completed  
Time Computed 11-09-12
Contract Working Days 246
Addl Days Granted 0
Working Days Charged 488
Percent Time Used 198
Contractor(s)
MENADE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-37-199
W. W. FOUNDATION DRILLING, LTD.(3.75%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.86%)
HIGHWAY TECHNOLOGIES, INC. (1.42%)
A BROTHERS MILLING, LLC(0.90%)
CURB PLANET INC. (0.10%)
YORK & YORK FOUNDATION DRILLING, INC.(1.50%)
DAVID GALA DBA GALAXY FENCE(0.54%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.35%)
MESA ROD BUSTERS, INC. (0.14%)
WILLOW CITY SIGN & RAIL, INC.(0.89%)
PROFESSIONAL TRAFFIC CONTROL, LLC(1.06%)
HODGES BROTHERS, INC.(0.43%)
CENTRAL CONSTRUCTION SERVICES, INC.(0.22%)
EROSION ABATEMENT, LLC (7.22%)
TREVINO INDUSTRIES, INC. (0.26%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.99%)
TEXAS STERLING CONSTRUCTION CO.( 28.17%)
EROSION PREVENTION PRODUCTS(3.94%)
WILLOW CITY SIGN & RAIL, INC.(0.33%)
PROFESSIONAL TRAFFIC CONTROL, LLC(0.24%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.15%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.50%)
Contract # 08123031
Totals 2836771.40 19625.00 2160569.35 81.8

CountyMONTGOMERY
Highway CR
From MOUNT MARIAH AT LITTLE CANEY CREEK
To .
CSJ 0912-37-219
Proj ID BR 2011(707)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.062 454454.20 112567.50 273981.50 60.2
Work Order 08-27-14
Work Began 10-27-14
Work Completed  
Time Computed 10-26-14
Contract Working Days 62
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 48
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-37-219
HEMPHILL PILE DRIVING CO., A CORP. (6.82%)
LONESTAR TRAFFIC SAFETY, LLC (0.45%)
WILLOW CITY SIGN & RAIL, INC.(4.55%)
BATTERSON,LLP(0.34%)
WATERS CONSTRUCTION CO., INC.(1.47%)
TEXAS LAND CLEARING, INC.(1.21%)
Contract # 06143227
Totals 454454.20 112567.50 273981.50 60.2

CountyMONTGOMERY
Highway CR
From DACUS JOHNSON RD AT LAKE CREEK
To .
CSJ 0912-37-221
Proj ID BR 2012(396)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.063 1378508.86 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-06-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-37-221
WILLOW CITY SIGN & RAIL, INC.(2.80%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.66%)
Contract # 09143032
Totals 1378508.86 0.00 0.00 0.0

CountyHARRIS
Highway CS
From AT BANG ELEMENTARY SCHOOL
To .
CSJ 0912-70-068
Proj ID STP 2014(745)SRS
Work Type SRTS TRAIL
 
1.473 499113.96 71961.93 71961.93 14.4
Work Order 10-02-14
Work Began 12-01-14
Work Completed  
Time Computed 12-01-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 20
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-068
BATTERSON,LLP( 14.72%)
LANDPRO, INC.(4.34%)
Contract # 07143054
Totals 499113.96 71961.93 71961.93 14.4

CountyHARRIS
Highway VA
From BRAYS BAYOU PATH IN E HOUS(75TH ST)
To OLD SPANISH TRAIL
CSJ 0912-70-077
Proj ID STP 2011(254)TE
Work Type ENHANCEMENT PROJECT
 
2.207 1525267.27 11285.00 1290571.71 84.7
Work Order 05-28-13
Work Began 07-15-13
Work Completed  
Time Computed 07-15-13
Contract Working Days 239
Addl Days Granted 0
Working Days Charged 241
Percent Time Used 100
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-077
PROFESSIONAL TRAFFIC CONTROL, LLC(1.10%)
GEORGE MEEKS LANDPRO, INC. (2.83%)
MCDONALD ELECTRIC(4.00%)
KAM CONSTRUCTION, INC. (0.32%)
REGIONAL TRAFFIC SERVICES LLC(0.20%)
Contract # 04133209
Totals 1525267.27 11285.00 1290571.71 84.7

CountyHARRIS
Highway VA
From FANNIN & MN ST ESPLANADES CAMBRIDGE
To MECOM FOUNTAIN
CSJ 0912-70-078
Proj ID STP 2011(255)TE
Work Type ENHANCEMENT PROJECT
 
0.807 2581444.90 0.00 2026823.50 78.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-26-13
Work Began 10-21-13
Work Completed  
Time Computed 10-12-13
Contract Working Days 176
Addl Days Granted 32
Working Days Charged 216
Percent Time Used 103
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-078
HIGHWAY BARRICADES AND SERVICES, LLC (0.88%)
DOWN UNDER CONSTRUCTION(1.83%)
SPECIALTY DRILLING (0.02%)
BUILDER SERVICES CO. (1.50%)
LEXTEX, INC. (7.15%)
Contract # 06133013
Totals 2581444.90 0.00 2026823.50 78.7

CountyHARRIS
Highway VA
From BW 8, NORTH OF IH 10
To EAST OF SH 249
CSJ 0912-70-080
Proj ID HP 1102(309)
Work Type LANDSCAPE DEVELOPMENT
 
21.348 1437954.68 3988.80 1516230.60 100.0
Work Order 10-07-11
Work Began 11-07-11
Work Completed 10-24-14
Time Computed 10-23-11
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 100
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-080
ENVIRONMENTAL ALLIES, L.P. (0.80%)
Contract # 08113035
Totals 1437954.68 3988.80 1516230.60 100.0

CountyHARRIS
Highway VA
From BW 8, FROM HOLLISTER
To MESA
CSJ 0912-70-081
Proj ID NH 2012(345)
Work Type LANDSCAPE DEVELOPMENT
 
14.413 1200452.82 3232.00 1101558.85 91.7
Work Order 05-04-12
Work Began 11-01-12
Work Completed  
Time Computed 05-20-12
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 119
Percent Time Used 99
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-081
CONROE WOOD PRODUCTS INC.(0.93%)
CC TREE FARMS, L.L.C.(3.47%)
Contract # 03123012
Totals 1200452.82 3232.00 1101558.85 91.7

CountyHARRIS
Highway VA
From US 59
To IH 10 EAST
CSJ 0912-70-085
Proj ID HP 2013(693)
Work Type LANDSCAPE DEVELOPMENT
 
5.800 810065.64 3842.05 661097.53 81.6
Work Order 11-25-13
Work Began 02-04-14
Work Completed  
Time Computed 01-25-14
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 91
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-085
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133227
Totals 810065.64 3842.05 661097.53 81.6

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS WITHIN CENTRAL
To HOUSTON AREA
CSJ 0912-70-094
Proj ID STP 2015(317)
Work Type BRIDGE MAINTENANCE WORK
 
0.001 1698653.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-02-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 304
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-094
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143212
Totals 1698653.40 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HARRIS COUNTY
To .
CSJ 0912-70-099
Proj ID NH 2014(640)
Work Type CONST CURB RAMPS
 
0.001 2767522.72 119882.00 294407.51 10.6
Work Order 07-02-14
Work Began 10-27-14
Work Completed  
Time Computed 08-31-14
Contract Working Days 244
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 18
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-099
ONE WAY CONCRETE ( 11.79%)
THIRD COAST SERVICES LLC (9.66%)
STRIPE-A-LINE, INC.(2.31%)
AAA TREASURE INTERNATIONAL COMPANY, INC. (6.44%)
GLOBE ELECTRIC SUPPLY COMPANY, INC.(2.65%)
GEORGE MEEKS LANDPRO, INC. (3.02%)
Contract # 05143031
Totals 2767522.72 119882.00 294407.51 10.6

CountyHARRIS
Highway CS
From CAROLINE STREET;ELGIN STREET
To PIERCE STREET
CSJ 0912-71-003
Proj ID C 912-71-3
Work Type GR, STRS, BASE
 
0.689 13919000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 360
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-003
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153004
Totals 13919000.00 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HOUSTON
To .
CSJ 0912-71-005
Proj ID STP 2013(789)MM
Work Type TRAFFIC SIGNAL IMPROVEMENTS
 
0.001 958854.12 0.00 978865.31 99.9
Work Order 09-17-13
Work Began 01-20-14
Work Completed  
Time Computed 01-15-14
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 176
Percent Time Used 88
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-005
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08133052
Totals 958854.12 0.00 978865.31 99.9

CountyHARRIS
Highway CS
From VARIOUS LOCATION IN HARRIS COUNTY
To PRECINCT 1
CSJ 0912-71-046
Proj ID C 912-71-46
Work Type HARRIS COUNTY PRECINCT 1 RCTSS
 
0.001 4241559.87 0.00 0.00 0.0
Work Order 10-28-14
Work Began 00-00-00
Work Completed  
Time Computed 11-13-14
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143027
Totals 4241559.87 0.00 0.00 0.0

CountyHARRIS
Highway VA
From BRAYS BAYOU BRIDGES AT BOB WHITE,
To ATWELL, HERMANN PARK & TIERWESTER
CSJ 0912-71-432
Proj ID STP 94(231)TE
Work Type TRANSPORTATION ENHANCEMENT
 
1.327 7458028.70 23800.00 8397135.71 100.0
Work Order 09-21-10
Work Began 11-08-10
Work Completed 11-24-14
Time Computed 10-07-10
Contract Working Days 240
Addl Days Granted 148
Working Days Charged 388
Percent Time Used 100
Contractor(s)
SPAWGLASS CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-432
MARTINEZ STEEL (2.76%)
BUILDER SERVICES CO. (3.49%)
W. W. FOUNDATION DRILLING, LTD.(3.36%)
TRAF-TEX, INC. (3.11%)
STRIPES & STOPS COMPANY, INC.(0.31%)
JCF BRIDGE & CONCRETE, INC.( 10.57%)
CONSTRUCTION ECO SERVICES(0.41%)
APCON SERVICES, LLC(2.07%)
VALLEY PLACERS, LLC(0.23%)
HAYDEN PAVING, INC.(0.48%)
IRON ACCESS(0.70%)
SOUTH TEXAS PAINTING CONTRACTORS (0.41%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.77%)
SCOTT DERR PAINTING CO (0.47%)
AYG CONSTRUCTION, LTD(4.00%)
Contract # 07103255
Totals 7458028.70 23800.00 8397135.71 100.0