Monthly State Let Construction Report For Houston District As Of Apr 10, 2015 Page 9 Of 11

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRIS
Highway CS
From ALDINE WESTFIELD AT HCFCD DITCH
To .
CSJ 0912-72-229
Proj ID BR 1102(481)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.069 600781.75 0.00 619251.32 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-04-13
Work Began 11-18-13
Work Completed 11-21-14
Time Computed 11-03-13
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 102
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-229
ROADSAFE TRAFFIC SYSTEMS, INC. (1.02%)
Contract # 07133017
Totals 600781.75 0.00 619251.32 100.0

CountyHARRIS
Highway CS
From MEMORIAL DR AT DRAINAGE DITCH
To .
CSJ 0912-72-285
Proj ID BR 2012(397)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.001 548724.86 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-03-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
3I CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-285
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153015
Totals 548724.86 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS
To US 59,US 90A,IH 610,SH 225 ETCETERA
CSJ 0912-72-287
Proj ID STP 2012(515)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2475888.05 0.00 2077240.43 85.0
Work Order 07-25-12
Work Began 10-18-12
Work Completed  
Time Computed 08-10-12
Contract Working Days 225
Addl Days Granted 48
Working Days Charged 310
Percent Time Used 113
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-287
THIRD COAST SERVICES LLC ( 10.39%)
PROFESSIONAL TRAFFIC CONTROL, LLC(5.01%)
AQUALAWN HYDROMULCH & EROSION CONTROL(1.27%)
Contract # 05123225
Totals 2475888.05 0.00 2077240.43 85.0

CountyHARRIS
Highway VA
From AT VARIOUS LOCATIONS ALONG IH 45
To AT SH 288 IN HARRIS COUNTY
CSJ 0912-72-288
Proj ID STP 2013(460)
Work Type CONSTRUCT CURB RAMPS
 
0.001 1189354.45 0.00 1200488.34 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-03-13
Work Began 08-12-13
Work Completed  
Time Computed 06-19-13
Contract Working Days 195
Addl Days Granted 0
Working Days Charged 195
Percent Time Used 100
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-288
PROFESSIONAL TRAFFIC CONTROL, LLC(4.72%)
THIRD COAST SERVICES LLC (5.32%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (1.27%)
Contract # 03133217
Totals 1189354.45 0.00 1200488.34 99.9

CountyGALVESTON
Highway CS
From SEAWOLF PKWY AT PELICAN ISLAND CHNL
To .
CSJ 0912-73-117
Proj ID BR 2007(366)
Work Type REHABILITATE BRIDGE
 
0.612 3439504.50 0.00 8422544.83 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-18-11
Work Began 08-03-11
Work Completed 12-09-14
Time Computed 06-03-11
Contract Working Days 301
Addl Days Granted 396
Working Days Charged 629
Percent Time Used 90
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-117
ORION CONSTRUCTION, L.P. (6.38%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.30%)
INTECH CONTRACTING LLC ( 74.13%)
BRIDGES R US PAINTING CO., INC.( 36.05%)
TIME MARINE, INC.(130.15%)
GENERAL METAL FABRICATING, INC.( 38.58%)
Contract # 04113207
Totals 3439504.50 0.00 8422544.83 100.0

CountyGALVESTON
Highway CR
From FRENCHTOWN RD AT HORSESHOE LAKE
To .
CSJ 0912-73-151
Proj ID BR 2010(780)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.059 686707.00 59310.08 494753.86 72.0
Work Order 09-11-14
Work Began 12-02-14
Work Completed  
Time Computed 12-02-14
Contract Working Days 96
Addl Days Granted 0
Working Days Charged 69
Percent Time Used 71
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-151
REGIONAL TRAFFIC SERVICES LLC(0.25%)
LONESTAR TRAFFIC SAFETY, LLC (0.43%)
JMHP, INC. (3.85%)
ENVIRONMENTAL ALLIES, L.P. (0.96%)
JUST GROOVING, LTD.(0.23%)
Contract # 06143046
Totals 686707.00 59310.08 494753.86 72.0

CountyGALVESTON
Highway VA
From VARIOUS LOCATIONS
To IN GALVESTON COUNTY
CSJ 0912-73-180
Proj ID STP 1102(311)
Work Type CONSTRUCT CURB RAMPS
 
3.842 3284825.97 0.00 2720205.55 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-21-11
Work Began 11-06-11
Work Completed 12-01-14
Time Computed 11-06-11
Contract Working Days 254
Addl Days Granted 0
Working Days Charged 361
Percent Time Used 142
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-180
THIRD COAST SERVICES, LLC( 11.29%)
WORK ZONE PRODUCTS, INC. (5.46%)
KOSSMAN CONTRACTING COMPANY(1.91%)
SUPERIOR LIGHTING(0.43%)
Contract # 08113036
Totals 3284825.97 0.00 2720205.55 100.0

CountyGALVESTON
Highway VA
From AT GALVESTON FERRY OFFICE
To .
CSJ 0912-73-189
Proj ID FT 912-73-189
Work Type REHAB BILGE WATER TREATMENT SYSTEMS
 
0.001 629425.00 125764.70 564648.77 92.0
Work Order 04-02-14
Work Began 04-24-14
Work Completed  
Time Computed 04-18-14
Contract Working Days 120
Addl Days Granted 49
Working Days Charged 193
Percent Time Used 114
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-189
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01143202
Totals 629425.00 125764.70 564648.77 92.0

CountyGALVESTON
Highway VA
From AT GALVESTON FERRY OFFICE
To .
CSJ 0912-73-190
Proj ID C 912-73-190
Work Type RENOVATION OF SHOP RESTROOMS
 
0.001 357800.00 0.00 410494.51 99.9
Work Order 05-12-14
Work Began 05-19-14
Work Completed  
Time Computed 05-28-14
Contract Working Days 120
Addl Days Granted 72
Working Days Charged 202
Percent Time Used 105
Contractor(s)
J.C. LEWIS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-190
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143232
Totals 357800.00 0.00 410494.51 99.9

CountyGALVESTON
Highway VA
From AT THE GALVESTON FERRY LANDING
To .
CSJ 0912-73-193
Proj ID FT 912-73-193
Work Type CONSTRUCT NEW BOAT LIFT
 
0.001 305695.00 0.00 276803.72 91.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-08-14
Work Began 08-13-14
Work Completed  
Time Computed 05-24-14
Contract Working Days 120
Addl Days Granted 37
Working Days Charged 164
Percent Time Used 104
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-193
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143230
Totals 305695.00 0.00 276803.72 91.9

CountyGALVESTON
Highway VA
From AT GALV AND BOLIVAR FERRY LANDING
To .
CSJ 0912-73-194
Proj ID C 912-73-194
Work Type CONSTRUCT NEW SCREENING CANOPIES
 
0.001 731490.00 225415.31 679045.30 97.0
Work Order 05-08-14
Work Began 05-27-14
Work Completed  
Time Computed 05-24-14
Contract Working Days 120
Addl Days Granted 11
Working Days Charged 181
Percent Time Used 138
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-194
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143231
Totals 731490.00 225415.31 679045.30 97.0

CountyHARRIS
Highway FM 865
From ALMEDA-GENOA
To BW 8
CSJ 0976-01-019
Proj ID C 976-1-19
Work Type GR, BS & SURF
 
1.272 13285921.44 0.00 585927.83 4.4
Work Order 02-12-14
Work Began 00-00-00
Work Completed  
Time Computed 11-09-14
Contract Working Days 305
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0976-01-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11133025
Totals 13285921.44 0.00 585927.83 4.4

CountyGALVESTON
Highway FM 518
From BAY AREA BLVD
To FM 2094
CSJ 0976-03-100
Proj ID C 976-3-100
Work Type ACCESS MANAGEMENT IMPROVEMENTS
 
0.668 1295137.47 1000.00 1279248.55 99.9
Work Order 12-03-13
Work Began 02-12-14
Work Completed  
Time Computed 02-01-14
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 189
Percent Time Used 248
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0976-03-100
TRAFFIC SYSTEMS CONSTRUCTION, INC. ( 25.48%)
ROADSAFE TRAFFIC SYSTEMS, INC. (3.48%)
AGGREGATE TECHNOLOGIES, INC. (1.99%)
SPEEDY PAVING(1.62%)
Contract # 08133223
Totals 1295137.47 1000.00 1279248.55 99.9

CountyGALVESTON
Highway FM 646
From GRAND AVE
To FM 517
CSJ 0978-02-054
Proj ID STP 2007(404)
Work Type INST CULV, ADJ DRWAYS & RESTORE DRNG
 
3.700 5827858.98 174731.74 528393.12 9.0
Work Order 12-10-14
Work Began 02-12-15
Work Completed  
Time Computed 02-12-15
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 20
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0978-02-054
BATTERSON,LLP(0.06%)
TEXAS DRAINAGE INC.(0.91%)
GEORGE MEEKS LANDPRO, INC. (7.34%)
LONE STAR TRAFFIC SERVICE, INC.(0.20%)
Contract # 07143223
Totals 5827858.98 174731.74 528393.12 9.0

CountyGALVESTON
Highway FM 517
From AT FM 3436
To .
CSJ 0978-02-069
Proj ID STP 2014(570)HES
Work Type INST INTERSECTION FLASHING BEACON
 
0.404 246122.55 48345.24 223737.84 90.9
Work Order 06-05-14
Work Began 01-05-15
Work Completed  
Time Computed 12-02-14
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 58
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0978-02-069
ISI CONTRACTING, INC.( 17.44%)
STRIPES & STOPS COMPANY, INC.(1.45%)
Contract # 04143029
Totals 246122.55 48345.24 223737.84 90.9

CountyGALVESTON
Highway FM 517
From AT FM 146
To .
CSJ 0978-02-071
Proj ID STP 2014(035)HES
Work Type TS IMPRVMT & LT TN LN
 
0.537 959632.80 235536.70 670109.45 69.8
Work Order 11-22-13
Work Began 11-24-14
Work Completed  
Time Computed 12-08-13
Contract Working Days 45
Addl Days Granted 10
Working Days Charged 46
Percent Time Used 83
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0978-02-071
LONE STAR TRAFFIC SERVICE, INC.(0.28%)
REGIONAL TRAFFIC SERVICES LLC(3.73%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. ( 18.99%)
Contract # 09133220
Totals 959632.80 235536.70 670109.45 69.8

CountyBRAZORIA
Highway FM 523
From SH 35
To FM 2004
CSJ 1003-01-091
Proj ID STP 2015(540)
Work Type OCST, RBL AND ACP O / L
 
16.942 7475838.93 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 112
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 1003-01-091
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153004
Totals 7475838.93 0.00 0.00 0.0

CountyHARRIS
Highway FM 529
From FREEMAN ROAD
To W OF FRY ROAD
CSJ 1006-01-059
Proj ID NH 2012(474)
Work Type GR, STRS, BASE AND SURF
 
1.184 7690213.53 92192.05 6547793.62 85.1
Work Order 01-31-13
Work Began 03-15-13
Work Completed  
Time Computed 02-16-13
Contract Working Days 322
Addl Days Granted 0
Working Days Charged 293
Percent Time Used 90
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 1006-01-059
HIGHWAY TECHNOLOGIES, INC. (0.79%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.96%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.42%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.77%)
ROSALES TRUCKING (1.50%)
BATTERSON,LLP(0.97%)
DURWOOD GREENE CONSTRUCTION CO.(7.49%)
EL DORADO PAVING COMPANY, INC. (0.49%)
TEX OP CONSTRUCTION, LP(1.02%)
CPAV SPECIALTIES, LP (0.60%)
INDUS CONSTRUCTION, L.P. (2.66%)
MASTER CURB, LLC (0.10%)
DNA TRUCKING, INC. (0.93%)
Contract # 10123217
Totals 7690213.53 92192.05 6547793.62 85.1

CountyHARRIS
Highway FM 2100
From FM 1960 (GUY ROAD)
To 0.066 M. S OF HUFFMAN-CLEVELAND RD
CSJ 1062-02-023
Proj ID STP 2013(696)
Work Type MILL & ACP OVERLAY
 
12.426 5966662.66 114311.61 5797469.00 97.3
Work Order 07-31-13
Work Began 09-24-13
Work Completed  
Time Computed 09-24-13
Contract Working Days 186
Addl Days Granted 3
Working Days Charged 198
Percent Time Used 104
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1062-02-023
SIEMENS INDUSTRY, INC. (1.83%)
PROFESSIONAL TRAFFIC CONTROL, LLC(3.07%)
WILLOW CITY SIGN & RAIL, INC.(1.34%)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC(2.08%)
SOUTHWEST SIGNAL SUPPLY, INC.(0.35%)
CURB PLANET INC. (0.99%)
Contract # 05133003
Totals 5966662.66 114311.61 5797469.00 97.3

CountyHARRIS
Highway FM 2100
From DIAMONDHEAD BLVD.
To 0.14 MI S. OF FIRST STREET
CSJ 1062-04-047
Proj ID STP 2010(903)RGS
Work Type CONST RR GRADE SEPARATION STR & APP
 
0.870 8537094.26 0.00 11416707.71 100.0
CountyHARRIS
Highway FM 2100
From DIAMONDHEAD BLVD.
To 0.14 MILE SOUTH OF FIRST STREET
CSJ 1062-04-051
Proj ID STP 2011(543)ES
Work Type UTILITY ADJUSTMENT
 
0.870 335846.50 0.00 575841.86 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-01-10
Work Began 11-28-11
Work Completed 11-21-14
Time Computed 09-17-10
Contract Working Days 455
Addl Days Granted 101
Working Days Charged 556
Percent Time Used 100
Contractor(s)
NBG CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1062-04-047
ALLSTATE SIGNAL & CONSTRUCTION, LLC(2.70%)
BATTERSON,LLP(0.79%)
HASSELL CONSTRUCTION COMPANY, INC. ( 48.33%)
HOUSTON SAWING & DRILLING(0.09%)
JTB SERVICES (0.33%)
KOSSMAN CONTRACTING CO., INC.(0.23%)
REPUBLIC TRAFFIC SAFETY, INC.(0.43%)
SCOTT DERR PAINTING CO, LLC(0.26%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(2.70%)
MICKIE SERVICE, INC. (0.10%)
SAN JACINTO BORING & TUNNELING, INC. (0.23%)
SOUTHERN CRUSHED CONCRETE LLC(0.31%)
PM CONSTRUCTION & REHAB, LLC (1.62%)
JMHP, INC. (0.52%)
GMJ PAVING CO. (3.78%)
BREDA COMPANY, INC.(0.61%)
H & H CURB COMPANY (0.09%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.31%)
ENVIRONMENTAL ALLIES, L.P. (0.24%)
DORAN STEEL, INC.(0.18%)
LOPEZ UTILITIES, LLC (0.23%)
R & A BORING COMPANY (0.30%)
Contract # 07103015
Totals 8872940.76 0.00 11992549.57 100.0