Monthly State Let Construction Report For Houston District As Of Jan 13, 2015 Page 9 Of 11

Last Update: Tuesday, January 13, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGALVESTON
Highway VA
From VARIOUS LOCATIONS
To IN GALVESTON COUNTY
CSJ 0912-73-180
Proj ID STP 1102(311)
Work Type CONSTRUCT CURB RAMPS
 
3.842 3284825.97 7000.00 2720205.55 100.0
Work Order 10-21-11
Work Began 11-06-11
Work Completed 12-01-14
Time Computed 11-06-11
Contract Working Days 254
Addl Days Granted 0
Working Days Charged 361
Percent Time Used 142
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-180
THIRD COAST SERVICES, LLC( 11.29%)
WORK ZONE PRODUCTS, INC. (5.46%)
KOSSMAN CONTRACTING COMPANY(1.91%)
SUPERIOR LIGHTING(0.43%)
Contract # 08113036
Totals 3284825.97 7000.00 2720205.55 100.0

CountyGALVESTON
Highway VA
From AT GALVESTON FERRY OFFICE
To .
CSJ 0912-73-189
Proj ID FT 912-73-189
Work Type REHAB BILGE WATER TREATMENT SYSTEMS
 
0.001 629425.00 0.00 379543.29 60.3
Work Order 04-02-14
Work Began 04-24-14
Work Completed  
Time Computed 04-18-14
Contract Working Days 120
Addl Days Granted 49
Working Days Charged 157
Percent Time Used 92
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-189
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01143202
Totals 629425.00 0.00 379543.29 60.3

CountyGALVESTON
Highway VA
From AT GALVESTON FERRY OFFICE
To .
CSJ 0912-73-190
Proj ID C 912-73-190
Work Type RENOVATION OF SHOP RESTROOMS
 
0.001 357800.00 6478.40 402262.51 99.9
Work Order 05-12-14
Work Began 05-19-14
Work Completed  
Time Computed 05-28-14
Contract Working Days 120
Addl Days Granted 72
Working Days Charged 198
Percent Time Used 103
Contractor(s)
J.C. LEWIS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-190
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143232
Totals 357800.00 6478.40 402262.51 99.9

CountyGALVESTON
Highway VA
From AT THE GALVESTON FERRY LANDING
To .
CSJ 0912-73-193
Proj ID FT 912-73-193
Work Type CONSTRUCT NEW BOAT LIFT
 
0.001 305695.00 3362.65 267788.83 87.6
Work Order 05-08-14
Work Began 08-13-14
Work Completed  
Time Computed 05-24-14
Contract Working Days 120
Addl Days Granted 37
Working Days Charged 141
Percent Time Used 89
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-193
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143230
Totals 305695.00 3362.65 267788.83 87.6

CountyGALVESTON
Highway VA
From AT GALV AND BOLIVAR FERRY LANDING
To .
CSJ 0912-73-194
Proj ID C 912-73-194
Work Type CONSTRUCT NEW SCREENING CANOPIES
 
0.001 731490.00 25108.54 604526.86 83.8
Work Order 05-08-14
Work Began 05-27-14
Work Completed  
Time Computed 05-24-14
Contract Working Days 120
Addl Days Granted 11
Working Days Charged 146
Percent Time Used 111
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-194
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143231
Totals 731490.00 25108.54 604526.86 83.8

CountyHARRIS
Highway FM 865
From ALMEDA-GENOA
To BW 8
CSJ 0976-01-019
Proj ID C 976-1-19
Work Type GR, BS & SURF
 
1.272 13285921.44 276104.73 585927.83 4.4
Work Order 02-12-14
Work Began 00-00-00
Work Completed  
Time Computed 11-09-14
Contract Working Days 305
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0976-01-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11133025
Totals 13285921.44 276104.73 585927.83 4.4

CountyHARRIS
Highway FM 865
From SOUTH OF BW 8
To BRAZORIA COUNTY LINE(CLEAR CREEK)
CSJ 0976-01-035
Proj ID STP 1102(436)
Work Type CR, BS & SURF
 
1.106 9266318.15 0.00 9267159.36 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-27-11
Work Began 11-29-11
Work Completed 09-09-14
Time Computed 11-12-11
Contract Working Days 410
Addl Days Granted 0
Working Days Charged 410
Percent Time Used 100
Contractor(s)
HASSELL CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0976-01-035
EMBARK TREE AND LANDSCAPE SERVICES (0.35%)
URBAN FORESTERS, LLC (0.34%)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC(4.74%)
GMJ PAVING CO. (2.40%)
BREDA COMPANY, INC.(0.58%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.25%)
BATTERSON,LLP(1.10%)
CHAMPIONS HYDROLAWN(0.33%)
JMHP, INC. (0.05%)
H & H CURB COMPANY (0.11%)
NBG CONSTRUCTORS, INC. ( 22.94%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(2.39%)
MESA ROD BUSTERS, INC. (0.00%)
CHERRY CONCRETE REMOVAL(0.26%)
DORAN STEEL, INC.(0.04%)
WALLACE CONCRETE SAWING(0.06%)
Contract # 08113207
Totals 9266318.15 0.00 9267159.36 100.0

CountyGALVESTON
Highway FM 518
From BAY AREA BLVD
To FM 2094
CSJ 0976-03-100
Proj ID C 976-3-100
Work Type ACCESS MANAGEMENT IMPROVEMENTS
 
0.668 1295137.47 -262.61 1105034.39 90.9
Work Order 12-03-13
Work Began 02-12-14
Work Completed  
Time Computed 02-01-14
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 189
Percent Time Used 248
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0976-03-100
TRAFFIC SYSTEMS CONSTRUCTION, INC. ( 25.48%)
ROADSAFE TRAFFIC SYSTEMS, INC. (3.48%)
AGGREGATE TECHNOLOGIES, INC. (1.99%)
SPEEDY PAVING(1.62%)
Contract # 08133223
Totals 1295137.47 262.61 1105034.39 90.9

CountyGALVESTON
Highway FM 646
From GRAND AVE
To FM 517
CSJ 0978-02-054
Proj ID STP 2007(404)
Work Type INST CULV, ADJ DRWAYS & RESTORE DRNG
 
3.700 5827858.98 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-10-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0978-02-054
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143223
Totals 5827858.98 0.00 0.00 0.0

CountyGALVESTON
Highway FM 517
From AT FM 3436
To .
CSJ 0978-02-069
Proj ID STP 2014(570)HES
Work Type INST INTERSECTION FLASHING BEACON
 
0.404 246122.55 29412.37 29412.37 11.9
Work Order 06-05-14
Work Began 00-00-00
Work Completed  
Time Computed 12-02-14
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0978-02-069
ISI CONTRACTING, INC.( 17.44%)
STRIPES & STOPS COMPANY, INC.(1.45%)
Contract # 04143029
Totals 246122.55 29412.37 29412.37 11.9

CountyGALVESTON
Highway FM 517
From AT FM 146
To .
CSJ 0978-02-071
Proj ID STP 2014(035)HES
Work Type TS IMPRVMT & LT TN LN
 
0.537 959632.80 66139.55 66139.55 6.8
Work Order 11-22-13
Work Began 11-24-14
Work Completed  
Time Computed 12-08-13
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 26
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0978-02-071
LONE STAR TRAFFIC SERVICE, INC.(0.28%)
REGIONAL TRAFFIC SERVICES LLC(3.73%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. ( 16.32%)
Contract # 09133220
Totals 959632.80 66139.55 66139.55 6.8

CountyBRAZORIA
Highway FM 524
From FM 521
To CR 334
CSJ 1004-01-052
Proj ID STP 2012(519)
Work Type UPGRADE DRAINAGE STRUCTURES
 
3.176 249163.00 0.00 216661.86 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-09-12
Work Began 08-17-12
Work Completed 09-10-14
Time Computed 07-25-12
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 76
Percent Time Used 253
Contractor(s)
NNA FINANCIAL SERVICES CO.
SUBCONTRACTOR(S) FOR CCSJ: 1004-01-052
HIGHWAY TECHNOLOGIES, INC. (1.41%)
Contract # 05123213
Totals 249163.00 0.00 216661.86 100.0

CountyHARRIS
Highway FM 529
From FREEMAN ROAD
To W OF FRY ROAD
CSJ 1006-01-059
Proj ID NH 2012(474)
Work Type GR, STRS, BASE AND SURF
 
1.184 7690213.53 228646.31 5909412.36 76.8
Work Order 01-31-13
Work Began 03-15-13
Work Completed  
Time Computed 02-16-13
Contract Working Days 322
Addl Days Granted 0
Working Days Charged 251
Percent Time Used 77
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 1006-01-059
HIGHWAY TECHNOLOGIES, INC. (0.79%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.96%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.42%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.77%)
ROSALES TRUCKING (1.50%)
BATTERSON,LLP(0.97%)
DURWOOD GREENE CONSTRUCTION CO.(7.49%)
EL DORADO PAVING COMPANY, INC. (0.49%)
TEX OP CONSTRUCTION, LP(1.02%)
CPAV SPECIALTIES, LP (0.60%)
INDUS CONSTRUCTION, L.P. (2.66%)
MASTER CURB, LLC (0.10%)
Contract # 10123217
Totals 7690213.53 228646.31 5909412.36 76.8

CountyHARRIS
Highway FM 2100
From FM 1960 (GUY ROAD)
To 0.066 M. S OF HUFFMAN-CLEVELAND RD
CSJ 1062-02-023
Proj ID STP 2013(696)
Work Type MILL & ACP OVERLAY
 
12.426 5966662.66 -4372.95 5653190.49 94.9
Work Order 07-31-13
Work Began 09-24-13
Work Completed  
Time Computed 09-24-13
Contract Working Days 186
Addl Days Granted 3
Working Days Charged 198
Percent Time Used 104
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1062-02-023
SIEMENS INDUSTRY, INC. (1.83%)
PROFESSIONAL TRAFFIC CONTROL, LLC(3.07%)
WILLOW CITY SIGN & RAIL, INC.(1.34%)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC(2.08%)
SOUTHWEST SIGNAL SUPPLY, INC.(0.35%)
CURB PLANET INC. (0.99%)
Contract # 05133003
Totals 5966662.66 4372.95 5653190.49 94.9

CountyHARRIS
Highway FM 2100
From DIAMONDHEAD BLVD.
To 0.14 MI S. OF FIRST STREET
CSJ 1062-04-047
Proj ID STP 2010(903)RGS
Work Type CONST RR GRADE SEPARATION STR & APP
 
0.870 8537094.26 0.00 11381687.75 100.0
CountyHARRIS
Highway FM 2100
From DIAMONDHEAD BLVD.
To 0.14 MILE SOUTH OF FIRST STREET
CSJ 1062-04-051
Proj ID STP 2011(543)ES
Work Type UTILITY ADJUSTMENT
 
0.870 335846.50 0.00 575841.86 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-01-10
Work Began 11-28-11
Work Completed 11-21-14
Time Computed 09-17-10
Contract Working Days 455
Addl Days Granted 101
Working Days Charged 556
Percent Time Used 100
Contractor(s)
NBG CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1062-04-047
ALLSTATE SIGNAL & CONSTRUCTION, LLC(2.70%)
BATTERSON,LLP(0.79%)
HASSELL CONSTRUCTION COMPANY, INC. ( 48.33%)
HOUSTON SAWING & DRILLING(0.09%)
JTB SERVICES (0.33%)
KOSSMAN CONTRACTING CO., INC.(0.23%)
REPUBLIC TRAFFIC SAFETY, INC.(0.43%)
SCOTT DERR PAINTING CO, LLC(0.26%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(2.70%)
MICKIE SERVICE, INC. (0.10%)
SAN JACINTO BORING & TUNNELING, INC. (0.23%)
SOUTHERN CRUSHED CONCRETE LLC(0.31%)
PM CONSTRUCTION & REHAB, LLC (1.62%)
JMHP, INC. (0.52%)
GMJ PAVING CO. (3.78%)
BREDA COMPANY, INC.(0.61%)
H & H CURB COMPANY (0.09%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.31%)
ENVIRONMENTAL ALLIES, L.P. (0.24%)
DORAN STEEL, INC.(0.18%)
LOPEZ UTILITIES, LLC (0.23%)
R & A BORING COMPANY (0.30%)
Contract # 07103015
Totals 8872940.76 0.00 11957529.61 100.0

CountyHARRIS
Highway FM 1093
From 3.6 MILES WEST OF IH 610
To 0.25 MILES EAST OF SH 6
CSJ 1258-04-056
Proj ID CM 2013(790)
Work Type IMPLEMENTATION OF ACCESS MGMT
 
7.386 2561914.38 178000.53 2402139.52 93.7
Work Order 11-04-13
Work Began 02-11-14
Work Completed  
Time Computed 02-02-14
Contract Working Days 154
Addl Days Granted 0
Working Days Charged 151
Percent Time Used 98
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1258-04-056
KOSSMAN CONTRACTING CO., INC.(0.45%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.22%)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC( 35.08%)
Contract # 07133031
Totals 2561914.38 178000.53 2402139.52 93.7

CountyHARRIS
Highway FM 1093
From AT BW 8
To .
CSJ 1258-04-060
Proj ID STP 2015(163)HESG
Work Type IMPROVE TS
 
0.202 493967.08 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-10-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 79
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1258-04-060
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143025
Totals 493967.08 0.00 0.00 0.0

CountyMONTGOMERY
Highway FM 1097
From FM 149
To IH 45
CSJ 1259-01-039
Proj ID STP 2015(541)
Work Type BASE REPAIR AND ACP O / L
 
13.600 4097441.59 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 77
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1259-01-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153217
Totals 4097441.59 0.00 0.00 0.0

CountyMONTGOMERY
Highway FM 1774
From 0.045 MI S OF W. LOST CREEK BLVD
To FM 149
CSJ 1400-04-011
Proj ID STP 1402(182)
Work Type GR, STRS, BS & CONC PAV
 
2.831 18070204.05 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-03-14
Work Began 00-00-00
Work Completed  
Time Computed 11-19-14
Contract Working Days 360
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1400-04-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143203
Totals 18070204.05 0.00 0.00 0.0

CountyMONTGOMERY
Highway FM 1774
From 0.109 MI N OF FM 1488
To 0.045 MI S OF W LOST CREEK BLVD
CSJ 1400-04-035
Proj ID STP 1102(437)
Work Type RECONSTRUCT ROADWAY
 
2.320 11301777.00 130107.99 12926036.88 99.9
Work Order 11-03-11
Work Began 12-06-11
Work Completed  
Time Computed 11-19-11
Contract Working Days 280
Addl Days Granted 302
Working Days Charged 494
Percent Time Used 84
Contractor(s)
HASSELL CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1400-04-035
GULF COAST PAVERS, INC.(0.22%)
GMJ PAVING CO. (7.32%)
H & H CURB COMPANY (0.12%)
BREDA COMPANY, INC.(0.89%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.55%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.36%)
BATTERSON,LLP(1.83%)
THIRD COAST SERVICES, LLC(4.26%)
URBAN FORESTERS, LLC (0.44%)
CHAMPIONS HYDRO-LAWN (0.80%)
Contract # 08113209
Totals 11301777.00 130107.99 12926036.88 99.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11