Monthly State Let Construction Report For Houston District As Of Apr 10, 2015 Page 6 Of 11

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-413
Proj ID STP 2013(542)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1456616.50 37158.60 789256.67 54.1
Work Order 07-08-13
Work Began 11-06-13
Work Completed  
Time Computed 11-06-13
Contract Working Days 417
Addl Days Granted 0
Working Days Charged 83
Percent Time Used 19
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-413
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133222
Totals 1456616.50 37158.60 789256.67 54.1

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-417
Proj ID STP 2012(462)
Work Type NEW / UPGRADE TO LED LIGHT ASSEMBLIES
 
0.001 859065.05 35092.17 971229.05 99.9
Work Order 05-09-12
Work Began 12-04-12
Work Completed  
Time Computed 05-25-12
Contract Working Days 220
Addl Days Granted 24
Working Days Charged 187
Percent Time Used 76
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-417
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04123026
Totals 859065.05 35092.17 971229.05 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-418
Proj ID STP 2013(321)
Work Type NEW SATELLITE BUILDING POWER SYS
 
0.001 598106.25 0.00 561011.57 93.7
Work Order 03-22-13
Work Began 02-24-14
Work Completed  
Time Computed 04-07-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 312
Percent Time Used 85
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-418
GENERATORS OF HOUSTON, LP( 69.74%)
BEVCO COMPANY, INC.(3.17%)
Contract # 01133028
Totals 598106.25 0.00 561011.57 93.7

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-420
Proj ID STP 2013(322)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1899903.95 0.00 0.00 0.0
Work Order 03-20-13
Work Began 00-00-00
Work Completed  
Time Computed 09-16-13
Contract Working Days 525
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-420
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01133213
Totals 1899903.95 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HARRIS COUNTY
To .
CSJ 0912-00-424
Proj ID CM 1102(560)
Work Type PED & SIG IMPRVMTS IN AIRLINE DIST
 
1.367 2697458.33 156210.76 1333660.26 49.4
Work Order 01-23-14
Work Began 04-14-14
Work Completed  
Time Computed 04-14-14
Contract Working Days 228
Addl Days Granted 0
Working Days Charged 215
Percent Time Used 94
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-424
GEORGE MEEKS LANDPRO, INC. (7.03%)
ODUM SERVICES, L.P.(0.35%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. ( 11.47%)
REGIONAL TRAFFIC SERVICES LLC(2.15%)
AGGREGATE TECHNOLOGIES, INC. (5.02%)
SPEEDY PAVING(1.31%)
Contract # 10133027
Totals 2697458.33 156210.76 1333660.26 49.4

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-440
Proj ID NH 2015(316)
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 772662.59 0.00 0.00 0.0
Work Order 01-16-15
Work Began 00-00-00
Work Completed  
Time Computed 02-01-15
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 11
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-440
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143019
Totals 772662.59 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-441
Proj ID NH 2014(297)
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 1210347.90 785.00 1118730.96 92.4
Work Order 03-03-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 500
Addl Days Granted 0
Working Days Charged 140
Percent Time Used 28
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-441
REGIONAL TRAFFIC SERVICES LLC(1.78%)
Contract # 12133223
Totals 1210347.90 785.00 1118730.96 92.4

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS
To .
CSJ 0912-00-443
Proj ID STP 2014(298)
Work Type INSTALL CCTV
 
0.001 243957.34 1425.42 252350.52 100.0
Work Order 01-17-14
Work Began 03-11-14
Work Completed 03-12-15
Time Computed 03-11-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 148
Percent Time Used 98
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-443
AMERICAN CABLE SERVICES, INC.(2.55%)
Contract # 12133020
Totals 243957.34 1425.42 252350.52 100.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS ON IH 45
To .
CSJ 0912-00-468
Proj ID IM 0451(341)
Work Type LANDSCAPE DEVELOPMENT
 
52.668 1130845.26 7941.36 1054252.81 93.2
Work Order 05-15-12
Work Began 06-15-12
Work Completed  
Time Computed 07-15-12
Contract Working Days 105
Addl Days Granted 45
Working Days Charged 130
Percent Time Used 86
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-468
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04123018
Totals 1130845.26 7941.36 1054252.81 93.2

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To ALL LOCATIONS ON US 59 & IH 610
CSJ 0912-00-469
Proj ID NH 2012(513)
Work Type LANDSCAPE DEVELOPMENT
 
0.001 778293.17 7210.79 720929.89 92.6
Work Order 06-11-12
Work Began 06-15-12
Work Completed  
Time Computed 06-27-12
Contract Working Days 90
Addl Days Granted 75
Working Days Charged 139
Percent Time Used 84
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-469
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05123222
Totals 778293.17 7210.79 720929.89 92.6

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-484
Proj ID STP 2013(993)
Work Type UPGRADE & MODERNIZE SIGNALS
 
0.001 557849.99 0.00 601002.38 99.9
Work Order 10-30-13
Work Began 05-12-14
Work Completed  
Time Computed 04-28-14
Contract Working Days 94
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 109
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-484
PROFESSIONAL TRAFFIC CONTROL, LLC(3.36%)
Contract # 08133263
Totals 557849.99 0.00 601002.38 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS WITHIN DISTRICT
To .
CSJ 0912-00-489
Proj ID NH 2014(744)
Work Type LANDSCAPE DEVELOPMENT
 
0.001 887550.77 7016.12 280812.13 31.6
Work Order 08-13-14
Work Began 09-22-14
Work Completed  
Time Computed 09-22-14
Contract Working Days 45
Addl Days Granted 9
Working Days Charged 18
Percent Time Used 33
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-489
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143020
Totals 887550.77 7016.12 280812.13 31.6

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-509
Proj ID STP 2015(161)
Work Type REP BR APPROACH SLABS
 
0.001 3708936.00 1129530.22 2564881.19 69.1
Work Order 10-17-14
Work Began 01-12-15
Work Completed  
Time Computed 12-16-14
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 54
Contractor(s)
NORTEX CONCRETE LIFT & STABILIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-509
ROADSAFE TRAFFIC SYSTEMS, INC. ( 13.59%)
MAIN LANE INDUSTRIES, LTD. ( 13.09%)
Contract # 09143233
Totals 3708936.00 1129530.22 2564881.19 69.1

CountyBRAZORIA
Highway CS
From CR 149 AT MUSTANG BAYOU
To .
CSJ 0912-31-203
Proj ID BR 2008(059)
Work Type REPL BR & APPRS
 
0.288 2748072.00 12100.00 1701724.64 61.9
Work Order 09-17-12
Work Began 11-26-12
Work Completed  
Time Computed 11-16-12
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 177
Percent Time Used 65
Contractor(s)
MENADE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-203
W. W. FOUNDATION DRILLING, LTD.(9.86%)
ENVIRONMENTAL ALLIES, L.P. (0.77%)
JUST GROOVING, LTD.(0.03%)
WILLOW CITY SIGN & RAIL, INC.(1.01%)
Contract # 07123007
Totals 2748072.00 12100.00 1701724.64 61.9

CountyBRAZORIA
Highway VA
From VARIOUS LOCATIONS
To .
CSJ 0912-31-211
Proj ID STP 2013(125)
Work Type MBGF UPGRADES
 
0.001 422144.20 0.00 408730.79 98.7
Work Order 07-31-13
Work Began 10-21-13
Work Completed  
Time Computed 09-29-13
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 140
Contractor(s)
TEXAS HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-211
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133207
Totals 422144.20 0.00 408730.79 98.7

CountyBRAZORIA
Highway CR
From CR 64 AT DRAINAGE DITCH
To .
CSJ 0912-31-222
Proj ID BR 2008(792)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.064 435258.40 172672.85 340170.57 78.1
Work Order 08-15-14
Work Began 01-20-15
Work Completed  
Time Computed 10-14-14
Contract Working Days 54
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 72
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-222
LONESTAR TRAFFIC SAFETY, LLC (0.76%)
REGIONAL TRAFFIC SERVICES LLC(0.35%)
ENVIRONMENTAL ALLIES, L.P. (1.57%)
JMHP, INC. (4.72%)
Contract # 06143206
Totals 435258.40 172672.85 340170.57 78.1

CountyBRAZORIA
Highway CR
From CR 48, CR 894
To SH 6
CSJ 0912-31-224
Proj ID STP 2009(103)MM
Work Type GR, STRS, BASE AND PAVE
 
3.022 14518735.55 -55110.17 7428952.71 51.1
Work Order 10-24-13
Work Began 01-06-14
Work Completed  
Time Computed 12-23-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 287
Percent Time Used 78
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-224
FLORIDA TRAFFIC CONTROL DEVICES, INC.(3.13%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.74%)
VAQUERO CONSTRUCTION, INC. (7.37%)
BREDA COMPANY, INC.(8.09%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.43%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(1.37%)
JAMES CONSTRUCTION GROUP, L.L.C. (7.58%)
EROSION CONTROL, INC.(0.78%)
JMHP, INC. (0.18%)
SCOTT DERR PAINTING CO (0.08%)
CPAVE, INC.(0.41%)
PEREZ CONSTRUCTION CO. (0.18%)
SPECIALTY DRILLING, LTD. (0.13%)
SCMU (0.27%)
Contract # 08133009
Totals 14518735.55 55110.17 7428952.71 51.1

CountyBRAZORIA
Highway CS
From NORTH 2ND STREET AT MUSTANG BAYOU
To .
CSJ 0912-31-237
Proj ID BR 2010(723)
Work Type REPLACE BRIDGE
 
0.126 766156.52 0.00 403426.71 52.6
Work Order 08-01-12
Work Began 09-17-12
Work Completed  
Time Computed 09-17-12
Contract Working Days 113
Addl Days Granted 0
Working Days Charged 65
Percent Time Used 57
Contractor(s)
TOM-MAC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-237
REPUBLIC TRAFFIC SAFETY, INC.(0.26%)
KOSSMAN CONTRACTING CO., INC.(2.07%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.05%)
GMJ PAVING CO. (7.38%)
KATY CONSTRUCTION(2.34%)
Contract # 06123205
Totals 766156.52 0.00 403426.71 52.6

CountyBRAZORIA
Highway CS
From CR 51 AT AUSTIN BAYOU
To .
CSJ 0912-31-263
Proj ID BR 1102(111)
Work Type REPLACE BRIDGE
 
0.131 456579.24 33143.50 221743.28 48.5
Work Order 10-30-14
Work Began 01-05-15
Work Completed  
Time Computed 12-29-14
Contract Working Days 84
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 66
Contractor(s)
TOM-MAC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-263
STRIPES & STOPS COMPANY, INC.(0.62%)
GMJ PAVING CO. (3.53%)
KOSSMAN CONTRACTING CO., INC.(3.77%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
Contract # 08143012
Totals 456579.24 33143.50 221743.28 48.5

CountyBRAZORIA
Highway CR
From CR 210 AT DRAINAGE DITCH
To .
CSJ 0912-31-265
Proj ID BR 2011(708)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.069 448817.82 0.00 394955.06 91.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-17-14
Work Began 02-25-14
Work Completed  
Time Computed 02-25-14
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 95
Percent Time Used 135
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-265
JMHP, INC. (3.35%)
LONE STAR TRAFFIC SERVICE, INC.(0.49%)
REGIONAL TRAFFIC SERVICES LLC(0.33%)
Contract # 10133205
Totals 448817.82 0.00 394955.06 91.2

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11