Monthly State Let Construction Report For Houston District As Of Apr 11, 2016 Page 6 Of 10

Last Update: Monday, April 11, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-385
Proj ID STP 2011(714)G
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 911168.15 0.00 1196058.08 99.9
Work Order 02-10-11
Work Began 11-01-11
Work Completed  
Time Computed 02-26-11
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 67
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-385
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12103230
Totals 911168.15 0.00 1196058.08 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-413
Proj ID STP 2013(542)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1456616.50 580.00 1258435.35 86.3
Work Order 07-08-13
Work Began 11-06-13
Work Completed  
Time Computed 11-06-13
Contract Working Days 417
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 28
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-413
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133222
Totals 1456616.50 580.00 1258435.35 86.3

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-417
Proj ID STP 2012(462)
Work Type NEW / UPGRADE TO LED LIGHT ASSEMBLIES
 
0.001 859065.05 0.00 1105336.31 99.9
Work Order 05-09-12
Work Began 12-04-12
Work Completed  
Time Computed 05-25-12
Contract Working Days 220
Addl Days Granted 24
Working Days Charged 210
Percent Time Used 86
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-417
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04123026
Totals 859065.05 0.00 1105336.31 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-420
Proj ID STP 2013(322)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1899903.95 336968.92 505453.72 26.6
Work Order 03-20-13
Work Began 09-30-15
Work Completed  
Time Computed 09-16-13
Contract Working Days 525
Addl Days Granted 0
Working Days Charged 33
Percent Time Used 6
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-420
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01133213
Totals 1899903.95 336968.92 505453.72 26.6

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HARRIS COUNTY
To .
CSJ 0912-00-424
Proj ID CM 1102(560)
Work Type PED & SIG IMPRVMTS IN AIRLINE DIST
 
1.367 2697458.33 3674.59 2304312.57 86.7
Work Order 01-23-14
Work Began 04-14-14
Work Completed  
Time Computed 04-14-14
Contract Working Days 228
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 119
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-424
GEORGE MEEKS LANDPRO, INC. (7.03%)
ODUM SERVICES, L.P.(0.35%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. ( 11.47%)
REGIONAL TRAFFIC SERVICES LLC(2.15%)
AGGREGATE TECHNOLOGIES, INC. (5.02%)
SPEEDY PAVING(1.31%)
AAA ASPHALT PAVING, INC. (0.00%)
Contract # 10133027
Totals 2697458.33 3674.59 2304312.57 86.7

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-440
Proj ID NH 2015(316)
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 772662.59 47948.52 799900.72 99.9
Work Order 01-16-15
Work Began 10-01-15
Work Completed  
Time Computed 02-01-15
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 88
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-440
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143019
Totals 772662.59 47948.52 799900.72 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-441
Proj ID NH 2014(297)
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 1210347.90 785.00 1172324.13 96.8
Work Order 03-03-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 500
Addl Days Granted 0
Working Days Charged 141
Percent Time Used 28
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-441
REGIONAL TRAFFIC SERVICES LLC(1.78%)
Contract # 12133223
Totals 1210347.90 785.00 1172324.13 96.8

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-484
Proj ID STP 2013(993)
Work Type UPGRADE & MODERNIZE SIGNALS
 
0.001 557849.99 0.00 606782.38 99.9
Work Order 10-30-13
Work Began 05-12-14
Work Completed  
Time Computed 04-28-14
Contract Working Days 94
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 109
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-484
PROFESSIONAL TRAFFIC CONTROL, LLC(3.36%)
Contract # 08133263
Totals 557849.99 0.00 606782.38 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN MISSOURI CITY
To .
CSJ 0912-00-488
Proj ID CM 2015(611)
Work Type COMMUNICATIONS / RELIABILITY URGRADE
 
0.001 1394256.88 67600.00 226200.00 16.2
Work Order 11-10-15
Work Began 02-01-16
Work Completed  
Time Computed 02-01-16
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 17
Contractor(s)
CREACOM, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-488
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153067
Totals 1394256.88 67600.00 226200.00 16.2

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS WITHIN DISTRICT
To .
CSJ 0912-00-489
Proj ID NH 2014(744)
Work Type LANDSCAPE DEVELOPMENT
 
0.001 887550.77 112400.32 771877.41 86.9
Work Order 08-13-14
Work Began 09-22-14
Work Completed  
Time Computed 09-22-14
Contract Working Days 45
Addl Days Granted 9
Working Days Charged 53
Percent Time Used 98
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-489
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143020
Totals 887550.77 112400.32 771877.41 86.9

CountyBRAZORIA
Highway CS
From CR 149 AT MUSTANG BAYOU
To .
CSJ 0912-31-203
Proj ID BR 2008(059)
Work Type REPL BR & APPRS
 
0.288 2748072.00 0.00 2710587.72 99.6
Work Order 09-17-12
Work Began 11-26-12
Work Completed  
Time Computed 11-16-12
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 305
Percent Time Used 112
Contractor(s)
MENADE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-203
W. W. FOUNDATION DRILLING, LTD.(9.86%)
ENVIRONMENTAL ALLIES, L.P. (0.77%)
JUST GROOVING, LTD.(0.03%)
WILLOW CITY SIGN & RAIL, INC.(1.01%)
GMJ PAVING CO. (5.09%)
Contract # 07123007
Totals 2748072.00 0.00 2710587.72 99.6

CountyBRAZORIA
Highway CR
From CR 48, CR 894
To SH 6
CSJ 0912-31-224
Proj ID STP 2009(103)MM
Work Type GR, STRS, BASE AND PAVE
 
3.022 14518735.55 176779.35 14324307.64 99.9
Work Order 10-24-13
Work Began 01-06-14
Work Completed  
Time Computed 12-23-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 524
Percent Time Used 143
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-224
FLORIDA TRAFFIC CONTROL DEVICES, INC.(3.13%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.74%)
VAQUERO CONSTRUCTION, INC. (7.37%)
BREDA COMPANY, INC.(8.09%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.43%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(1.37%)
JAMES CONSTRUCTION GROUP, L.L.C. (7.58%)
EROSION CONTROL, INC.(0.78%)
JMHP, INC. (0.18%)
SCOTT DERR PAINTING CO (0.08%)
CPAVE, INC.(0.41%)
PEREZ CONSTRUCTION CO. (0.18%)
SPECIALTY DRILLING, LTD. (0.13%)
SCMU (0.27%)
Contract # 08133009
Totals 14518735.55 176779.35 14324307.64 99.9

CountyBRAZORIA
Highway CS
From NORTH 2ND STREET AT MUSTANG BAYOU
To .
CSJ 0912-31-237
Proj ID BR 2010(723)
Work Type REPLACE BRIDGE
 
0.126 766156.52 25413.83 715356.32 95.1
Work Order 08-01-12
Work Began 09-17-12
Work Completed  
Time Computed 09-17-12
Contract Working Days 113
Addl Days Granted 0
Working Days Charged 135
Percent Time Used 119
Contractor(s)
TOM-MAC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-237
REPUBLIC TRAFFIC SAFETY, INC.(0.26%)
KOSSMAN CONTRACTING CO., INC.(2.07%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.05%)
GMJ PAVING CO. (7.38%)
KATY CONSTRUCTION(2.34%)
EROSION PREVENTION PRODUCTS(2.63%)
Contract # 06123205
Totals 766156.52 25413.83 715356.32 95.1

CountyBRAZORIA
Highway CS
From PEARLAND PKWY FROM W OF OILER DR
To DIXIE FARM RD
CSJ 0912-31-270
Proj ID C 912-31-270
Work Type CONSTRUCT 4 - LN DIVIDED ROADWAY
 
0.001 4837804.80 17946.50 4753400.93 99.1
Work Order 12-05-13
Work Began 03-17-14
Work Completed  
Time Computed 03-05-14
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 344
Percent Time Used 114
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-270
CPAVE, INC.(0.47%)
FLORIDA TRAFFIC CONTROL DEVICES, INC.(6.13%)
DNA TRUCKING (1.44%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.94%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.56%)
JUST GROOVING, LTD.(0.07%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.23%)
RDI FOUNDATION DRILLING(2.46%)
PEREZ CONSTRUCTION (2.49%)
MESA ROD BUSTERS, INC. (1.22%)
KOSSMAN CONTRACTING CO., INC.(1.56%)
SPEEDY PAVING(1.67%)
JMHP, INC. (0.29%)
H & E AGGREGATE, LLC (0.26%)
CONTRACTORS PAVING SUPPLY, LLP (0.68%)
SPECIALTY DRILLING, LTD. (0.23%)
WEIMER CONSTRUCTION COMPANY(0.47%)
HYDROZONE LANDSCAPE CORPORATION(3.55%)
BATTERSON,LLP(0.21%)
SEMARCK LANDSCAPE SERVICES, INC. (1.74%)
Contract # 08133213
Totals 4837804.80 17946.50 4753400.93 99.1

CountyBRAZORIA
Highway VA ETC
From VAR LOCATIONS ON SH 288 & SH 332
To IN LAKE JACKSON
CSJ 0912-31-279
Proj ID STP 2012(516)
Work Type LANDSCAPE DEVELOPMENT
 
0.006 2131009.80 -9470.70 1422611.07 67.5
Work Order 09-30-14
Work Began 02-24-15
Work Completed  
Time Computed 11-29-14
Contract Working Days 120
Addl Days Granted 24
Working Days Charged 142
Percent Time Used 98
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-279
HOGGATT, LP(5.10%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.02%)
APACE SERVICES, INC. (4.11%)
SCOTT DERR PAINTING CO (0.59%)
CC TREE FARMS, L.L.C.( 10.11%)
Contract # 07143012
Totals 2131009.80 9470.70 1422611.07 67.5

CountyBRAZORIA
Highway CR
From CR 227; AT CHOC BYU WA CO CAN.
To .
CSJ 0912-31-282
Proj ID BR 2013(574)
Work Type REPL BR & APPR
 
0.204 1423278.90 372307.04 1386242.54 97.7
Work Order 08-13-15
Work Began 10-15-15
Work Completed  
Time Computed 09-13-15
Contract Working Days 84
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 109
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-282
GMJ PAVING CO. (4.67%)
ODUM SERVICES, L.P.(2.88%)
WEBER-BALKE FOUNDATION COMPANY, INC(4.59%)
PROFFESSIONAL TRAFFIC CONTROL, LLC.(0.53%)
MESA ROD BUSTERS, INC. (0.99%)
SCOTT DERR PAINTING CO, LLC(0.07%)
A1 EROSION CONTROL (1.36%)
PRIMATE CONSTRUCTION, INC. (0.59%)
LONESTAR TRAFFIC SAFETY, LLC (0.37%)
Contract # 06153061
Totals 1423278.90 372307.04 1386242.54 97.7

CountyBRAZORIA
Highway CR
From CR 48, BROADWAY (FM 518)
To CR 894
CSJ 0912-31-294
Proj ID STP 2015(612)MM
Work Type WIDEN FROM 2 TO 4 - LANE DIVIDED
 
1.944 12154201.39 332687.78 7814857.20 64.2
Work Order 04-10-15
Work Began 06-09-15
Work Completed  
Time Computed 06-09-15
Contract Working Days 357
Addl Days Granted 3
Working Days Charged 185
Percent Time Used 51
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-294
CPAVE, INC.(0.04%)
GEORGE MEEKS LANDPRO, INC. (0.89%)
GMJ PAVING CO. (3.06%)
MESA ROD BUSTERS, INC. (6.36%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.41%)
SCOTT DERR PAINTING CO (0.04%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.49%)
TEXAS CLEARING AND LEVELING(0.40%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.58%)
W. W. FOUNDATION DRILLING, LTD.(3.10%)
MBN ENTERPRISES LLC(2.49%)
WEBBER BARRIER SERVICES, LLC.(0.22%)
DNA TRUCKING, INC. (0.20%)
CURB PLANET INC. (0.03%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.04%)
SOUTHERN CRUSHED CONCRETE LLC(1.11%)
Contract # 02153002
Totals 12154201.39 332687.78 7814857.20 64.2

CountyFORT BEND
Highway CS
From WEST AIRPORT - FROM US 59
To 800 FEET WEST OF KIRKWOOD DRIVE
CSJ 0912-34-130
Proj ID HP 2011(793)
Work Type RECONSTRUCTION OF WEST AIRPORT
 
0.695 4192145.17 0.00 3967302.61 95.5
Work Order 03-12-14
Work Began 05-28-14
Work Completed  
Time Computed 05-10-14
Contract Working Days 213
Addl Days Granted 0
Working Days Charged 251
Percent Time Used 117
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-130
CHERRY CRUSHED CONCRETE(0.99%)
REGIONAL TRAFFIC SERVICES LLC(1.27%)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC(6.68%)
ABLE PAVING(0.52%)
HODGES BROTHERS, INC.(0.81%)
DORAN STEEL, INC.(0.19%)
CURB PLANET INC. (0.15%)
JASSO"S SAWING & SEALING (0.10%)
KOSSMAN CONTRACTING CO., INC.(0.35%)
A-1 EROSION CONTROL, LLC (0.38%)
MICKIE SERVICE, INC. (0.33%)
Contract # 01143211
Totals 4192145.17 0.00 3967302.61 95.5

CountyFORT BEND
Highway CS
From TRAMMEL FRESNO RD, FORT BEND PKWY
To FM 521
CSJ 0912-34-144
Proj ID STP 2010(596)MM
Work Type GR, STR, BASE AND 0AVE
 
3.041 20864455.45 5000.00 4065902.46 19.4
Work Order 03-03-15
Work Began 03-24-15
Work Completed  
Time Computed 03-19-15
Contract Working Days 622
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 4
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-144
STRIPE-A-LINE, INC.(0.72%)
RICE ENVIRONMENTAL SERVICES(0.24%)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC(1.96%)
INDUS CONSTRUCTION, L.P. (3.85%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.17%)
BASE CONSTRUCTION, L.L.P.( 23.02%)
KMA CONTRACTORS SERVICES INC.(4.77%)
Contract # 12143003
Totals 20864455.45 5000.00 4065902.46 19.4

CountyFORT BEND
Highway CR ETC
From MEYER ROAD AT SNAKE CREEK TRIBUTARY
To .
CSJ 0912-34-176
Proj ID BR 2013(735)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.712 2828589.45 104764.98 1878019.06 66.3
Work Order 08-04-15
Work Began 09-08-15
Work Completed  
Time Computed 09-08-15
Contract Working Days 321
Addl Days Granted 0
Working Days Charged 133
Percent Time Used 41
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-176
LONESTAR TRAFFIC SAFETY, LLC (0.55%)
REGIONAL TRAFFIC SERVICES LLC(0.40%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.45%)
ODUM SERVICES, L.P.(1.77%)
MESA ROD BUSTERS, INC. (0.19%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.98%)
EROSION PREVENTION PRODUCTS(4.81%)
Contract # 06153027
Totals 2828589.45 104764.98 1878019.06 66.3

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10