Monthly State Let Construction Report For Houston District As Of Jun 08, 2018 Page 6 Of 10

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBRAZORIA
HighwaySH 332
FromUPRR
ToFM 523
CSJ0586-01-066
Proj IDNH 2018(666)
Work TypeSC,LEVEL UP,W/ LP DETRS & O/L
 
3.7992395790.470.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-17-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days95
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0586-01-066
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183011
Totals2395790.470.000.000.0

CountyBRAZORIA
HighwaySH 288
FromAT RODEO PALMS PARKWAY
To.
CSJ0598-02-047
Proj IDNH 1702(112)
Work TypeCONST NB EXIT & ENT RAMPS & TIE-IN
 
1.0632336954.311922989.9082.3
Work Order07-20-17
Work Began10-16-17
Work Completed
Time Computed09-18-17
Contract Working Days138
Addl Days Granted0
Working Days Charged140
Percent Time Used101
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-047
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.59)
DURWOOD GREENE CONSTRUCTION CO. (3.99)
TRAF-TEX, INC. (5.81)
MESA ROD BUSTERS, INC. (3.42)
A-1 EROSION CONTROL, LLC (1.36)
HIGHWAY 1, LLC (1.19)
LONESTAR TRAFFIC SAFETY, LLC (0.13)
SOUTHERN CRUSHED CONCRETE LLC (0.19)
Contract #06173244
Totals2336954.31111883.591922989.9082.3

CountyBRAZORIA
HighwaySH 288
FromFM 2234
ToHAYES CREEK
CSJ0598-02-100
Proj IDNH 2017(494)
Work TypeMILL,SEAL & PFC O/L
 
9.4784993779.695370904.8999.9
Work Order02-09-17
Work Began05-07-17
Work Completed
Time Computed04-10-17
Contract Working Days183
Addl Days Granted0
Working Days Charged172
Percent Time Used93
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-100
PROFFESSIONAL TRAFFIC CONTROL, LLC. (5.44)
STRIPE LINES, INC. (0.21)
CPAVE, INC. (2.63)
ODUM SERVICES, L.P. (2.97)
Contract #01173247
Totals4993779.690.005370904.8999.9

CountyMONTGOMERY
HighwayFM 149
FromN. SOUTHERN MONTGOMERY CITY LIMITS
ToKEENAN CUTOFF ROAD
CSJ0720-02-085
Proj IDSTP 2017(635)
Work TypeBS REPR, OCST, 1.5" OL & ADD SHLDR
 
3.8602864063.573068605.3499.9
Work Order06-01-17
Work Began07-17-17
Work Completed
Time Computed07-03-17
Contract Working Days113
Addl Days Granted20
Working Days Charged100
Percent Time Used75
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0720-02-085
WILLOW CITY SIGN & RAIL, INC. (4.28)
J & M CONTRACTING COMPANY (16.25)
STRIPE LINES, INC. (2.26)
STRIPE-A-ZONE, INC. (0.31)
WATERS CONSTRUCTION CO., INC. (5.35)
CEN TEX HYDROSEED, INC. (7.54)
TEXAS LAND CLEARING, INC. (2.11)
Contract #02173208
Totals2864063.5760263.703068605.3499.9

CountyMONTGOMERY
HighwaySH 249
FromHARRIS COUNTY LINE
ToFM 149
CSJ0720-02-086
Proj IDSTP 2018(315)
Work TypeINST PV MKS
 
4.230130786.9099199.0775.8
Work Order12-19-17
Work Began03-05-18
Work Completed
Time Computed01-18-18
Contract Working Days84
Addl Days Granted0
Working Days Charged43
Percent Time Used51
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 0720-02-086
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11173007
Totals130786.9016378.2399199.0775.8

CountyMONTGOMERY
HighwayFM 149
FromFM 1097
ToFM 1791
CSJ0720-02-087
Proj IDSTP 1502(606)HES
Work TypeBS REPR, OCST, 1.5" OL & ADD SHLDR
 
10.17010198541.1810390239.8599.9
Work Order11-10-15
Work Began01-11-16
Work Completed
Time Computed01-11-16
Contract Working Days183
Addl Days Granted32
Working Days Charged192
Percent Time Used89
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0720-02-087
J & M CONTRACTING, COMPANY (5.60)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.13)
TEXAS LAND CLEARING, INC. (18.16)
WATERS CONSTRUCTION CO., INC. (3.85)
WILLOW CITY SIGN & RAIL, INC. (1.56)
CEN TEX HYDROSEED, INC. (8.45)
Contract #08153044
Totals10198541.1827247.0510390239.8599.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-331
Proj IDCM 2008(055)
Work TypeNEW TRAFFIC SIGNALS
 
0.0011482581.451414891.6795.4
Work Order09-11-07
Work Began04-04-08
Work Completed
Time Computed09-27-07
Contract Working Days235
Addl Days Granted120
Working Days Charged235
Percent Time Used66
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-331
BATTERSON, L.L.P. (1.04)
SPRING CREEK CONSTRUCTION, INC. (4.49)
Contract #08073244
Totals1482581.450.001414891.6795.4

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-336
Proj IDSTP 2011(578)G
Work TypeINSTALL VIVDS AND INSTALL LOOPS
 
0.003439963.75553599.8199.9
Work Order01-06-11
Work Began04-09-12
Work Completed
Time Computed01-22-11
Contract Working Days187
Addl Days Granted0
Working Days Charged187
Percent Time Used100
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-336
CURB PLANET INC. (0.11)
Contract #12103011
Totals439963.753937.58553599.8199.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-350
Proj IDCM 2009(364)
Work TypeNEW TRAFFIC SIGNALS
 
0.0011289999.251391087.7699.9
Work Order06-02-09
Work Began08-12-12
Work Completed
Time Computed06-18-09
Contract Working Days225
Addl Days Granted0
Working Days Charged221
Percent Time Used98
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-350
CREACOM, INC. (0.04)
SPRING CREEK CONSTRUCTION, INC. (3.15)
HIGHWAY TECHNOLOGIES, INC. (0.76)
KAM CONSTRUCTION, INC. (0.86)
WALLACE CONCRETE SAWING (0.14)
REGIONAL TRAFFIC SERVICES LLC (0.00)
VASQUEZ CONCRETE COMPANY (0.38)
ENERGY ELECTRIC SUPPLY, INC. (4.03)
Contract #04093209
Totals1289999.250.001391087.7699.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-380
Proj IDSTP 2012(020)
Work TypeNEW TRAFFIC SIGNALS
 
0.0011515998.781619598.4899.9
Work Order11-16-11
Work Began02-13-12
Work Completed
Time Computed12-02-11
Contract Working Days437
Addl Days Granted0
Working Days Charged285
Percent Time Used65
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-380
BATTERSON,LLP (5.72)
ISI CONTRACTING, INC. (6.40)
VASQUEZ CONCRETE COMPANY (0.32)
ENERGY ELECTRIC SUPPLY, INC. (0.92)
Contract #09113211
Totals1515998.780.001619598.4899.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-413
Proj IDSTP 2013(542)
Work TypeNEW TRAFFIC SIGNALS
 
0.0011456616.501632294.9399.9
Work Order07-08-13
Work Began11-06-13
Work Completed
Time Computed11-06-13
Contract Working Days417
Addl Days Granted0
Working Days Charged160
Percent Time Used38
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-413
STRIPE-A-LINE, INC. (0.12)
ELEC-NET SUPPLY (34.89)
Contract #04133222
Totals1456616.5013133.001632294.9399.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-420
Proj IDSTP 2013(322)
Work TypeNEW TRAFFIC SIGNALS
 
0.0011899903.952024371.5299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-20-13
Work Began09-30-15
Work Completed
Time Computed09-16-13
Contract Working Days525
Addl Days Granted0
Working Days Charged252
Percent Time Used48
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-420
PROFESSIONAL TRAFFIC CONTROL, LLC (3.97)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC (0.07)
SPRING CREEK CONSTRUCTION, INC. (7.16)
Contract #01133213
Totals1899903.950.002024371.5299.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS WITHIN DISTRICT
To.
CSJ0912-00-489
Proj IDNH 2014(744)
Work TypeLANDSCAPE DEVELOPMENT
 
0.001887550.772203714.7399.9
Work Order08-13-14
Work Began09-22-14
Work Completed
Time Computed09-22-14
Contract Working Days45
Addl Days Granted9
Working Days Charged53
Percent Time Used98
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-489
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06143020
Totals887550.770.002203714.7399.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-511
Proj IDSTP 2017(158)
Work TypeNEW TRAFFIC SIGNALS
 
0.5081718929.72819921.2547.6
Work Order01-04-17
Work Began07-10-17
Work Completed
Time Computed07-10-17
Contract Working Days199
Addl Days Granted0
Working Days Charged97
Percent Time Used48
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-511
GLOBE ELECTRIC SUPPLY COMPANY, INC. (5.90)
STRIPE LINES, INC. (1.74)
MENADE, INC. (12.49)
Contract #10163215
Totals1718929.7275947.01819921.2547.6

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-513
Proj IDSTP 2017(306)
Work TypeTRAFFIC SIGNAL UPGRADES
 
0.001927576.88970132.0199.9
Work Order01-17-17
Work Began03-20-17
Work Completed
Time Computed02-16-17
Contract Working Days119
Addl Days Granted0
Working Days Charged104
Percent Time Used87
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-513
SIGNAL & UTILITY COMPANY (4.27)
Contract #12163021
Totals927576.880.00970132.0199.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-522
Proj IDNH 1702(791)
Work TypeTS UPGRADE
 
0.0011887654.90333113.5217.6
Work Order11-27-17
Work Began02-20-18
Work Completed
Time Computed01-26-18
Contract Working Days160
Addl Days Granted0
Working Days Charged75
Percent Time Used46
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-522
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173001
Totals1887654.90115219.04333113.5217.6

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-523
Proj IDNH 2018(110)
Work TypeINST TS
 
0.0011468618.08645203.2343.9
Work Order01-10-18
Work Began03-19-18
Work Completed
Time Computed04-10-18
Contract Working Days260
Addl Days Granted0
Working Days Charged47
Percent Time Used18
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-523
AAA ASPHALT PAVING, INC. (4.43)
HIGHWAY 1 LLC (5.13)
Contract #12173014
Totals1468618.08121671.73645203.2343.9

CountyBRAZORIA
HighwayCR
FromCR 168 AT GULF COAST WATER CANAL
To.
CSJ0912-31-221
Proj IDBR 2008(795)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.094602388.750.000.0
Work Order10-03-17
Work Began00-00-00
Work Completed
Time Computed01-01-18
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-221
HIGHWAY 1 LLC (3.07)
Contract #08173233
Totals602388.750.000.000.0

CountyBRAZORIA
HighwayVA
FromLOCATIONS IN LAKE JACKSON
To.
CSJ0912-31-301
Proj IDSTP 1602(077)
Work TypeLANDSCAPE DEVELOPMENT
 
0.300920524.00882597.2395.8
Work Order08-18-16
Work Began10-24-16
Work Completed
Time Computed10-17-16
Contract Working Days120
Addl Days Granted0
Working Days Charged120
Percent Time Used100
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-301
LONESTAR TRAFFIC SAFETY, LLC (0.92)
Contract #07163041
Totals920524.003000.00882597.2395.8

CountyFORT BEND
HighwayCS
FromTRAMMEL FRESNO RD, FORT BEND PKWY
ToFM 521
CSJ0912-34-144
Proj IDSTP 2010(596)MM
Work TypeGR, STR, BASE AND 0AVE
 
3.04120864455.458625339.3941.3
Work Order03-03-15
Work Began03-24-15
Work Completed
Time Computed03-19-15
Contract Working Days622
Addl Days Granted0
Working Days Charged219
Percent Time Used35
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-144
STRIPE-A-LINE, INC. (0.72)
RICE ENVIRONMENTAL SERVICES (0.24)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC (1.96)
INDUS CONSTRUCTION, L.P. (3.85)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.17)
BASE CONSTRUCTION, L.L.P. (23.02)
KMA CONTRACTORS SERVICES INC. (4.77)
BORTUNCO (0.87)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.36)
WILLOW CITY SIGN & RAIL, INC. (0.34)
Contract #12143003
Totals20864455.45761882.378625339.3941.3

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10