Monthly State Let Construction Report For Houston District As Of Feb 11, 2016 Page 6 Of 15

Last Update: Thursday, February 11, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13 | page 14 | page 15

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGALVESTON
Highway IH 45
From FM 1764
To TO TEXAS CITY WYE (SBML ONLY)
CSJ 0500-04-129
Proj ID NH 2015(694)
Work Type CAM & TOM O / L
 
7.825 4920504.92 35779.40 6260847.52 99.9
Work Order 05-19-15
Work Began 08-10-15
Work Completed  
Time Computed 07-19-15
Contract Working Days 60
Addl Days Granted 15
Working Days Charged 83
Percent Time Used 110
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0500-04-129
BATTERSON,LLP(3.81%)
MAIN LANE INDUSTRIES, LTD. (8.50%)
Contract # 04153217
Totals 4920504.92 35779.40 6260847.52 99.9

CountyGALVESTON
Highway IH 45
From SH 6
To GALVESTON/HARRIS COUNTY LINE
CSJ 0500-04-134
Proj ID NH 1502(605)
Work Type LANDSCAPE DEVELOPMENT
 
48.838 960543.57 0.00 0.00 0.0
Work Order 10-19-15
Work Began 01-19-16
Work Completed  
Time Computed 01-17-16
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 13
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-04-134
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153221
Totals 960543.57 0.00 0.00 0.0

CountyHARRIS
Highway SH 225
From 0.23 MILES WEST OF RICHEY
To 0.36 MILES EAST OF RED BLUFF
CSJ 0502-01-207
Proj ID NH 2014(054)
Work Type CLEAN & SEAL JTS, FULL DPTH REP, MILL
 
1.395 1050533.90 0.00 830429.43 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-12-14
Work Began 04-04-14
Work Completed 12-09-14
Time Computed 02-28-14
Contract Working Days 72
Addl Days Granted 32
Working Days Charged 128
Percent Time Used 123
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-207
UNITED PAVEMENT & MARKINGS, LLC(1.74%)
ISI CONTRACTING, INC.( 40.25%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 27.98%)
UNDER CONSTRUCTION INC.(4.75%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.47%)
Contract # 10133213
Totals 1050533.90 0.00 830429.43 100.0

CountyHARRIS
Highway SH 225
From AT SL 8
To .
CSJ 0502-01-209
Proj ID STP 2015(704)HES
Work Type IMPROVE TS
 
0.202 229926.40 670.00 220602.26 95.9
Work Order 04-14-15
Work Began 09-14-15
Work Completed  
Time Computed 08-13-15
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 62
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-209
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153017
Totals 229926.40 670.00 220602.26 95.9

CountyHARRIS
Highway SH 225
From BW 8
To TIDAL RD
CSJ 0502-01-210
Proj ID NH 2016(060)
Work Type REHAB BRIDGE
 
3.160 2602026.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-210
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10153226
Totals 2602026.60 0.00 0.00 0.0

CountyHARRIS
Highway SH 225
From BW 8
To SH 146 (MAINLANES & FRONTAGE ROADS)
CSJ 0502-01-211
Proj ID NH 1502(034)
Work Type PAVEMENT MARKINGS
 
7.391 684681.90 0.00 746190.96 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-21-15
Work Began 07-15-15
Work Completed 12-11-15
Time Computed 06-21-15
Contract Working Days 84
Addl Days Granted 0
Working Days Charged 97
Percent Time Used 115
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-211
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153045
Totals 684681.90 0.00 746190.96 100.0

CountyHARRIS
Highway IH 10
From CROSBY-LYNCHBURG ROAD
To GARTH ROAD
CSJ 0508-01-034
Proj ID IM 0107(443)
Work Type INSTALL CTMS
 
4.735 2122122.80 50347.00 1787483.26 84.2
Work Order 06-23-14
Work Began 03-11-15
Work Completed  
Time Computed 12-19-14
Contract Working Days 312
Addl Days Granted 0
Working Days Charged 186
Percent Time Used 59
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-034
JMHP, INC. (4.78%)
BAY CITY TRAFFIC (1.61%)
Contract # 04143024
Totals 2122122.80 50347.00 1787483.26 84.2

CountyHARRIS
Highway IH 10
From ON ELYSIAN ST.; FROM COMMERCE ST.
To BROOKS ST.
CSJ 0508-01-276
Proj ID IM 0107(442)
Work Type REPLC BR & APPR
 
1.126 34623242.31 4189.00 5606685.26 16.1
Work Order 06-05-14
Work Began 00-00-00
Work Completed  
Time Computed 03-02-15
Contract Working Days 907
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-276
LINDAMOOD DEMOLITION, INC. (3.28%)
THIRD COAST SERVICES LLC (1.53%)
HOUSTON SAWING & DRILLING(0.09%)
BIO LANDSCAPE & MAINTENANCE, INC.(1.02%)
BREDA COMPANY, INC.(1.89%)
CHOCTAW ERECTORS, INC. (1.41%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.17%)
PROFESSIONAL TRAFFIC CONTROL, LLC(0.09%)
SCOTT DERR PAINTING CO, LLC(0.36%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.06%)
GMJ PAVING CO. (0.34%)
Contract # 09133203
Totals 34623242.31 4189.00 5606685.26 16.1

CountyHARRIS
Highway IH 10
From AT THOMPSON RD
To .
CSJ 0508-01-338
Proj ID IM 0107(437)
Work Type CONCRETE PAVEMENT
 
0.969 4306347.00 66754.50 4391628.11 99.9
Work Order 07-20-15
Work Began 09-08-15
Work Completed  
Time Computed 08-20-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 74
Percent Time Used 164
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-338
PROFESSIONAL TRAFFIC CONTROL, LLC(1.86%)
ANGEL BROTHERS ENTERPRISES, LTD. (9.07%)
BUYERS BARRICADES, INC.(0.13%)
SOUTHERN CRUSHED CONCRETE LLC(0.28%)
AAA ASPHALT PAVING, INC. (0.00%)
INDUS CONSTRUCTION, L.P. (1.21%)
STRIPE-A-LINE, INC.(0.49%)
Contract # 06153265
Totals 4306347.00 66754.50 4391628.11 99.9

CountyHARRIS
Highway IH 10
From AT MEADOW STREET
To .
CSJ 0508-01-343
Proj ID BR 1302(017)
Work Type REHABILITATION OF BRIDGE DECK
 
0.001 1881415.65 0.00 2206418.63 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-23-13
Work Began 10-28-14
Work Completed 08-21-15
Time Computed 01-21-14
Contract Working Days 60
Addl Days Granted 14
Working Days Charged 66
Percent Time Used 89
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-343
BATTERSON,LLP(0.56%)
CHOCTAW ERECTORS, INC. (7.94%)
HOLES INCORPORATED (2.27%)
HOUSTON SAWING & DRILLING(0.11%)
LONESTAR TRAFFIC SAFETY, LLC (3.72%)
MESA ROD BUSTERS, INC. (0.59%)
REPUBLIC TRAFFIC SAFETY, INC.(0.74%)
ROMAR UNLIMITED, INC.(0.69%)
Contract # 08133058
Totals 1881415.65 0.00 2206418.63 100.0

CountyHARRIS
Highway IH 10
From IH 45
To CHAMBERS COUNTY LINE
CSJ 0508-01-344
Proj ID IM 0107(445)
Work Type LANDSCAPE DEVELOPMENT
 
0.001 1351369.79 1256.49 1018671.47 75.3
Work Order 07-02-14
Work Began 09-04-14
Work Completed  
Time Computed 09-04-14
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 76
Percent Time Used 84
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-344
N-LINE TRAFFIC MAINTENANCE, L.P. (0.68%)
ENVIRONMENTAL ALLIES, L.P. (1.26%)
Contract # 04143020
Totals 1351369.79 1256.49 1018671.47 75.3

CountyHARRIS
Highway IH 10
From AT JOHN MARTIN
To .
CSJ 0508-01-349
Proj ID NH 2015(416)
Work Type CONSTRUCT UTURN
 
0.077 669740.30 0.00 699771.61 99.9
Work Order 01-22-15
Work Began 05-14-15
Work Completed  
Time Computed 03-23-15
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 89
Percent Time Used 98
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-349
ROADSAFE TRAFFIC SYSTEMS, INC. (2.28%)
Contract # 12143216
Totals 669740.30 0.00 699771.61 99.9

CountyHARRIS
Highway IH 10
From BW 8
To SP 330
CSJ 0508-01-350
Proj ID NH 2016(416)
Work Type PAVEMENT MARKINGS
 
6.770 428325.12 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 108
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-350
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153220
Totals 428325.12 0.00 0.00 0.0

CountyHARRIS
Highway SS 330
From SAN JACINTO AVE/ROLLINGBROOK STREET
To BAKER ROAD
CSJ 0508-07-286
Proj ID CC 508-7-286
Work Type LEFT TURN LN & UTURN IMPROVEMENTS
 
0.427 2251558.84 91834.26 2167239.53 97.9
Work Order 03-20-15
Work Began 06-22-15
Work Completed  
Time Computed 05-19-15
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 100
Percent Time Used 192
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-07-286
REGIONAL TRAFFIC SERVICES LLC(1.36%)
LONE STAR TRAFFIC SERVICE, INC.(0.10%)
JASSO"S SAWING & SEALING (0.88%)
OSCAR ORDUNO, INC. ( 16.23%)
CENTURY ASPHALT MATERIALS(0.79%)
HOLES INCORPORATED (1.19%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (4.82%)
MESA ROD BUSTERS, INC. (0.57%)
CURB PLANET INC. (0.07%)
BATTERSON,LLP(1.11%)
Contract # 01153024
Totals 2251558.84 91834.26 2167239.53 97.9

CountyWALLER
Highway FM 362
From AT FM 529
To .
CSJ 0523-02-044
Proj ID STP 2014(486)HES
Work Type INST FLASHING BEACON
 
0.001 109572.50 0.00 108848.50 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-11-14
Work Began 10-07-14
Work Completed 02-06-15
Time Computed 10-07-14
Contract Working Days 29
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 51
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0523-02-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143031
Totals 109572.50 0.00 108848.50 100.0

CountyWALLER
Highway FM 362
From 2.159 MI S OF FM 1488
To 2.923 MI N OF US 290
CSJ 0523-02-046
Proj ID STP 2016(466)HES
Work Type INSTALL LED FLASHING CHEVRONS
 
7.478 1069740.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0523-02-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163239
Totals 1069740.00 0.00 0.00 0.0

CountyMONTGOMERY
Highway FM 1488
From FM 149
To 0.3 MI E OF COMMUNITY RD AT MOSTYN
CSJ 0523-10-034
Proj ID C 523-10-34
Work Type CONSTRUCT RR GRADE SEPARATION
 
2.779 27649979.11 2227817.01 8912932.60 32.2
Work Order 10-22-13
Work Began 02-16-15
Work Completed  
Time Computed 07-19-14
Contract Working Days 478
Addl Days Granted 0
Working Days Charged 157
Percent Time Used 32
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0523-10-034
PROFESSIONAL TRAFFIC CONTROL, LLC(1.11%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.67%)
EUBANK EXCAVATION, L.L.C.(0.76%)
BREDA COMPANY, INC.(1.41%)
WILLOW CITY SIGN & RAIL, INC.(0.51%)
GMJ PAVING CO. (5.71%)
RDI FOUNDATION DRILLING(4.28%)
HOUSTON SAWING & DRILLING(0.04%)
TEX OP CONSTRUCTION, LP(0.60%)
SCOTT DERR PAINTING CO (0.13%)
NORTHWEST MATERIALS(0.25%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.27%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.15%)
CREACOM, INC.(1.18%)
VALLEY PLACERS, LLC(0.27%)
APCON SERVICES, LLC(0.00%)
FORDE CONSTRUCTION COMPANY, INC. (0.19%)
CEN TEX HYDROSEED, INC.(0.42%)
Contract # 07133003
Totals 27649979.11 2227817.01 8912932.60 32.2

CountyFORT BEND
Highway FM 359
From AT US 90A AND UPRR
To .
CSJ 0543-02-055
Proj ID STP 2013(734)RGS
Work Type RR GRADE SEPARATION
 
0.408 27124547.77 0.00 0.00 0.0
Work Order 07-22-15
Work Began 00-00-00
Work Completed  
Time Computed 01-19-16
Contract Working Days 482
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0543-02-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153205
Totals 27124547.77 0.00 0.00 0.0

CountyFORT BEND
Highway FM 762
From AT FM 2977
To .
CSJ 0543-03-071
Proj ID STP 2014(927)
Work Type INSTALL TURN LANE & IMPROVE SHLDS
 
0.615 477521.30 0.00 531619.35 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-13-14
Work Began 09-04-14
Work Completed 12-18-14
Time Computed 09-04-14
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 44
Percent Time Used 80
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0543-03-071
INTERSTATE BARRICADES & MARKINGS, INC. (5.36%)
WEST TEXAS RUMBLE STRIP(0.82%)
BAY CITY TRAFFIC (5.41%)
EROSION CONTROL, INC.(2.80%)
JMHP, INC. (0.91%)
R & A TRANSPORT, INC.(3.11%)
Contract # 06143052
Totals 477521.30 0.00 531619.35 100.0

CountyBRAZORIA
Highway SH 288
From CR 56
To 0.35 MI S OF FM 1462 (FRTG RD)
CSJ 0598-02-097
Proj ID NH 2016(695)
Work Type PV REP, SC, ACP OL AND PV MKS
 
17.256 6895441.63 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 156
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-097
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163236
Totals 6895441.63 0.00 0.00 0.0