Letting Schedule for December, 2006 (FY 2007)
Letting Schedule for December, 2006 (FY 2007) | ||||
Last Update: Monday, July 30, 2007 |
December, 2006 (FY 2007) | (see Links) |
SEP 2006 | OCT 2006 | NOV 2006 | DEC 2006 | JAN 2007 | FEB 2007 | MAR 2007 | APR 2007 | MAY 2007 | JUN 2007 | JUL 2007 | AUG 2007 | ||||||
CCSJ | County/ District |
Highway | Let Status | Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0915-13-015 | Atascosa/ San Antonio |
CR | Actual | $261,724 | 6 | REPLACE BRIDGE AND APPROACHES |
0114-06-031 | Bastrop/ Austin |
US 290 | Actual | $3,735,687 | 1 | LVL - UP, SEAL, & PFC 2.31 MI PORTION |
0915-00-125 | Bexar/ San Antonio |
VA | Actual | $854,820 | 1 | SPOT BASE REPAIR |
0976-02-084 | Brazoria/ Houston |
FM 518 | Actual | $3,466,547 | 5 | RAISE MEDIANS, CEMENT TREATED BASE WIDEN, RCP, SIGNAL, SIGN |
0212-03-045 | Brazos/ Bryan |
FM 158 | Actual | $77,152 | 10 | MISCELLANEOUS WORK CONSISTING OF LANDSCAPE DEVELOPMENT |
0303-04-032 | Briscoe/ Childress |
SH 86 | Actual | $5,049,759 | 1 | BASE, SURFACE TREAT, HOTMIX, ADA |
0242-03-066 | Chambers/ Beaumont |
SH 61 | Actual | $1,688,652 | 11 | UPGRADE BRIDGE RAIL |
1225-01-013 | Childress/ Childress |
FM 1034 | Actual | $1,172,747 | 6 | REPLACE BRIDGE |
0047-06-131 | Collin/ Dallas |
US 75 | Actual | $200,000 | 7 | RAILROAD GRADE CROSSING REPLANKING |
0918-24-102 | Collin/ Dallas |
VA | Actual | $1,632,772 | 7 | PLANO TRANSIT VILLAGE - RECONSTRUCTION OF 15TH STREET AND |
1433-02-035 | Comal/ San Antonio |
FM 2252 | Actual | $30,080 | 10 | RAILROAD GRADE CROSSING REPLANKING |
0140-08-021 | Crockett/ San Angelo |
SH 290 | Actual | $3,963,252 | 10 | REPLACE BRIDGE AND APPROACHES |
0918-00-128 | Dallas/ Dallas |
VA | Actual | $797,730 | 1 | NON SITE SPECIFIC TRAFFIC SIGNAL INSTALLATIONS |
0918-45-367 | Dallas/ Dallas |
CS | Actual | $17,789,497 | 7 | WIDEN 2 LANE FACILITY TO 4 LANE FACILITY |
0918-45-671 | Dallas/ Dallas |
VA | Actual | $875,000 | 5 | ALTERNATIVE FUELS, CNG CONVERSION |
0918-45-775 | Dallas/ Dallas |
VA | Actual | $65,825 | 5 | 19 INTERSECTIONS - SIGNAL IMPROVEMENTS, LEDS AND GPS CLOCKS |
0918-45-794 | Dallas/ Dallas |
VA | Actual | $709,000 | 5 | CITYWIDE SIGNAL TIMING AND COMMUNICATIONS IMPROVEMENTS |
0924-06-280 | El Paso/ El Paso |
VA | Actual | $4,340,402 | 10 | INTELLIGENT TRANSPORTATION SYSTEM INSTALLATION AT THE BRIDGE |
0048-08-040 | Ellis/ Dallas |
IH 35E | Actual | $62,387,239 | 10 | REHABILITATE FREEWAY MAINLANES |
0902-49-059 | Erath/ Fort Worth |
CR | Actual | $569,096 | 10 | REPLACE BRIDGE AND APPROACHES |
0202-09-025 | Grayson/ Paris |
FM 697 | Actual | $4,772,210 | 1 | SEAL COAT |
0901-19-110 | Grayson/ Paris |
CR | Actual | $390,094 | 6 | REPLACE BRIDGE AND APPROACHES |
0065-05-133 | Hardin/ Beaumont |
US 96 | Actual | $4,726,919 | 1 | SEAL COAT |
0912-72-054 | Harris/ Houston |
VA | Actual | $1,700,430 | 10 | ADA CURB RAMP PROGRAM FY 06, VARIOUS LOCATIONS ON FM 1093, |
0495-08-090 | Harrison/ Atlanta |
IH 20 | Actual | $4,021,948 | 1 | PAVEMENT REPAIR, MICROSURFACING, AND PAVEMENT MARKINGS |
0255-06-054 | Hidalgo/ Pharr |
US 281 | Actual | $4,528,499 | 1 | ASPHALT CONCRETE PAVEMENT OVERLAY |
0901-22-041 | Hunt/ Paris |
VA | Actual | $1,355,312 | 9 | CONSTRUCTION AND REHAB OF SIDEWALKS AND CROSSWALKS, INSTALLA |
0356-01-092 | Hutchinson/ Amarillo |
SH 207 | Actual | $4,946,930 | 6 | REPLACE BRIDGE & APPR |
0307-01-133 | Jefferson/ Beaumont |
SH 87 | Actual | $2,795,582 | 6 | CONSTRUCT PIER PROTECTION AT BRIDGE |
0932-01-105 | Jefferson/ Beaumont |
FM 365 | Actual | $159,704 | 11 | UPGRADE DRAINAGE CROSSING |
0033-04-060 | Jones/ Abilene |
US 83 | Actual | $92,254 | 10 | LANDSCAPE IMPROVEMENTS |
0141-09-067 | Kimble/ San Angelo |
IH 10 | Actual | $10,578,545 | 1 | PFC AND HMACP OVERLAY |
0045-09-087 | Lamar/ Paris |
US 82 | Actual | $24,820 | 1 | INSTALL FLASHING BEACON |
0920-02-058 | Liberty/ Beaumont |
CR | Actual | $317,186 | 6 | REPLACE BRIDGE AND APPROACHES |
0053-01-106 | Lubbock/ Lubbock |
US 84 | Actual | $14,561,161 | 1 | OVERLAY |
0905-00-044 | Lubbock/ Lubbock |
VA | Actual | $494,572 | 1 | RAISED PAVEMENT MARKERS AND SPECIALITY MARKERS |
0905-06-065 | Lubbock/ Lubbock |
VA | Actual | $1,446,830 | 10 | DYNAMIC MESSAGE SIGN, FIBER OPTIC CABLE, SOFTWARE |
0179-04-087 | Matagorda/ Yoakum |
SH 35 | Actual | $529,205 | 11 | UPGRADE STORM SEWER |
0909-00-045 | McLennan/ Waco |
VA | Actual | $567,824 | 1 | NON - SITE SPECIFIC SIGNALS |
0035-06-030 | Menard/ San Angelo |
US 83 | Actual | $1,480,000 | 1 | RETRACE PAVEMENT MARKINGS |
1718-01-026 | Midland/ Odessa |
FM 1788 | Actual | $374,620 | 11 | TRAFFIC SIGNALS |
0920-06-022 | Newton/ Beaumont |
VA | Actual | $257,416 | 11 | COUNTY ROAD SIGN REPLACEMENT |
0916-35-125 | Nueces/ Corpus Christi |
CS | Actual | $1,151,028 | 6 | REPLACE BRIDGE AND APPROACHES |
0654-02-022 | Polk/ Lufkin |
FM 350 | Actual | $1,982,257 | 1 | SEAL COAT |
2002-03-017 | Randall/ Amarillo |
FM 1151 | Actual | $2,189,590 | 11 | HAZARD ELIMINATION |
0003-06-082 | Reeves/ Odessa |
IH 20 | Actual | $3,738,949 | 1 | PAVEMENT OVERLAY |
0390-05-005 | San Augustine/ Lufkin |
FM 2558 | Actual | $635,998 | 8 | SAFETY TREAT FIXED OBJECTS |
0395-02-032 | San Jacinto/ Lufkin |
SH 150 | Actual | $410,971 | 1 | INSTALL TRAFFIC SIGNALS AND MODIFY INTERSECTION ALIGNMENT |
0395-04-016 | San Jacinto/ Lufkin |
FM 222 | Actual | $1,599,690 | 1 | WIDEN ROADWAY 3' ON EACH SIDE, HMA LEVEL - UP |
0074-03-037 | San Patricio/ Corpus Christi |
IH 37 | Actual | $2,840,121 | 1 | POROUS FRICTION COURSE ON IH 37 SOUTH BOUND LANES |
0175-04-077 | Shelby/ Lufkin |
US 59 | Actual | $5,477,028 | 1 | SEAL COAT |
0038-06-038 | Starr/ Pharr |
US 83 | Actual | $2,677,268 | 1 | SEAL COAT |
0039-01-065 | Starr/ Pharr |
US 83 | Actual | $32,905 | 10 | LANDSCAPE AND IRRIGATION IMPROVEMENTS |
0718-02-058 | Tarrant/ Fort Worth |
FM 156 | Actual | $91,700 | 1 | INSTALLATION OF FULL TRAFFIC ACTUATED TRAFFIC SIGNAL |
0902-48-646 | Tarrant/ Fort Worth |
VA | Actual | $289,907 | 5 | SIGNAL INTEGRATION & MONITORING PHASE 3 |
0902-48-650 | Tarrant/ Fort Worth |
VA | Actual | $1,110,201 | 5 | SIGNAL INTERGRATION & MONITORING PHASE 3 |
0902-48-668 | Tarrant/ Fort Worth |
VA | Actual | $1,625,000 | 5 | SECOND TRACK ADDITION PE FOR TRANSFER; UPGRADE THE CLASS 1 |
0902-48-669 | Tarrant/ Fort Worth |
VA | Actual | $1,500,000 | 5 | DESIGN AND INITIAL CONSTRUCTION FOR TRANSIT PLAZA |
0902-48-670 | Tarrant/ Fort Worth |
VA | Actual | $19,968,750 | 5 | CENTREPORT EXPANSION ON TRE |
0914-04-204 | Travis/ Austin |
CS | Actual | $1,048,501 | 6 | REHABILITATE BRIDGE & APPROACHES |
0018-03-039 | Webb/ Laredo |
IH 35 | Actual | $6,914,478 | 1 | FOR THE CONSTRUCTION OF SEAL COAT TYPE OF WORK (WEST FRONTAG |
0922-33-075 | Webb/ Laredo |
CR | Actual | $729,483 | 6 | REPLACE BRIDGE AND APPROACHES |
0089-15-016 | Wharton/ Yoakum |
BU 59-S | Actual | $1,183,596 | 6 | REPLACE BRIDGE AND APPROACHES |
0030-09-038 | Wheeler/ Childress |
US 83 | Actual | $5,727,390 | 1 | REHABILITATION OF ROADWAY |
0151-04-061 | Williamson/ Austin |
US 183 | Actual | $919,092 | 10 | ACC / DEC LANE & LTL |
|
|