Letting Schedule for Wichita Falls District (FY 2016)

Last Update: Tuesday, November 25, 2014
Wichita Falls District (FY 2016)
Clay | Wichita | Wilbarger

Clay County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0282-01-016 SH 79 Tentative AUG 2016 $5,597,000 6 REPLACE BRIDGE

Wichita County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0802-02-052 FM 369 Tentative MAY 2016 $2,000,001 11 ENCLOSE DRAINAGE DITCH
0903-03-071 VA Tentative MAY 2016 $4,150,000 11 GRADING, STRUCTURES, BASE AND SURFACING

Wilbarger County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0702-01-014 FM 91 Tentative APR 2016 $255,000 6 REPLACE BRIDGE AND APPROACHES


Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract