Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
County | KAUFMAN |
Highway |
FM 3039 |
From |
FM 1389 |
To |
FM 148 |
CSJ |
3089-01-010 |
Proj ID |
STP 2014(769) |
Work Type |
REWORK, CEMENT TR BS, SURF, PVMT MRKGS |
|
|
3.965 |
3913714.36 |
520522.53 |
3565776.68 |
91.1 |
Work Order |
08-20-14 |
Work Began |
10-20-14 |
Work Completed |
|
Time Computed |
10-20-14 |
Contract Working Days |
158 |
Addl Days Granted |
137 |
Working Days Charged |
272 |
Percent Time Used |
92 |
Contractor(s) |
A. L. HELMCAMP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 3089-01-010 ALTUS TRAFFIC MANAGEMENT LLC (0.35%) FORTSON CONTRACTING, INC.(2.93%) J & M CONTRACTING, COMPANY (5.72%) MARCOM"S MOWING SERVICE, LLC (0.39%) S & S TRUCKING (1.53%) TOTAL HIGHWAY MAINTENANCE, LLC (1.23%)
|
Contract # |
06143220 |
|
Totals |
3913714.36 |
520522.53 |
3565776.68 |
91.1 |
|
County | KAUFMAN |
Highway |
FM 148 |
From |
FM 3094 SOUTH |
To |
FM 3094 NORTH |
CSJ |
3146-01-006 |
Proj ID |
STP 1502(499) |
Work Type |
MILL, REPAIR, OL, STR, MRKS, SIGNS |
|
|
2.767 |
3178556.05 |
447496.89 |
464991.89 |
14.6 |
Work Order |
12-21-15 |
Work Began |
02-26-16 |
Work Completed |
|
Time Computed |
02-22-16 |
Contract Working Days |
192 |
Addl Days Granted |
0 |
Working Days Charged |
25 |
Percent Time Used |
13 |
Contractor(s) |
A. L. HELMCAMP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 3146-01-006 ALTUS TRAFFIC MANAGEMENT LLC (0.54%) AUSTIN BRIDGE & ROAD SERVICES, LP( 18.60%) FORTSON CONTRACTING, INC.(1.11%) MARCOM"S MOWING SERVICE, LLC (0.68%) STRIPING TECHNOLOGY, L.P.(0.74%) W.S. CONSTRUCTION COMPANY( 16.86%) KENSAR LLC DBA S & S TRUCKING(7.31%)
|
Contract # |
10153231 |
|
Totals |
3178556.05 |
447496.89 |
464991.89 |
14.6 |
|
County | ROCKWALL |
Highway |
FM 3097 |
From |
FM 740 |
To |
EAST OF TUBBS ROAD |
CSJ |
3148-01-006 |
Proj ID |
STP 2013(597)MM |
Work Type |
WIDEN ROADWAY |
|
|
0.906 |
9349455.02 |
393635.98 |
1496242.07 |
16.0 |
Work Order |
09-15-14 |
Work Began |
01-19-16 |
Work Completed |
|
Time Computed |
01-13-15 |
Contract Working Days |
362 |
Addl Days Granted |
0 |
Working Days Charged |
62 |
Percent Time Used |
17 |
Contractor(s) |
ED BELL CONSTRUCTION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 3148-01-006 WYLIE DRILLING & DRAINAGE, INC.(0.82%) SCOTT DERR PAINTING CO (0.07%) W.O.E. CONSTRUCTION(0.20%) SYNERGY SIGNS & SERVICES, LLC(0.22%) BRENDA PRICE TRUCKING(3.31%) HAYWARD BAKER, INC.(1.63%) STRIPING TECHNOLOGY, L.P.(0.85%) USA SWPPP INSPECTIONS, INC.(0.68%) PREMIER PAVING, LTD. ( 10.75%) FORTSON CONTRACTING, INC.(0.04%) DURABLE SPECIALTIES, INC.(6.96%) DUSTROL, INC.(1.32%) BROCK ENVIRONMENTAL SERVICES, LLC(0.40%) MCL CONTRACTING, LLC (0.68%) FANNIN TREE FARM, LTD(0.17%)
|
Contract # |
07143235 |
|
Totals |
9349455.02 |
393635.98 |
1496242.07 |
16.0 |
|
County | COLLIN |
Highway |
FM 2786 |
From |
SH 5 |
To |
EAST OF ANGEL PARKWAY IN ALLEN |
CSJ |
3392-01-008 |
Proj ID |
STP 2015(397)MM |
Work Type |
STR, PVMT, SIGNS, MEDIAN |
|
|
0.926 |
7976761.50 |
0.00 |
0.00 |
0.0 |
County | COLLIN |
Highway |
FM 2786 |
From |
EAST OF ANGEL PKWY IN ALLEN |
To |
FM 1378 |
CSJ |
3392-01-009 |
Proj ID |
C 3392-1-9 |
Work Type |
PVMT, DRAINAGE, SIGNS, MEDIAN |
|
|
1.008 |
7822942.39 |
28100.00 |
28100.00 |
0.3 |
Work Order |
01-16-15 |
Work Began |
00-00-00 |
Work Completed |
|
Time Computed |
07-15-15 |
Contract Working Days |
483 |
Addl Days Granted |
0 |
Working Days Charged |
0 |
Percent Time Used |
0 |
Contractor(s) |
ED BELL CONSTRUCTION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 3392-01-008 WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.61%) DURABLE SPECIALTIES, INC.(2.47%) OSCAR ORDUNO, INC. (1.10%) BREDA COMPANY, INC.(0.64%) BRENDA PRICE TRUCKING(0.06%) SCOTT DERR PAINTING CO, LLC(0.03%) TEX OP CONSTRUCTION, LP(1.10%) W.O.E. CONSTRUCTION(0.25%) LONE STAR BARRIER SERVICES, LLC(0.16%) PREMIER PAVING, LTD. ( 10.71%) STRIPING TECHNOLOGY, L.P.(0.88%)
|
Contract # |
12143203 |
|
Totals |
15799703.89 |
28100.00 |
28100.00 |
0.1 |
|