Letting Schedule for March, 2005 (FY 2005)

 
 
Last Update: Monday, August 15, 2005
March, 2005 (FY 2005) (see Links)
SEP 2004 | OCT 2004 | NOV 2004 | DEC 2004 | JAN 2005 | FEB 2005 | MAR 2005 | APR 2005 | MAY 2005 | JUN 2005 | JUL 2005 | AUG 2005
CCSJ County/
District
Highway Let Status Contract
Cost
Fund
Cat
Description
3162-01-009 Angelina/
Lufkin
FM 819 Actual $90,902 1 INSTALL TRAFFIC SIGNALS
0903-29-018 Archer/
Wichita Falls
VA Actual $219,645 10 EARTHWORK AND SEALCOAT
0101-07-015 Bee/
Corpus Christi
BU 181J Actual $1,784,347 1 REPLACE BRIDGE
1531-01-013 Borden/
Abilene
FM 1610 Actual $266,118 1 SPOT BASE REPAIR
0923-00-045 Brown/
Brownwood
VA Actual $175,640 1 ACCESSIBILITY FACILITIES CONSISTING OF CURB RAMPS
3477-01-003 Cameron/
Pharr
FM 3462 Actual $1,827,747 1 RECONSTRUCT AND ADD SHOULDERS
0919-00-061 Cass/
Atlanta
VA Actual $106,108 1 REMOVE BARRIERS TO COMPLY WITH ADA
1574-02-017 Cass/
Atlanta
FM 161 Actual $470,720 1 REHABILITATE EXISTING 2 - LANE RURAL HIGHWAY
0913-26-049 Colorado/
Yoakum
VA Actual $262,430 10 LANDSCAPE DEVELOPMENT AND SCENIC ENHANCEMENT
1356-01-023 Cooke/
Wichita Falls
FM 1201 Actual $1,367,345 1 ASPHALTIC CONCRETE PAVEMENT OVERLAY
2964-01-034 Dallas/
Dallas
SH 161 Actual $9,432,432 2 COURT MANDATED MITIGATION FOR PARKS IMPACTED BY SH 161
0136-13-009 Delta/
Paris
BS 24-D Actual $1,578,148 1 MILLING AND OVERLAY
0195-02-056 Denton/
Dallas
US 77 Actual $299,984 10 LANDSCAPE DEVELOPMENT
0923-09-038 Eastland/
Brownwood
VA Actual $2,688,705 1 GRADING, STRUCTURES, PLANING, BASE, ACP ON RAMPS AND
2121-04-072 El Paso/
El Paso
IH 10 Actual $238,445 5 TMC EMERGENCY & BACKUP POWER PROJECT
0079-04-047 Erath/
Fort Worth
US 67 Actual $576,625 1 OVERLAY WITH 2 INCHES
1105-01-015 Fayette/
Yoakum
FM 1291 Actual $1,307,933 1 RESTORE ROADWAY
0543-02-053 Fort Bend/
Houston
FM 359 Actual $300,000 7 PRELIMINARILY ENGINEERING AND ENVIRONMENTAL ANALYSIS
0543-03-056 Fort Bend/
Houston
FM 762 Actual $290,000 7 PRELIMINARILY ENGINEERING AND ENVIRONMENTAL ANALYSIS
0912-34-109 Fort Bend/
Houston
CS Actual $340,000 7 PRELIMINARILY ENGINEERING AND ENVIRONMENTAL ANALYSIS
0901-21-007 Franklin/
Paris
CR Actual $768,250 6 REPLACE BRIDGE AND APPROACHES
0389-06-093 Galveston/
Houston
SH 146 Actual $5,188,724 1 BASE REPAIR, OVERLAY AND SHOULDER LEVELUP
0389-07-032 Galveston/
Houston
SH 146 Actual $1,043,632 1 BASE REPAIR, OVERLAY AND SHOULDER LEVELUP
0500-01-131 Galveston/
Houston
IH 45 Actual $1,189,174 1 PAINTING, JOINT REPAIRS AND OVERLAY OF SANTA FE RAILROAD
0275-23-002 Gray/
Amarillo
BI 40-H Actual $4,095,124 1 REHAB EXISTING BRIDGE
0271-07-249 Harris/
Houston
IH 10 Actual 152,535,376 11 RECONSTRUCT & WIDEN TO 8 MAINLANES, 4 MANAGED LANES & TWO
0271-17-150 Harris/
Houston
IH 610 Actual $577,225 10 LANDSCAPE DEVELOPMENT IN BELLAIRE
0912-00-076 Harris/
Houston
VA Actual $1,267,665 7 FY 2005 CAPITAL UPGRADE (FUNDING FOR PURCHASE OF SOFTWARE /
0912-00-280 Harris/
Houston
VA Actual $646,971 1 REPLACE RAISED REFLECTIVE PAVEMENT MARKERS
0912-00-301 Harris/
Houston
VA Actual $2,200,000 5 FY 2005 CONTINUATION OF ALTERNATIVE FUEL PROGRAM
0912-71-827 Harris/
Houston
VA Actual $1,500,000 11 INTELLIGENCE TRANSPORTATION SYSTEM MAINTENANCE
0912-71-867 Harris/
Houston
VA Actual $689,307 1 INSTALL SIDEWALK & SLOTTED CURB (SAFE ROUTES TO SCHOOLS)
0912-71-890 Harris/
Houston
VA Actual $1,070,097 1 REPLACE PAVEMENT MARKINGS & RAISED REFLECTIVE PAVEMENT
2941-02-043 Harris/
Houston
FM 2920 Actual $1,424,096 1 BASE REPAIR, PLANING, LEVEL - UP, ONE COURSE SURFACE TREATMENT
0921-00-058 Hidalgo/
Pharr
VA Actual $942,783 1 NON - SITE SPECIFIC TRAFFIC SIGNALS
0902-51-019 Hood/
Fort Worth
VA Actual $100,000 10 PURCHASE OF LANDSCAPE MATERIALS AND INSTALLATION
0083-11-023 Hunt/
Paris
LP 178 Actual $98,000 1 TRAFFIC SIGNAL
0920-12-024 Jasper/
Beaumont
CR Actual $475,354 6 REPLACE BRIDGE AND APPROACHES
2120-01-023 Jasper/
Beaumont
FM 2246 Actual $1,553,933 11 OVERLAY EXISTING ROADWAY
0368-02-040 Jefferson/
Beaumont
SH 124 Actual $2,970,372 1 REHABILITATE EXISTING ROADWAY
0920-00-068 Jefferson/
Beaumont
VA Actual $1,018,229 11 RESTRIPING EXISTING ROADWAYS
0902-50-087 Johnson/
Fort Worth
VA Actual $100,000 10 PURCHASE OF LANDSCAPE MATERIALS AND INSTALLATION
0495-01-050 Kaufman/
Dallas
IH 20 Actual $2,791,797 1 RESTORATION OF IH 20 FOLLOWING EXPIRATION OF TOTAL MAINT
1091-01-013 Kaufman/
Dallas
FM 740 Actual $2,186,530 11 RECONSTRUCT EXISTING 2 - LANE ROADWAY TO 4 - LANES
0496-02-015 Knox/
Childress
SH 222 Actual $1,998,824 11 ADA / SIDWALKS / OVERLAY
1344-01-011 Lynn/
Lubbock
FM 1317 Actual $713,584 1 OVERLAY
0209-07-031 McLennan/
Waco
FM 933 Actual $12,467,099 11 ADD TWO LANES AND CONTINUOUS LEFT TURN LANE
2104-01-006 Medina/
San Antonio
FM 1957 Actual $313,347 11 WIDEN ROADWAY FOR THE ADDITION OF A LEFT TURN LANE AND
0906-32-038 Midland/
Odessa
VA Actual $388,020 9 HIKE AND BIKE TRAIL
0110-03-035 Montgomery/
Houston
SH 75 Actual $3,393,439 1 WIDEN TO 4 - LANE DIVIDED WITH CURB AND GUTTER
2263-02-078 Nueces/
Corpus Christi
SH 361 Actual $4,597,629 11 CONSTR NEW FERRY LANDINGS AND APPROACHES
0243-04-046 Orange/
Beaumont
SH 62 Actual $2,194,457 1 REHABILITATE EXISTING ROADWAY
2288-01-010 Palo Pinto/
Fort Worth
FM 1821 Actual $58,300 10 INSTALL TRAFFIC SIGNAL
0394-03-032 Panola/
Atlanta
FM 699 Actual $3,412,347 1 REHABILITATION OF EXISTING 2 - LANE RURAL HIGHWAY
0008-02-067 Parker/
Fort Worth
US 180 Actual $3,017,018 1 MILL, BASE REPAIR / LEVEL UP AND OVERLAY
0008-03-090 Parker/
Fort Worth
US 180 Actual $392,882 10 REPLACE VEGETATION WITH STAMPED AND COLORED ASPHALT
0313-07-015 Parker/
Fort Worth
FM 51 Actual $1,362,243 1 HMAC OVERLAY
0902-38-038 Parker/
Fort Worth
CR Actual $749,397 6 REPLACE BRIDGE AND APPROACHES
0902-38-042 Parker/
Fort Worth
CR Actual $475,162 6 REPLACE BRIDGE AND APPROACHES
0902-38-051 Parker/
Fort Worth
CR Actual $262,409 6 REPLACE BRIDGE
0902-38-053 Parker/
Fort Worth
CR Actual $446,172 6 REPLACE BRIDGE
0902-38-061 Parker/
Fort Worth
VA Actual $100,000 10 PURCHASE OF LANDSCAPE MATERIALS AND INSTALLATION
0140-04-041 Pecos/
Odessa
IH 10 Actual $3,246,018 1 PAVEMENT OVERLAY
0904-00-092 Potter/
Amarillo
VA Actual $628,600 11 UPGRADE SIGNAL SYSTEM
0074-05-086 San Patricio/
Corpus Christi
IH 37 Actual $2,727,166 2 FREEWAY MANAGEMENT SYSTEM
0008-05-025 Tarrant/
Fort Worth
SH 180 Actual $2,885,039 1 MILL AND 2" OVERLAY
0008-12-085 Tarrant/
Fort Worth
IH 20 Actual $270,000 1 UPGRADE CONTROL ROOM VIDEO PROJECTOR SYSTEM IN TRANSVISION
0094-01-035 Tarrant/
Fort Worth
SH 183 Actual $89,400 8 IMPROVE TRAFFIC SIGNAL
0902-48-614 Tarrant/
Fort Worth
VA Actual $546,189 10 MATERIALS PURCHASE OF LANDSCAPING ITEMS AND INSTALLATION
0902-48-617 Tarrant/
Fort Worth
VA Actual $298,145 5 SIGNAL TIMING OPTIMIZATION ON FM1938, IH820, SH26 & FM3029
0033-06-097 Taylor/
Abilene
US 83 Actual $2,819,678 1 MILLING, UNDERSEAL, ASPHALTIC CONCRETE PAVEMENT AND METAL
0556-05-019 Terrell/
Odessa
SH 349 Actual $3,299,035 1 ROADWAY REHABILITATION
0914-04-170 Travis/
Austin
VA Actual $590,594 7 CONST BIKE LANES ON EXISTING ROADWAY
0200-07-046 Tyler/
Beaumont
US 69 Actual $8,454,038 1 REHABILITATE EXISTING ROADWAY
0495-03-055 Van Zandt/
Tyler
IH 20 Actual $2,412,234 1 REPLACE BRIDGE AND APPROACHES
0088-05-082 Victoria/
Yoakum
US 59 Actual $7,562,015 1 ASPHALTIC CONCRETE PAVEMENT
0050-04-025 Waller/
Houston
SH 6 Actual $3,142,056 1 BASE REPAIR, PLANING, ONE COURSE SURFACE TREATMENT,


Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract