Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
|
February, 2021 (FY 2021) | (see Links) |
SEP 2020 | OCT 2020 | NOV 2020 | DEC 2020 | JAN 2021 | FEB 2021 | MAR 2021 | APR 2021 | MAY 2021 | JUN 2021 | JUL 2021 | AUG 2021 | | |||||||
CCSJ | County/ District | Highway | Let Status | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
1157-01-018 | Angelina/ Lufkin | FM 841 | Actual | $5,172,350 | 8 | REPLACE GUARDRAIL | 6.0 |
0915-00-224 | Bexar/ San Antonio | VA | Actual | $2,172,495 | 1 | HIGHWAY IMPROVEMENT | 7.0 |
0915-12-679 | Bexar/ San Antonio | VA | Actual | $7,553,334 | 3 | TRANSIT | 0.0 |
0915-12-680 | Bexar/ San Antonio | VA | Actual | $2,181,429 | 3 | TRANSIT SYSTEM OPERATIONS | 0.0 |
0915-00-228 | Bexar/ San Antonio | VA | Actual | $1,496,283 | 1 | TRAFFIC SIGNAL IMPROVEMENTS | 3.0 |
0915-12-633 | Bexar/ San Antonio | CS | Actual | $933,602 | 3 | HAZARD ELIMINATION & SAFETY | 0.0 |
0179-02-085 | Brazoria/ Houston | BS 35-E | Actual | $946,362 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
1375-01-011 | Caldwell/ Austin | FM 1322 | Actual | $4,737,143 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0921-06-304 | Cameron/ Pharr | CS | Actual | $812,862 | 3 | TRANSPORTATION NON-ROADWAY | 0.0 |
0634-01-014 | Cherokee/ Tyler | FM 22 | Actual | $5,329,290 | 8 | HAZARD ELIMINATION & SAFETY | 3.5 |
3236-02-012 | Collin/ Dallas | FM 3133 | Actual | $7,303,416 | 1 | HAZARD ELIMINATION & SAFETY | 9.0 |
0195-01-119 | Cooke/ Wichita Falls | IH 35 | Actual | $214,383,174 | 1 | WIDEN ROAD - ADD LANES | 9.0 |
0918-47-215 | Dallas/ Dallas | CS | Actual | $2,059,691 | 3 | TRAFFIC SIGNAL IMPROVEMENTS | 6.0 |
0918-48-003 | Dallas/ Dallas | VA | Actual | $14,980,000 | 5 | BICYCLE AND PEDESTRIAN IMPROVEMENTS | 0.0 |
0047-07-228 | Dallas/ Dallas | US 75 | Actual | $10,461,667 | 3 | BICYCLE AND PEDESTRIAN IMPROVEMENTS | 8.5 |
0134-09-067 | Denton/ Dallas | US 380 | Actual | $1,829,261 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0007-03-097 | Eastland/ Brownwood | IH 20 | Actual | $5,211,370 | 8 | HAZARD ELIMINATION & SAFETY | 6.0 |
0924-00-143 | El Paso/ El Paso | VA | Actual | $584,867 | 1 | REPLACE GUARDRAIL | 0.0 |
0924-00-144 | El Paso/ El Paso | VA | Actual | $1,574,143 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0267-03-030 | Fayette/ Yoakum | FM 609 | Actual | $4,114,215 | 1 | SURFACING/ROADWAY RESTORATION | 2.0 |
1685-06-036 | Fort Bend/ Houston | SH 6 | Actual | $2,219,345 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0976-03-111 | Galveston/ Houston | FM 518 | Actual | $2,935,761 | 10 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 7.0 |
0516-02-029 | Goliad/ Corpus Christi | SH 239 | Actual | $7,795,715 | 1 | REHABILITATE EXISTING ROADWAY | 7.0 |
0901-19-191 | Grayson/ Paris | CR | Actual | $351,583 | 6 | BRIDGE REPLACEMENT | 0.0 |
0912-00-576 | Harris/ Houston | VA | Actual | $1,300,000 | 1 | ADVANCED TRAFFIC MANAGEMENT SYSTEM | 0.0 |
1685-01-110 | Harris/ Houston | FM 1960 | Actual | $5,117,781 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0111-01-095 | Harris/ Houston | FM 521 | Actual | $1,397,202 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0912-00-575 | Harris/ Houston | VA | Actual | $2,750,000 | 1 | UPGRADE DYNAMIC MESSAGE SIGN BOARDS | 0.0 |
0113-07-074 | Hays/ Austin | US 290 | Actual | $2,956,176 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
1427-01-040 | Hidalgo/ Pharr | FM 1423 | Actual | $5,649,564 | 1 | PREVENTIVE MAINTENANCE | 2.0 |
0002-06-059 | Hudspeth/ El Paso | IH 10 | Actual | $3,269,099 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0374-04-035 | Hudspeth/ El Paso | US 62 | Actual | $1,842,014 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0920-00-131 | Jefferson/ Beaumont | VA | Actual | $2,368,838 | 1 | HAZARD ELIMINATION & SAFETY | 0.0 |
0019-02-034 | Johnson/ Ft Worth | SH 171 | Actual | $7,523,308 | 1 | RESURFACE ROADWAY | 3.0 |
0173-04-060 | Kaufman/ Dallas | SH 34 | Actual | $1,236,816 | 8 | HAZARD ELIMINATION & SAFETY | 6.0 |
2982-01-007 | Kaufman/ Dallas | FM 1390 | Actual | $8,344,338 | 1 | ADDING SHOULDERS WITH NO ADDED CAPACITY | 0.0 |
0675-03-067 | Leon/ Bryan | IH 45 | Actual | $1,331,115 | 1 | HIGHWAY IMPROVEMENT | 6.5 |
0905-00-103 | Lubbock/ Lubbock | VA | Actual | $2,287,029 | 1 | HAZARD ELIMINATION & SAFETY | 0.0 |
0905-00-108 | Lubbock/ Lubbock | VA | Actual | $936,253 | 1 | HAZARD ELIMINATION & SAFETY | 0.0 |
0843-03-015 | Marion/ Atlanta | FM 728 | Actual | $1,241,076 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0913-21-053 | Matagorda/ Yoakum | CR | Actual | $91,275 | 1 | EMBANKMENT STABILIZATION | 0.0 |
0005-14-067 | Midland/ Odessa | IH 20 | Actual | $39,047,179 | 11 | CONSTRUCT BRIDGE | 8.5 |
0055-01-029 | Mills/ Brownwood | US 84 | Actual | $3,713,250 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0305-01-035 | Newton/ Beaumont | SH 87 | Actual | $1,707,126 | 11 | SURFACING/ROADWAY RESTORATION | 0.0 |
0904-02-045 | Potter/ Amarillo | VA | Actual | $308,870 | 8 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0104-05-025 | Presidio/ El Paso | SH 17 | Actual | $922,393 | 1 | SURFACING/ROADWAY RESTORATION | 4.0 |
0168-08-073 | Randall/ Amarillo | US 60 | Actual | $3,792,890 | 8 | INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT TURN LANES | 6.0 |
0180-02-041 | Refugio/ Corpus Christi | SH 35 | Actual | $5,718,658 | 1 | WIDEN ROAD - ADD LANES | 0.0 |
0160-02-025 | Sutton/ San Angelo | US 277 | Actual | $23,984,402 | 1 | HIGHWAY IMPROVEMENT | 6.0 |
0081-01-049 | Tarrant/ Ft Worth | US 377 | Actual | $1,527,431 | 1 | RESURFACE ROADWAY | 0.0 |
0158-02-092 | Tom Green/ San Angelo | US 67 | Actual | $1,262,325 | 1 | BRIDGE MAINTENANCE | 0.0 |
0922-11-036 | Val Verde/ Laredo | CS | Actual | $1,500,000 | 3 | REHABILITATE EXISTING ROADWAY | 0.0 |
0022-07-031 | Val Verde/ Laredo | US 90 | Actual | $9,284,312 | 1 | RESURFACE ROADWAY | 0.0 |
0495-03-065 | Van Zandt/ Tyler | IH 20 | Actual | $4,075,842 | 8 | REPLACE GUARDRAIL | 7.0 |
2850-01-018 | Walker/ Bryan | FM 2821 | Actual | $2,215,967 | 11 | INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT TURN LANES | 7.0 |
0050-04-027 | Waller/ Houston | SH 6 | Actual | $5,968,402 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0922-33-178 | Webb/ Laredo | CS | Actual | $10,300,000 | 3 | TRANSPORTATION NON-ROADWAY | 0.0 |
1302-02-013 | Wharton/ Yoakum | FM 647 | Actual | $1,273,088 | 6 | BRIDGE REPLACEMENT | 2.0 |
0802-02-069 | Wichita/ Wichita Falls | FM 369 | Actual | $2,774,532 | 1 | INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT TURN LANES | 8.0 |
0903-03-117 | Wichita/ Wichita Falls | CS | Actual | $1,528,750 | 3 | HIKE AND/OR BIKE | 0.0 |
2690-01-036 | Williamson/ Austin | FM 971 | Actual | $8,755,739 | 1 | ADDING SHOULDERS WITH NO ADDED CAPACITY | 7.5 |
2211-02-031 | Williamson/ Austin | FM 1460 | Actual | $1,265,719 | 1 | RESURFACE ROADWAY | 0.0 |
0401-02-034 | Wood/ Tyler | SH 154 | Actual | $746,399 | 3 | WIDEN ROAD - ADD SHOULDERS | 0.0 |
|