Letting Schedule for June, 2021 County (FY 2021)
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
|
June, 2021 (FY 2021) | (see Links) |
SEP 2020 | OCT 2020 | NOV 2020 | DEC 2020 | JAN 2021 | FEB 2021 | MAR 2021 | APR 2021 | MAY 2021 | JUN 2021 | JUL 2021 | AUG 2021 | | |||||||
CCSJ | County/ District | Highway | Let Status | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
1837-01-014 | Archer/ Wichita Falls | FM 1954 | Actual | $5,023,077 | 11 | SURFACING/ROADWAY RESTORATION | 8.0 |
2452-02-128 | Bexar/ San Antonio | SL 1604 | Actual | $256,245,119 | 1 | WIDEN ROAD - ADD LANES | 11.0 |
0073-02-080 | Bexar/ San Antonio | US 281 | Actual | $5,066,580 | 1 | INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT TURN LANES | 0.0 |
0085-03-017 | Bowie/ Atlanta | FM 2735 | Actual | $1,761,238 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
2523-02-073 | Brazoria/ Houston | FM 2004 | Actual | $706,416 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0540-08-008 | Brazos/ Bryan | SH 40 | Actual | $2,856,026 | 8 | HAZARD ELIMINATION & SAFETY | 7.5 |
0923-06-083 | Brown/ Brownwood | CR | Actual | $417,194 | 6 | BRIDGE REPLACEMENT | 4.0 |
0684-02-014 | Cameron/ Pharr | FM 511 | Actual | $986,990 | 1 | BRIDGE REPLACEMENT | 4.0 |
0010-10-026 | Cass/ Atlanta | US 67 | Actual | $6,412,223 | 6 | BRIDGE REPLACEMENT | 3.0 |
0031-05-045 | Childress/ Childress | US 62 | Actual | $4,045,918 | 6 | BRIDGE MAINTENANCE | 5.5 |
0042-12-082 | Childress/ Childress | US 287 | Actual | $2,162,942 | 6 | BRIDGE REPLACEMENT | 5.0 |
2845-01-022 | Collin/ Dallas | FM 455 | Actual | $4,769,556 | 1 | ADDING SHOULDERS WITH NO ADDED CAPACITY | 8.0 |
0797-07-032 | Collingsworth/ Childress | FM 1547 | Actual | $1,145,447 | 1 | BRIDGE REPLACEMENT | 4.5 |
0016-05-120 | Comal/ San Antonio | IH 35 | Actual | $5,591,576 | 1 | HIGHWAY IMPROVEMENT | 0.0 |
1268-01-013 | Comal/ San Antonio | FM 1103 | Actual | $40,975,029 | 1 | WIDEN ROAD - ADD LANES | 0.0 |
0513-01-017 | Coryell/ Waco | SH 236 | Actual | $5,176,664 | 1 | BRIDGE REPLACEMENT | 6.5 |
0581-01-159 | Dallas/ Dallas | SL 12 | Actual | $2,476,944 | 8 | HAZARD ELIMINATION & SAFETY | 7.0 |
0918-00-347 | Dallas/ Dallas | VA | Actual | $1,503,000 | 3 | BICYCLE AND PEDESTRIAN IMPROVEMENTS | 0.0 |
0261-02-079 | Dallas/ Dallas | US 67 | Actual | $2,465,544 | 3 | LANDSCAPE DEVELOPMENT | 0.0 |
0197-02-129 | Dallas/ Dallas | US 175 | Actual | $172,482 | 3 | LANDSCAPE DEVELOPMENT | 0.0 |
0353-09-002 | Denton/ Dallas | SH 114 | Actual | $41,100,125 | 11 | INTERCHANGE IMPROVEMENT | 0.0 |
0288-03-032 | Eastland/ Brownwood | SH 16 | Actual | $1,747,469 | 1 | BRIDGE REPLACEMENT | 4.5 |
0906-00-200 | Ector/ Odessa | VA | Actual | $440,651 | 1 | INFRASTRUCTURE IMPROVEMENTS | 0.0 |
0924-06-562 | El Paso/ El Paso | VA | Actual | $10,339,730 | 3 | LANDSCAPE DEVELOPMENT | 0.0 |
3451-01-035 | El Paso/ El Paso | FM 1281 | Actual | $6,441,872 | 8 | HAZARD ELIMINATION & SAFETY | 7.0 |
0924-06-549 | El Paso/ El Paso | VA | Actual | $716,107 | 3 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0374-02-115 | El Paso/ El Paso | US 62 | Actual | $1,414,745 | 8 | HAZARD ELIMINATION & SAFETY | 6.0 |
0001-01-062 | El Paso/ El Paso | SH 20 | Actual | $4,780,284 | 8 | HAZARD ELIMINATION & SAFETY | 4.5 |
0173-01-050 | Ellis/ Dallas | SH 34 | Actual | $934,955 | 8 | INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT TURN LANES | 7.0 |
0550-02-050 | Erath/ Ft Worth | FM 8 | Actual | $8,255,309 | 1 | REHABILITATE EXISTING ROADWAY | 0.0 |
0550-02-052 | Erath/ Ft Worth | FM 8 | Actual | $609,326 | 1 | HAZARD ELIMINATION & SAFETY | 0.0 |
0902-49-077 | Erath/ Ft Worth | VA | Actual | $330,000 | 8 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
0902-49-070 | Erath/ Ft Worth | CS | Actual | $344,851 | 8 | INSTALL TRAFFIC SIGNAL | 0.0 |
0026-02-034 | Fayette/ Yoakum | US 90 | Actual | $2,999,043 | 1 | SURFACING/ROADWAY RESTORATION | 4.0 |
0266-01-086 | Fayette/ Yoakum | SH 71 | Actual | $3,254,483 | 8 | HAZARD ELIMINATION & SAFETY | 3.0 |
0983-02-022 | Fisher/ Abilene | FM 419 | Actual | $1,473,540 | 6 | BRIDGE REPLACEMENT | 0.0 |
1133-02-032 | Gonzales/ Yoakum | FM 794 | Actual | $6,350,418 | 8 | HAZARD ELIMINATION & SAFETY | 4.0 |
1861-02-024 | Gray/ Amarillo | RM 1321 | Actual | $3,527,838 | 6 | BRIDGE REPLACEMENT | 7.5 |
0067-06-060 | Hale/ Lubbock | IH 27 | Actual | $226,016 | 8 | INSTALL/REHABILITATE ITS | 0.0 |
0912-72-610 | Harris/ Houston | VA | Actual | $3,214,098 | 8 | HIGHWAY IMPROVEMENT | 0.0 |
0502-01-222 | Harris/ Houston | SH 225 | Actual | $1,709,474 | 1 | REHABILITATE EXISTING ROADWAY | 0.0 |
0062-07-096 | Harrison/ Atlanta | US 59 | Actual | $565,099 | 8 | INSTALL ILLUMINATION | 0.0 |
0495-08-130 | Harrison/ Atlanta | IH 20 | Actual | $1,924,393 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0041-01-048 | Hartley/ Amarillo | US 87 | Actual | $482,892 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0914-33-068 | Hays/ Austin | CR | Actual | $21,369,599 | 3 | CONSTRUCT NEW ROAD | 0.0 |
0921-02-311 | Hidalgo/ Pharr | CR | Actual | $703,040 | 3 | WIDEN ROAD - ADD LANES AND SHOULDERS | 0.0 |
0109-03-036 | Houston/ Lufkin | US 287 | Actual | $1,884,651 | 8 | REPLACE GUARDRAIL | 5.5 |
0911-28-049 | Houston/ Lufkin | CR | Actual | $1,758,952 | 6 | BRIDGE REPLACEMENT | 3.5 |
0764-03-018 | Hunt/ Paris | FM 903 | Actual | $2,238,199 | 1 | REHABILITATE EXISTING ROADWAY | 4.0 |
0920-00-145 | Jefferson/ Beaumont | VA | Actual | $345,943 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0259-05-080 | Johnson/ Ft Worth | US 67 | Actual | $10,125,392 | 1 | RESURFACE ROADWAY | 3.0 |
0197-03-076 | Kaufman/ Dallas | US 175 | Actual | $2,141,610 | 6 | REMOVE/REPLACE BRIDGE RAIL | 3.0 |
0197-05-060 | Kaufman/ Dallas | US 175 | Actual | $296,886 | 8 | INSTALL FLASHING BEACON | 0.0 |
0907-20-005 | Kimble/ San Angelo | PW | Actual | $1,099,860 | 10 | STATE PARK IMPROVEMENTS | 0.0 |
2373-01-022 | La Salle/ Laredo | FM 624 | Actual | $5,754,069 | 1 | WIDEN ROAD - ADD SHOULDERS | 4.0 |
1690-01-127 | Lamar/ Paris | US 82 | Actual | $3,115,201 | 8 | HAZARD ELIMINATION & SAFETY | 2.0 |
0916-29-015 | Live Oak/ Corpus Christi | VA | Actual | $734,945 | 3 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0905-00-110 | Lubbock/ Lubbock | VA | Actual | $4,588,697 | 10 | CONSTRUCT RAMPS | 0.0 |
0905-00-100 | Lubbock/ Lubbock | VA | Actual | $355,032 | 1 | REPLACE DYNAMIC MESSAGE SIGNS | 0.0 |
1502-01-029 | Lubbock/ Lubbock | FM 1585 | Actual | $139,838,833 | 1 | CONVERT NON-FREEWAY | 11.5 |
0916-00-232 | Nueces/ Corpus Christi | VA | Actual | $1,555,885 | 8 | INSTALL ILLUMINATION | 0.0 |
1557-01-043 | Nueces/ Corpus Christi | FM 43 | Actual | $4,386,361 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0075-02-026 | Pecos/ Odessa | US 67 | Actual | $37,570,691 | 1 | WIDEN ROAD - ADD LANES AND SHOULDERS | 0.0 |
0176-04-087 | Polk/ Lufkin | US 59 | Actual | $6,447,982 | 8 | HIGHWAY IMPROVEMENT | 3.0 |
2494-01-015 | Potter/ Amarillo | RM 2381 | Actual | $1,972,567 | 8 | INTERSECTION IMPROVEMENT | 2.5 |
2277-01-010 | Rains/ Paris | FM 275 | Actual | $4,552,514 | 1 | REHABILITATE EXISTING ROADWAY | 4.0 |
0003-06-096 | Reeves/ Odessa | IH 20 | Actual | $889,939 | 6 | BRIDGE MAINTENANCE | 0.0 |
1409-03-020 | Shelby/ Lufkin | FM 2261 | Actual | $1,222,603 | 6 | BRIDGE REPLACEMENT | 4.0 |
0910-00-120 | Smith/ Tyler | VA | Actual | $796,864 | 11 | HAZARD ELIMINATION & SAFETY | 0.0 |
0160-01-036 | Sutton/ San Angelo | US 277 | Actual | $8,510,241 | 1 | HIGHWAY IMPROVEMENT | 6.0 |
2855-01-023 | Tarrant/ Ft Worth | RM 2871 | Actual | $1,023,021 | 1 | RESURFACE ROADWAY | 0.0 |
0172-06-101 | Tarrant/ Ft Worth | US 287 | Actual | $4,608,920 | 1 | BRIDGE MAINTENANCE | 8.0 |
0033-08-043 | Taylor/ Abilene | BU 83-D | Actual | $165,455 | 8 | INSTALL FLASHING BEACON | 0.0 |
0610-03-100 | Titus/ Atlanta | IH 30 | Actual | $5,435,680 | 8 | HAZARD ELIMINATION & SAFETY | 5.0 |
0907-24-048 | Tom Green/ San Angelo | CS | Actual | $2,272,852 | 3 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0683-04-022 | Travis/ Austin | RM 3238 | Actual | $14,520,825 | 11 | REHABILITATE EXISTING ROADWAY | 7.5 |
0022-10-073 | Val Verde/ Laredo | US 90 | Actual | $2,647,753 | 8 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
0086-02-030 | Webb/ Laredo | SH 359 | Actual | $6,107,897 | 8 | WIDEN ROAD - ADD LANES AND SHOULDERS | 4.0 |
0086-16-016 | Webb/ Laredo | SL 20 | Actual | $296,761 | 8 | INSTALL ILLUMINATION | 0.0 |
2211-01-026 | Williamson/ Austin | RM 2338 | Actual | $8,296,923 | 1 | CONSTRUCT BRIDGE | 6.0 |
2690-01-037 | Williamson/ Austin | FM 971 | Actual | $3,847,767 | 3 | WIDEN ROAD - ADD LANES | 0.0 |
0134-06-053 | Wise/ Ft Worth | SH 101 | Actual | $5,637,486 | 1 | REHABILITATE EXISTING ROADWAY | 0.0 |
|