Bid Totals Page 1 of 24

Last Update: Thursday, February 15, 2018

1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24

Text version of this page
County:POTTERLet Date:01/04/18
Type:BRIDGE REPLACEMENTS AND MISC. CONSTRUCTIONSeq No:3002
Time:696 WORKING DAYSProject ID:BR 2018(359)
Highway:IH 40Contract #:01183002
Length:8.374CCSJ:0275-01-180
Limits: 
From:WEST OF WHITAKER RDCheck:$100,000
To:US 287 SPLITMisc Cost:$155,000.00
Estimate$50,751,953.25% Over/UnderCompany
Bidder 1$50,440,638.45-0.61%J. LEE MILLIGAN, INC.
Bidder 2$51,601,100.00+1.67%WEBBER, LLC
Bidder 3$51,865,660.78+2.19%JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
Bidder 4$54,522,564.11+7.43%ALLEN BUTLER CONSTRUCTION, INC.
Bidder 5$55,985,372.53+10.31%OHL USA, INC.
Bidder 6$60,760,317.77+19.72%GILVIN-TERRILL, LTD.
State Let Construction Projects for January, 2018

Text version of this page
County:MCMULLENLet Date:01/04/18
Type:GRADE, BASE, SURF, PAVEMENT MARKINGSSeq No:3003
Time:586 WORKING DAYSProject ID:STP 2018(077)
Highway:SH 72Contract #:01183003
Length:15.563CCSJ:0483-02-021
Limits: 
From:SH 97Check:$100,000
To:SH 16Misc Cost:$220,000.00
Estimate$35,918,323.60% Over/UnderCompany
Bidder 1$28,907,909.72-19.52%HUNTER INDUSTRIES, LTD.
Bidder 2$28,938,759.70-19.43%ANGEL BROTHERS HOLDINGS CORP.
Bidder 3$32,412,874.58-9.76%H. L. ZUMWALT CONSTRUCTION, INC.
Bidder 4$33,724,629.24-6.11%ANDERSON COLUMBIA CO., INC.
Bidder 5$35,502,516.23-1.16%RAY FARIS, INC.
Bidder 6$35,905,362.45-0.04%LONE STAR PAVING COMPANY
Bidder 7$37,484,143.08+4.36%AUSTIN MATERIALS, LLC
Bidder 8$39,144,134.88+8.98%JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
State Let Construction Projects for January, 2018

Text version of this page
County:GAINESLet Date:01/04/18
Type:MILL, CEMENT, TRT, TYB, SMA, DMSSeq No:3004
Time:116 WORKING DAYSProject ID:NH 2018(437)
Highway:US 62Contract #:01183004
Length:22.916CCSJ:0294-01-040
Limits: 
From:TEXAS/NEW MEXICO STATE LINECheck:$100,000
To:WEST SEMINOLE CITY LIMITSMisc Cost:$134,500.00
Estimate$10,975,467.55% Over/UnderCompany
Bidder 1$9,630,759.46-12.25%CI CONSTRUCTORS, INC.
Bidder 2$10,568,292.31-3.71%DUININCK, INC.
Bidder 3$11,127,747.94+1.39%JAMES HAMILTON CONSTRUCTION CO.
Bidder 4$11,190,472.54+1.96%KIEWIT INFRASTRUCTURE SOUTH CO.
Bidder 5$11,815,519.26+7.65%PRICE CONSTRUCTION, LTD.
Bidder 6$12,542,492.49+14.28%FNF CONSTRUCTION, INC.
State Let Construction Projects for January, 2018

Text version of this page
County:SMITHLet Date:01/04/18
Type:PLANT TREES&SHRUBS, DRIP IRRIGATION, SOIL PREPSeq No:3005
Time:34 WORKING DAYSProject ID:STP 2018(429)
Highway:SS 248Contract #:01183005
Length:0.270CCSJ:2558-01-017
Limits: 
From:1.1 MI E OF SL 323/LAKE,IN TYLER,Check:$2,000
To:1.7 MI W OF FM 848/OLD OMEN RDMisc Cost:$6,000.00
Estimate$76,400.00% Over/UnderCompany
Bidder 1$69,000.00-9.69%AALC, INC.
Bidder 2$76,325.80-0.10%CENTRAL NORTH CONSTRUCTION, LLC
Bidder 3$82,281.00+7.70%TIGHT LINE CONSTRUCTION, LLC
Bidder 4$83,999.68+9.95%CARRUTH NURSERY IRRIGATION & LANDSCAPE, INC.
Bidder 5$95,832.00+25.43%SOUTH TEXAS ILLUMINATION, LLC
Bidder 6$109,380.00+43.17%PETTY'S IRRIGATION & LANDSCAPE, LTD.
State Let Construction Projects for January, 2018

Text version of this page
County:KENDALLLet Date:01/04/18
Type:OVERLAY AND PAVEMENT MARKINGSSeq No:3006
Time:80 WORKING DAYSProject ID:NH 2018(502)
Highway:US 87Contract #:01183006
Length:4.795CCSJ:0072-14-028
Limits: 
From:IH 10 NCheck:$50,000
To:IH 10 SMisc Cost:$7,000.00
Estimate$2,523,992.19% Over/UnderCompany
Bidder 1$1,983,029.00-21.43%ANGEL BROTHERS HOLDINGS CORP.
Bidder 2$2,126,549.65-15.75%LONE STAR PAVING COMPANY
Bidder 3$2,205,437.64-12.62%CLARK CONSTRUCTION OF TEXAS, INC.
Bidder 4$2,262,512.23-10.36%AUSTIN MATERIALS, LLC
Bidder 5$2,339,760.15-7.30%DEAN WORD COMPANY, LTD.
Bidder 6$2,509,770.29-0.56%HUNTER INDUSTRIES, LTD.
Bidder 7$2,637,272.01+4.49%CURRAN CONTRACTING COMPANY
State Let Construction Projects for January, 2018

Text version of this page
County:TOM GREENLet Date:01/04/18
Type:ACP OVERLAY AND FLEXIBLE PAVEMENT STRUCTURE REPAISeq No:3007
Time:83 WORKING DAYSProject ID:NH 2018(440)
Highway:US 87Contract #:01183007
Length:9.752CCSJ:0069-06-034
Limits: 
From:VARIOUS LOCATIONS IN SJT DISTRICTCheck:$81,000
To:Misc Cost:$1,000.00
Estimate$4,033,479.44% Over/UnderCompany
Bidder 1$3,255,516.17-19.29%REECE ALBERT, INC.
Bidder 2$5,123,677.72+27.03%PRICE CONSTRUCTION, LTD.
State Let Construction Projects for January, 2018

Text version of this page
County:CALHOUNLet Date:01/04/18
Type:ACP OVERLAY AND INSTALLING TRAFFIC SIGNALSSeq No:3008
Time:90 WORKING DAYSProject ID:NH 2018(388)
Highway:SH 35Contract #:01183008
Length:3.417CCSJ:0179-10-108
Limits: 
From:PORT LAVACA CAUSEWAYCheck:$53,000
To:0.024 MI N OF AIRLINE DRIVE(CR 101)Misc Cost:$17,000.00
Estimate$2,643,714.73% Over/UnderCompany
Bidder 1$3,082,748.47+16.61%HUNTER INDUSTRIES, LTD.
State Let Construction Projects for January, 2018

Text version of this page
County:TARRANTLet Date:01/04/18
Type:ITS FIBER AND EQUIPMENTSeq No:3009
Time:171 WORKING DAYSProject ID:CM 2018(453)
Highway:IH 35WContract #:01183009
Length:12.042CCSJ:0014-02-051
Limits: 
From:IH 20Check:$55,000
To:SH 174Misc Cost:$65,097.00
Estimate$2,744,059.06% Over/UnderCompany
Bidder 1$2,034,583.74-25.85%HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
Bidder 2$2,485,564.30-9.42%MICA CORPORATION
Bidder 3$2,699,092.52-1.64%FUTURE TELECOM, LLC
Bidder 4$2,831,977.27+3.20%AMERICAN LIGHTING AND SIGNALIZATION, LLC
Bidder 5$3,164,684.45+15.33%FLORIDA TRAFFIC CONTROL DEVICES, INC.
Bidder 6$3,424,418.57+24.79%THIRD COAST SERVICES LLC
State Let Construction Projects for January, 2018

Text version of this page
County:CORYELLLet Date:01/04/18
Type:SLP RPRSeq No:3010
Time:85 WORKING DAYSProject ID:STP 2018(500)
Highway:SH 9Contract #:01183010
Length:0.614CCSJ:3623-01-003
Limits: 
From:0.6 MI N OF BU 190Check:$12,000
To:BU 190Misc Cost:$9,000.00
Estimate$579,068.55% Over/UnderCompany
Bidder 1$661,980.04+14.32%TTG UTILITIES, LP
Bidder 2$665,302.87+14.89%BIG CREEK CONSTRUCTION, LTD.
Bidder 3$782,765.11+35.18%JAMES CONSTRUCTION GROUP, L.L.C.
Bidder 4$822,518.81+42.04%OLDCASTLE MATERIALS TEXAS, INC.
State Let Construction Projects for January, 2018

Text version of this page
County:LEELet Date:01/04/18
Type:REPLACE BRIDGE & APPROACHESSeq No:3011
Time:72 WORKING DAYSProject ID:BR 2016(252)
Highway:CRContract #:01183011
Length:0.064CCSJ:0914-21-031
Limits: 
From:ON CR 418 AT ALLEN CREEKCheck:$7,000
To:STR AA01-81-001Misc Cost:$21,000.00
Estimate$347,108.65% Over/UnderCompany
Bidder 1$313,217.77-9.76%TREVWAY, INC.
Bidder 2$318,543.05-8.23%ELLIS-MCGINNIS CONSTRUCTION CO.
Bidder 3$353,338.61+1.79%HARTBEAT CONSTRUCTION
Bidder 4$361,963.15+4.28%DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC.
Bidder 5$374,225.40+7.81%A GREATER AUSTIN DEVELOPMENT COMPANY, LTD.
Bidder 6$405,999.70+16.97%ANGEL BROTHERS HOLDINGS CORP.
Bidder 7$416,844.63+20.09%HILL COUNTRY BRIDGE, INC.
Bidder 8$449,909.45+29.62%DAN WILLIAMS COMPANY
Bidder 9$463,518.22+33.54%FUQUA CONSTRUCTION CO., INC.
Bidder 10$516,881.48+48.91%REECE CONSTRUCTION CO., INC.
State Let Construction Projects for January, 2018

Text version of this page
County:DALLASLet Date:01/04/18
Type:INSTALLATION OF TRAFFIC SIGNALSSeq No:3012
Time:548 WORKING DAYSProject ID:STP 2018(504)
Highway:VAContract #:01183012
Length:0.001CCSJ:0918-00-283
Limits: 
From:VARIOUS LOCATIONSCheck:$30,000
To:IN DALLAS DISTRICTMisc Cost:$300,000.00
Estimate$1,495,682.20% Over/UnderCompany
Bidder 1$1,468,000.00-1.85%DURABLE SPECIALTIES, INC.
Bidder 2$2,044,511.46+36.69%AMERICAN LIGHTING AND SIGNALIZATION, LLC
State Let Construction Projects for January, 2018

Text version of this page
County:GRAYSONLet Date:01/04/18
Type:MILL AND INLAYSeq No:3015
Time:120 WORKING DAYSProject ID:NH 2018(422)
Highway:US 75Contract #:01183015
Length:6.415CCSJ:0047-02-138
Limits: 
From:0.6 MILES S OF CENTER STREETCheck:$100,000
To:FM 131Misc Cost:$51,000.00
Estimate$7,097,806.31% Over/UnderCompany
Bidder 1$6,395,385.04-9.90%AUSTIN BRIDGE & ROAD SERVICES, LP
Bidder 2$7,196,973.67+1.40%RK HALL, LLC
State Let Construction Projects for January, 2018

Text version of this page
County:DENTONLet Date:01/04/18
Type:FULL DEPTH PAVEMENT REPAIRSeq No:3016
Time:104 WORKING DAYSProject ID:NH 2018(616)
Highway:IH 35WContract #:01183016
Length:17.147CCSJ:0081-13-063
Limits: 
From:TARRANT COUNTY LINECheck:$100,000
To:IH 35EMisc Cost:$378,700.00
Estimate$13,278,767.46% Over/UnderCompany
Bidder 1$11,361,086.24-14.44%JAGOE-PUBLIC COMPANY
Bidder 2$11,925,034.82-10.19%THE LANE CONSTRUCTION CORPORATION
Bidder 3$13,904,525.65+4.71%AUSTIN BRIDGE & ROAD SERVICES, LP
Bidder 4$15,899,317.72+19.73%OLDCASTLE MATERIALS TEXAS, INC.
State Let Construction Projects for January, 2018

Text version of this page
County:FALLSLet Date:01/04/18
Type:REPL BR & APPRSSeq No:3017
Time:255 WORKING DAYSProject ID:BR 1602(241)
Highway:CRContract #:01183017
Length:0.208CCSJ:0909-38-076
Limits: 
From:CR 299 @ BRAZOS RV TRIBCheck:$24,000
To:(MAP #2043)Misc Cost:$7,000.00
Estimate$1,195,137.00% Over/UnderCompany
Bidder 1$1,139,586.13-4.65%KNIFE RIVER CORPORATION - SOUTH
Bidder 2$1,310,647.36+9.67%JAMES CONSTRUCTION GROUP, L.L.C.
Bidder 3$1,311,305.00+9.72%HODGES AND SON CONSTRUCTION COMPANY, INC.
Bidder 4$1,346,794.50+12.69%PROJECT ALLIED RESOURCES, LLC
Bidder 5$1,348,556.20+12.84%ELLIS-MCGINNIS CONSTRUCTION CO.
Bidder 6$1,533,535.16+28.31%PIERCE R & B LLC
Bidder 7$1,543,888.48+29.18%COPPELL CONSTRUCTION CO., INC.
Bidder 8$1,708,602.30+42.96%HIGHWAY 19 CONSTRUCTION LLC
Bidder 9$1,759,215.35+47.20%IOWA BRIDGE & CULVERT, LC
Bidder 10$1,779,382.49+48.89%A GREATER AUSTIN DEVELOPMENT COMPANY, LTD.
State Let Construction Projects for January, 2018

Text version of this page
County:GUADALUPELet Date:01/04/18
Type:CONSTRUCT WEIGH STATION WEIGH IN MOTION RAMPSSeq No:3018
Time:198 WORKING DAYSProject ID:NH 2018(404)
Highway:IH 10Contract #:01183018
Length:1.261CCSJ:0535-02-048
Limits: 
From:0.3 MI EAST OF FM 1104Check:$70,000
To:0.3 MI WEST OF CR 216Misc Cost:$14,000.00
Estimate$3,600,843.83% Over/UnderCompany
Bidder 1$3,343,191.83-7.16%CAPITAL EXCAVATION COMPANY
Bidder 2$3,372,756.43-6.33%RELMCO, INC.
Bidder 3$3,481,478.45-3.31%ANGEL BROTHERS HOLDINGS CORP.
Bidder 4$3,583,835.00-0.47%DENBOW COMPANY INC.
Bidder 5$3,643,000.49+1.17%DAN WILLIAMS COMPANY
Bidder 6$3,696,788.23+2.66%DEAN WORD COMPANY, LTD.
Bidder 7$3,867,859.16+7.42%CURRAN CONTRACTING COMPANY
Bidder 8$4,037,393.24+12.12%HUNTER INDUSTRIES, LTD.
Bidder 9$4,081,690.75+13.35%MAIN LANE INDUSTRIES LTD.
Bidder 10$4,195,971.52+16.53%SPAWGLASS CIVIL CONSTRUCTION, INC.
Bidder 11$4,298,995.53+19.39%J3 COMPANY, LLC
State Let Construction Projects for January, 2018

Text version of this page
County:HARTLEYLet Date:01/04/18
Type:BRIDGE REPLACEMENTSeq No:3019
Time:280 WORKING DAYSProject ID:BR 2018(436)
Highway:FM 767Contract #:01183019
Length:0.531CCSJ:1108-01-020
Limits: 
From:AT PUNTA DE AGUA CREEKCheck:$100,000
To:Misc Cost:$32,500.00
Estimate$5,208,994.70% Over/UnderCompany
Bidder 1$4,253,525.11-18.34%COPPELL CONSTRUCTION CO., INC.
Bidder 2$4,429,162.00-14.97%STATELINE CONSTRUCTION, LLC
Bidder 3$4,743,700.75-8.93%EARTH BUILDERS, L.P.
Bidder 4$5,054,079.18-2.97%J. LEE MILLIGAN, INC.
Bidder 5$5,196,972.20-0.23%DCI CONTRACTING, INC.
Bidder 6$5,300,327.40+1.75%FNF CONSTRUCTION, INC.
State Let Construction Projects for January, 2018