Bid Totals Page 22 of 31

Last Update: Wednesday, June 29, 2022

Site improvements have arrived.

New interactive dashboards on TxDOT.gov make it simple for you to quickly find relevant and up-to-date information. Access them here

Need help finding something? Check out this information page for more details.

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.


1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31

Text version of this page
County:HUDSPETHLet Date:06/29/22
Type:HIGHWAY IMPROVEMENTSeq No:3405
Time:420 WORKING DAYSProject ID:F 2022(758)
Highway:US 62Contract #:06223405
Length:16.002CCSJ:0374-06-022
Limits: 
From:2.04 MI E OF FM 2317Check:$100,000
To:6.17 MI E OF RM 1111Misc Cost:$107,000.00
Estimate$23,168,431.85% Over/UnderCompany
Bidder 1$21,060,676.34-9.10%DAN WILLIAMS COMPANY
Bidder 2$21,954,050.50-5.24%INTERNATIONAL EAGLE ENTERPRISES, INC.
Bidder 3$24,891,695.95+7.44%LESNA CONSTRUCTION, INC.
State Let Construction Projects for June, 2022

Text version of this page
County:HARRISLet Date:06/29/22
Type:CONSTRUCT BRIDGESeq No:3406
Time:469 WORKING DAYSProject ID:C 389-13-39
Highway:SH 146Contract #:06223406
Length:0.000CCSJ:0389-13-039
Limits: 
From:FERRY RDCheck:$100,000
To:BS 146EMisc Cost:
Estimate$26,302,732.17% Over/UnderCompany
Bidder 1$24,851,806.25-5.52%ISI CONTRACTING, INC.
Bidder 2$24,955,649.65-5.12%STERLING DELAWARE HOLDING COMPANY, INC.
Bidder 3$25,196,281.81-4.21%SER CONSTRUCTION PARTNERS, LLC
Bidder 4$25,480,870.69-3.12%WEBBER, LLC
Bidder 5$26,397,506.92+0.36%JAMES CONSTRUCTION GROUP, LLC
State Let Construction Projects for June, 2022

Text version of this page
County:MIDLANDLet Date:06/29/22
Type:RAILROAD CROSSING IMPROVEMENTSSeq No:3407
Time:285 WORKING DAYSProject ID:STP 2021(748)FRS
Highway:BI 20-EContract #:06223407
Length:1.400CCSJ:0005-03-068
Limits: 
From:AT FAIRGROUNDS ROADCheck:$100,000
To:.Misc Cost:
Estimate$8,828,725.25% Over/UnderCompany
Bidder 1$11,943,374.13+35.28%ALTUS CONSTRUCTION LLC
Bidder 2$12,956,496.85+46.75%RAGLE CONSTRUCTION, INC.
Bidder 3$19,999,999.90+126.53%JONES BROS. DIRT & PAVING CONTRACTORS, INC.
State Let Construction Projects for June, 2022

Text version of this page
County:CASSLet Date:06/29/22
Type:RESURFACE EXISTING 4-LANE ROADWAYSeq No:3409
Time:136 WORKING DAYSProject ID:C 218-4-119
Highway:US 59Contract #:06223409
Length:2.308CCSJ:0218-04-119
Limits: 
From:0.1 MI. S. OF FM 2328NCheck:$100,000
To:1.9 MI. S. OF FM 2328SMisc Cost:
Estimate$8,971,075.35% Over/UnderCompany
Bidder 1$11,842,462.04+32.01%EAST TEXAS BRIDGE, INC.
Bidder 2$12,170,177.06+35.66%RK HALL, LLC
State Let Construction Projects for June, 2022

Text version of this page
County:DENTONLet Date:06/29/22
Type:HIGHWAY OPERATIONS PROGRAMSeq No:3410
Time:252 WORKING DAYSProject ID:F 2022(043)
Highway:IH 35EContract #:06223410
Length:2.727CCSJ:0196-02-132
Limits: 
From:FRANKFORD RDCheck:$100,000
To:CORPORATE DRMisc Cost:
Estimate$11,761,702.58% Over/UnderCompany
Bidder 1$19,987,979.01+69.94%RAGLE CONSTRUCTION, INC.
State Let Construction Projects for June, 2022

Text version of this page
County:MONTGOMERYLet Date:06/29/22
Type:CONSTRUCT FRONTAGE ROADSSeq No:3411
Time:252 WORKING DAYSProject ID:CC 675-8-114
Highway:IH 45Contract #:06223411
Length:0.000CCSJ:0675-08-114
Limits: 
From:FM 830Check:$100,000
To:FM 1097Misc Cost:$30,000.00
Estimate$7,368,740.09% Over/UnderCompany
Bidder 1$7,473,853.32+1.43%JAMES CONSTRUCTION GROUP, LLC
Bidder 2$7,729,703.65+4.90%MAIN LANE INDUSTRIES LTD.
Bidder 3$7,813,755.13+6.04%STERLING DELAWARE HOLDING COMPANY, INC.
Bidder 4$8,110,890.05+10.07%R CONSTRUCTION CIVIL, LLC
Bidder 5$8,465,836.62+14.89%HARPER BROTHERS CONSTRUCTION LLC
Bidder 6$8,832,072.52+19.86%SER CONSTRUCTION PARTNERS, LLC
Bidder 7$8,863,320.10+20.28%TEXAS MATERIALS GROUP, INC.
Bidder 8$10,686,324.05+45.02%ISI CONTRACTING, INC.
State Let Construction Projects for June, 2022

Text version of this page
County:NAVARROLet Date:06/29/22
Type:REHABILITATE EXISTING ROADWAYSeq No:3412
Time:241 WORKING DAYSProject ID:C 3325-1-14
Highway:FM 3243Contract #:06223412
Length:5.065CCSJ:3325-01-014
Limits: 
From:END OF MAINTENANCECheck:$100,000
To:US 287Misc Cost:
Estimate$6,524,789.42% Over/UnderCompany
Bidder 1$5,724,413.87-12.27%A. L. HELMCAMP, INC.
Bidder 2$6,156,460.26-5.65%A. K. GILLIS & SONS, LLC
Bidder 3$6,235,035.72-4.44%BIG CREEK CONSTRUCTION, LTD.
Bidder 4$6,514,178.12-0.16%KNIFE RIVER CORPORATION - SOUTH
Bidder 5$6,934,142.15+6.27%D. L. LENNON INCORPORATED - CONTRACTOR
State Let Construction Projects for June, 2022

Text version of this page
County:CROCKETTLet Date:06/29/22
Type:HAZARD ELIMINATION & SAFETYSeq No:3413
Time:455 WORKING DAYSProject ID:STP 2022(702)HES
Highway:IH 10Contract #:06223413
Length:14.964CCSJ:0140-10-034
Limits: 
From:15.9 MI E OF PECOS CLCheck:$84,000
To:29.0 MI E OF PECOS CLMisc Cost:
Estimate$4,212,424.15% Over/UnderCompany
Bidder 1$5,283,751.71+25.43%VECTOR UTILITIES LLC
Bidder 2$5,470,211.37+29.86%RELMCO, INC.
Bidder 3$5,740,572.56+36.28%ALTUS CONSTRUCTION LLC
Bidder 4$5,788,948.15+37.43%SCR CIVIL CONSTRUCTION, LLC
Bidder 5$10,299,666.46+144.51%3LW CIVIL LLC
State Let Construction Projects for June, 2022

Text version of this page
County:WHARTONLet Date:06/29/22
Type:BRIDGE REPLACEMENTSeq No:3414
Time:236 WORKING DAYSProject ID:BR 2022(718)
Highway:SH 60Contract #:06223414
Length:0.843CCSJ:0240-02-032
Limits: 
From:AT MIDDLE BERNARD CREEKCheck:$100,000
To:STR # 0240-02-009Misc Cost:
Estimate$5,322,493.15% Over/UnderCompany
Bidder 1$5,657,394.78+6.29%JOHN REED AND COMPANY, LLC
Bidder 2$5,702,313.29+7.14%JAMES CONSTRUCTION GROUP, LLC
Bidder 3$6,273,879.50+17.87%TEXAS STEEL INDUSTRIAL PLACING, LLC
Bidder 4$6,331,533.34+18.96%RAGLE CONSTRUCTION, INC.
Bidder 5$7,037,843.68+32.23%TEXAS MATERIALS GROUP, INC.
State Let Construction Projects for June, 2022

Text version of this page
County:HIDALGOLet Date:06/29/22
Type:HAZARD ELIMINATION & SAFETYSeq No:3415
Time:180 WORKING DAYSProject ID:STP 2022(723)HES
Highway:FM 491Contract #:06223415
Length:0.000CCSJ:0861-01-068
Limits: 
From:FM 1425Check:$78,000
To:CR 1390Misc Cost:
Estimate$3,910,866.61% Over/UnderCompany
Bidder 1$3,701,235.71-5.36%ASAGO, LLC
Bidder 2$3,839,510.90-1.82%FOREMOST PAVING, INC.
Bidder 3$3,918,802.00+0.20%TEXAS CORDIA CONSTRUCTION, LLC
Bidder 4$5,233,484.56+33.82%IOC COMPANY LLC
State Let Construction Projects for June, 2022

Text version of this page
County:TARRANTLet Date:06/29/22
Type:REHABILITATE EXISTING ROADWAYSeq No:3416
Time:365 WORKING DAYSProject ID:C 902-00-312
Highway:VAContract #:06223416
Length:0.000CCSJ:0902-00-312
Limits: 
From:VARIOUS LOCATIONSCheck:$69,000
To:WITHIN FORT WORTH DISTRICTMisc Cost:
Estimate$3,433,330.00% Over/UnderCompany
Bidder 1$4,103,210.00+19.51%NEW WORLD CONTRACTING, LLC
Bidder 2$4,392,540.00+27.94%O. TREVINO CONSTRUCTION, LLC
Bidder 3$5,471,035.38+59.35%ALTUS CONSTRUCTION LLC
State Let Construction Projects for June, 2022

Text version of this page
County:BEXARLet Date:06/29/22
Type:HIGHWAY IMPROVEMENTSeq No:3417
Time:165 WORKING DAYSProject ID:C 915-00-241
Highway:VAContract #:06223417
Length:0.001CCSJ:0915-00-241
Limits: 
From:VARIOUS LOCATIONS DISTRICTWIDECheck:$80,000
To:.Misc Cost:
Estimate$3,994,521.60% Over/UnderCompany
Bidder 1$3,546,574.10-11.21%STRIPE-A-ZONE, LLC
Bidder 2$3,580,291.45-10.37%PAVEMENT MARKINGS INC.
Bidder 3$3,784,127.45-5.27%INTERSTATE BARRICADES & MARKINGS, INC.
Bidder 4$3,846,753.95-3.70%TRP CONSTRUCTION GROUP, LLC
State Let Construction Projects for June, 2022

Text version of this page
County:DENTONLet Date:06/29/22
Type:CONSTRUCT RAMPSSeq No:3418
Time:71 WORKING DAYSProject ID:F 2022(771)
Highway:IH 35EContract #:06223418
Length:0.000CCSJ:0196-02-131
Limits: 
From:GARDEN RIDGE BLVDCheck:$46,000
To:LAKE LEWISVILLE BRIDGEMisc Cost:
Estimate$2,318,635.59% Over/UnderCompany
Bidder 1$2,796,046.88+20.59%TEXAS MATERIALS GROUP, INC.
Bidder 2$2,804,652.71+20.96%EUROVIA ATLANTIC COAST LLC
Bidder 3$3,142,166.10+35.52%JAGOE-PUBLIC COMPANY
State Let Construction Projects for June, 2022

Text version of this page
County:COMALLet Date:06/29/22
Type:HAZARD ELIMINATION & SAFETYSeq No:3419
Time:234 WORKING DAYSProject ID:STP 2022(687)HES
Highway:BS 46-CContract #:06223419
Length:12.693CCSJ:0016-10-025
Limits: 
From:0.1 MI WEST OF BEECH TRAILCheck:$42,000
To:0.1 MI EAST OF BEECH TRAILMisc Cost:
Estimate$2,113,035.34% Over/UnderCompany
Bidder 1$2,079,346.97-1.59%E-Z BEL CONSTRUCTION, LLC
Bidder 2$2,438,505.25+15.40%THE LEVY COMPANY, INC.
State Let Construction Projects for June, 2022

Text version of this page
County:BEXARLet Date:06/29/22
Type:HAZARD ELIMINATION & SAFETYSeq No:3422
Time:297 WORKING DAYSProject ID:STP 2022(690)HES
Highway:CSContract #:06223422
Length:1.800CCSJ:0915-12-624
Limits: 
From:ON CASTROVILLE RD AT CUPPLES RDCheck:$41,000
To:.Misc Cost:
Estimate$2,030,606.56% Over/UnderCompany
Bidder 1$2,074,271.50+2.15%D&G ENERGY CORPORATION
Bidder 2$2,220,228.00+9.34%E-Z BEL CONSTRUCTION, LLC
Bidder 3$2,273,138.20+11.94%VACA UNDERGROUND UTILITIES INC
State Let Construction Projects for June, 2022

Text version of this page
County:FISHERLet Date:06/29/22
Type:BRIDGE REPLACEMENTSeq No:3423
Time:196 WORKING DAYSProject ID:BR 2B20(044)
Highway:SH 70Contract #:06223423
Length:0.000CCSJ:0263-05-024
Limits: 
From:PLUM CREEKCheck:$62,000
To:.Misc Cost:
Estimate$3,124,039.90% Over/UnderCompany
Bidder 1$3,716,743.80+18.97%STATELINE CONSTRUCTION, LLC
Bidder 2$4,238,957.00+35.69%EARTH BUILDERS, L.P.
Bidder 3$4,447,774.90+42.37%COPPELL CONSTRUCTION CO., INC.
Bidder 4$4,711,770.75+50.82%HODGES AND SON CONSTRUCTION COMPANY, INC.
Bidder 5$4,897,979.00+56.78%GILVIN-TERRILL, LTD.
State Let Construction Projects for June, 2022