Bid Totals Page 3 of 21

Last Update: Wednesday, September 2, 2015

1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21

Text version of this page
County: IRION Let Date: 07/07/15
Type: PASSING LANES Seq No: 3003
Time: 375 WORKING DAYS Project ID: STP 1502(413)
Highway: US 67 Contract #: 07153003
Length: 66.381 CCSJ: 0077-02-031
Limits:  
From: REAGAN COUNTY LINE Check: $100,000.00
To: TOM GREEN COUNTY LINE Misc Cost: $67,500.00
Estimate $32,004,584.28 % Over/Under Company
Bidder 1 $30,896,539.76 -3.46% REECE ALBERT, INC.
Bidder 2 $35,683,237.09 +11.49% PRICE CONSTRUCTION, LTD.
Bidder 3 $40,279,783.53 +25.86% KIEWIT INFRASTRUCTURE SOUTH CO.
State Let Construction Projects for July, 2015

Text version of this page
County: JEFFERSON Let Date: 07/07/15
Type: RECONSTRUCT INTERCHANGE Seq No: 3004
Time: 484 WORKING DAYS Project ID: C 739-2-155
Highway: IH 10 Contract #: 07153004
Length: 3.020 CCSJ: 0739-02-155
Limits:  
From: AT FM 364 Check: $100,000.00
To:   Misc Cost: $280,000.00
Estimate $24,557,749.75 % Over/Under Company
Bidder 1 $29,990,329.95 +22.12% WILLIAMS BROTHERS CONSTRUCTION CO., INC.
Bidder 2 $36,235,990.47 +47.55% JB JAMES CONSTRUCTION LLC
State Let Construction Projects for July, 2015

Text version of this page
County: NUECES Let Date: 07/07/15
Type: CONSTRUCT OVERPASS AT FM 3386-MCKINZIE RD. Seq No: 3007
Time: 356 WORKING DAYS Project ID: NH 2013(751)
Highway: SH 44 Contract #: 07153007
Length: 1.844 CCSJ: 0102-01-106
Limits:  
From: W. END OF CLARKWOOD RELIEF ROUTE Check: $100,000.00
To: WEST OF FM 3386 Misc Cost: $242,000.00
Estimate $16,392,319.91 % Over/Under Company
Bidder 1 $16,390,152.96 -0.01% BAY LTD.
Bidder 2 $16,599,502.00 +1.26% HAAS-ANDERSON CONSTRUCTION, LTD.
State Let Construction Projects for July, 2015

Text version of this page
County: BASTROP Let Date: 07/07/15
Type: INSTALL CONTINUOUS TURN LANE Seq No: 3011
Time: 59 WORKING DAYS Project ID: STP 1502(386)HES
Highway: SH 21 Contract #: 07153011
Length: 1.048 CCSJ: 0471-05-039
Limits:  
From: 0.363 MI W OF MARTINS CROSSING Check: $13,000.00
To: 0.223 MI E OF MARTINS CROSSING Misc Cost: $16,000.00
Estimate $707,266.10 % Over/Under Company
Bidder 1 $790,877.19 +11.82% ANGEL BROTHERS HOLDINGS CORP.
Bidder 2 $813,733.50 +15.05% AARON CONCRETE CONTRACTORS, L.P.
Bidder 3 $829,846.26 +17.33% CAPITAL EXCAVATION COMPANY
Bidder 4 $862,845.62 +22.00% DEAN WORD COMPANY, LTD.
Bidder 5 $948,294.36 +34.08% SB CONTRACTORS LLC
Bidder 6 $1,011,545.20 +43.02% HUNTER INDUSTRIES, LTD.
State Let Construction Projects for July, 2015

Text version of this page
County: DALLAS Let Date: 07/07/15
Type: TRAFFIC SIGNALS Seq No: 3012
Time: 140 WORKING DAYS Project ID: STP 1502(494)HES
Highway: CS Contract #: 07153012
Length: 0.483 CCSJ: 0918-47-101
Limits:  
From: VARIOUS INTERSECTIONS Check: $11,000.00
To: IN CITY OF DALLAS Misc Cost: $15,000.00
Estimate $570,293.92 % Over/Under Company
Bidder 1 $802,955.85 +40.80% FNH CONSTRUCTION, LLC
Bidder 2 $1,067,461.50 +87.18% O. TREVINO CONSTRUCTION, LLC
Bidder 3 $1,249,254.43 +119.05% ED BELL CONSTRUCTION COMPANY
State Let Construction Projects for July, 2015

Text version of this page
County: BEE Let Date: 07/07/15
Type: SPOT BASE REPAIR AND OVERLAY Seq No: 3013
Time: 204 WORKING DAYS Project ID: STP 1502(436)
Highway: SH 202 Contract #: 07153013
Length: 0.161 CCSJ: 0447-03-039
Limits:  
From: CR 425 Check: $100,000.00
To: REFUGIO COUNTY LINE Misc Cost: $81,000.00
Estimate $7,751,951.88 % Over/Under Company
Bidder 1 $8,641,470.29 +11.47% BAY LTD.
Bidder 2 $8,804,443.60 +13.58% J. CARROLL WEAVER, INC.
Bidder 3 $9,673,364.81 +24.79% HUNTER INDUSTRIES, LTD.
Bidder 4 $10,464,057.15 +34.99% HAAS-ANDERSON CONSTRUCTION, LTD.
State Let Construction Projects for July, 2015

Text version of this page
County: BOWIE Let Date: 07/07/15
Type: DECK CRACK SEAL Seq No: 3014
Time: 89 WORKING DAYS Project ID: BR 1502(418)
Highway: IH 369 Contract #: 07153014
Length: 1.720 CCSJ: 0218-02-045
Limits:  
From: AT RAMP FR369SB-IH 369 OVER RAMP Check: $18,000.00
To: 369S-82DC TO IH 369 Misc Cost: $5,000.00
Estimate $920,712.00 % Over/Under Company
Bidder 1 $433,802.60 -52.88% SCR CONSTRUCTION CO., INC.
Bidder 2 $469,079.30 -49.05% GIBSON & ASSOCIATES, INC.
Bidder 3 $763,534.00 -17.07% DRS CONSTRUCTION, INC.
Bidder 4 $775,534.00 -15.77% L.C. JORDAN & SON
Bidder 5 $982,712.00 +6.73% CHAMPION INFRASTRUCTURE, LLC
Bidder 6 $1,285,534.00 +39.62% EAST TEXAS BRIDGE, INC.
State Let Construction Projects for July, 2015

Text version of this page
County: CAMERON Let Date: 07/07/15
Type: BRIDGE REHABILITATION Seq No: 3019
Time: 651 WORKING DAYS Project ID: BR 1502(468)
Highway: FM 106 Contract #: 07153019
Length: 0.161 CCSJ: 0630-02-041
Limits:  
From: @ RIO HONDO LIFT BRIDGE Check: $100,000.00
To:   Misc Cost: $33,510.00
Estimate $9,389,378.00 % Over/Under Company
Bidder 1 $12,406,043.30 +32.13% PCL CIVIL CONSTRUCTORS, INC.
Bidder 2 $12,794,191.00 +36.26% SCR CONSTRUCTION CO., INC.
Bidder 3 $12,860,378.78 +36.97% GIBSON & ASSOCIATES, INC.
Bidder 4 $13,969,659.68 +48.78% KIEWIT INFRASTRUCTURE SOUTH CO.
State Let Construction Projects for July, 2015

Text version of this page
County: HARRIS Let Date: 07/07/15
Type: LANDSCAPE DEVELOPMENT Seq No: 3020
Time: 90 WORKING DAYS Project ID: HP 1502(450)
Highway: SL 8 Contract #: 07153020
Length: 9.109 CCSJ: 3256-01-106
Limits:  
From: WEST AIRPORT_BLVD Check: $15,000.00
To: WESTPARK Misc Cost: $7,000.00
Estimate $751,189.05 % Over/Under Company
Bidder 1 $875,730.76 +16.58% BOYER, INC.
Bidder 2 $1,111,308.95 +47.94% BIO LANDSCAPE & MAINTENANCE, INC.
State Let Construction Projects for July, 2015

Text version of this page
County: CASS Let Date: 07/07/15
Type: PAVEMENT MARKINGS Seq No: 3021
Time: 50 WORKING DAYS Project ID: STP 1502(420)
Highway: VA Contract #: 07153021
Length: 0.005 CCSJ: 0919-00-071
Limits:  
From: VARIOUS LOCATIONS Check: $31,000.00
To: . Misc Cost: $7,500.00
Estimate $1,566,000.00 % Over/Under Company
Bidder 1 $781,005.30 -50.13% STRIPE-A-ZONE, INC.
Bidder 2 $911,558.20 -41.79% BATTERSON, LLP
Bidder 3 $1,103,182.90 -29.55% STRIPING TECHNOLOGY, L.P.
Bidder 4 $1,256,510.10 -19.76% PROFESSIONAL TRAFFIC CONTROL LLC
Bidder 5 $1,267,491.50 -19.06% TRP CONSTRUCTION GROUP, LLC
Bidder 6 $1,354,346.70 -13.52% TOTAL HIGHWAY MAINTENANCE, LLC
State Let Construction Projects for July, 2015

Text version of this page
County: DEWITT Let Date: 07/07/15
Type: SAFETY TREAT FIXED OBJECTS AND WIDEN SHOULDERS Seq No: 3025
Time: 150 WORKING DAYS Project ID: STP 1502(477)HES
Highway: SH 119 Contract #: 07153025
Length: 12.725 CCSJ: 0359-03-026
Limits:  
From: KARNES C/L Check: $100,000.00
To: FM 108 Misc Cost: $1,500.00
Estimate $5,481,782.45 % Over/Under Company
Bidder 1 $5,170,038.51 -5.69% HUNTER INDUSTRIES, LTD.
Bidder 2 $5,745,044.25 +4.80% DEAN WORD COMPANY, LTD.
Bidder 3 $5,928,915.44 +8.16% SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
Bidder 4 $6,081,576.29 +10.94% ANGEL BROTHERS HOLDINGS CORP.
State Let Construction Projects for July, 2015

Text version of this page
County: DENTON Let Date: 07/07/15
Type: LANDSCAPE DEVELOPMENT Seq No: 3027
Time: 150 WORKING DAYS Project ID: STP 1502(498)
Highway: FM 407 Contract #: 07153027
Length: 14.741 CCSJ: 1785-01-035
Limits:  
From: FM 1830 Check: $12,000.00
To: BRIARHILL BLVD Misc Cost: $8,500.00
Estimate $602,209.05 % Over/Under Company
Bidder 1 $498,172.50 -17.28% C. GREEN SCAPING, L.P.
Bidder 2 $510,005.11 -15.31% AALC, INC.
State Let Construction Projects for July, 2015

Text version of this page
County: DIMMIT Let Date: 07/07/15
Type: WIDEN,BASE,GRADE,SURF TREAT,STRT,MBGF,PAV MKS Seq No: 3028
Time: 119 WORKING DAYS Project ID: STP 1502(455)HES
Highway: FM 1019 Contract #: 07153028
Length: 10.161 CCSJ: 1270-01-026
Limits:  
From: FM 468 Check: $50,000.00
To: END OF PAVEMENT Misc Cost: $76,515.00
Estimate $2,517,153.78 % Over/Under Company
Bidder 1 $3,036,840.44 +20.65% RAY FARIS, INC.
Bidder 2 $3,233,429.47 +28.46% ANDERSON COLUMBIA CO., INC.
Bidder 3 $3,253,728.28 +29.26% BRANNAN PAVING CO., LTD.
State Let Construction Projects for July, 2015

Text version of this page
County: ECTOR Let Date: 07/07/15
Type: REHABILITATION OF EXISTING ROAD Seq No: 3029
Time: 60 WORKING DAYS Project ID: NH 1502(409)
Highway: SL 338 Contract #: 07153029
Length: 3.854 CCSJ: 2224-01-093
Limits:  
From: 0.10 MI. NORTH OF SH 302 Check: $78,000.00
To: 0.53 MI NORTH OF YUKON ROAD Misc Cost: $52,000.00
Estimate $3,907,513.18 % Over/Under Company
Bidder 1 $3,581,786.69 -8.34% JONES BROS. DIRT & PAVING CONTRACTORS, INC.
Bidder 2 $3,727,057.36 -4.62% REECE ALBERT, INC.
Bidder 3 $4,551,856.31 +16.49% PRICE CONSTRUCTION, LTD.
State Let Construction Projects for July, 2015

Text version of this page
County: EL PASO Let Date: 07/07/15
Type: REPLACE STRUCTURE Seq No: 3030
Time: 120 WORKING DAYS Project ID: BR 1502(392)
Highway: FM 258 Contract #: 07153030
Length: 0.850 CCSJ: 0002-14-042
Limits:  
From: 2.52 MI W OF FM 258/SH 20 INTERSECT Check: $8,000.00
To: 2.39 MI W OF FM 258/SH 20 INTERSECT Misc Cost: $15,000.00
Estimate $406,032.32 % Over/Under Company
Bidder 1 $457,012.00 +12.56% LESNA CONSTRUCTION, INC.
Bidder 2 $484,278.50 +19.27% INTERNATIONAL EAGLE ENTERPRISES, INC.
Bidder 3 $537,194.00 +32.30% JORDAN FOSTER CONSTRUCTION, LLC
Bidder 4 $612,880.20 +50.94% DAN WILLIAMS COMPANY
Bidder 5 $982,972.15 +142.09% AUSTIN ENGINEERING CO., INC.
State Let Construction Projects for July, 2015

Text version of this page
County: ELLIS Let Date: 07/07/15
Type: WIDEN, SAFETY TREAT FIXED OBJ & CENTERLINE TEXTURE Seq No: 3031
Time: 136 WORKING DAYS Project ID: STP 1502(491)HES
Highway: FM 66 Contract #: 07153031
Length: 5.556 CCSJ: 0596-02-043
Limits:  
From: FM 308 Check: $68,000.00
To: FM 916 Misc Cost: $362,701.14
Estimate $3,481,816.62 % Over/Under Company
Bidder 1 $4,255,415.48 +22.22% APAC-TEXAS, INC.
Bidder 2 $4,949,621.35 +42.16% ED BELL CONSTRUCTION COMPANY
State Let Construction Projects for July, 2015