Bid Totals Page 3 of 25

Last Update: Thursday, December 06, 2018

1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25

Text version of this page
County:COMALLet Date:10/02/18
Type:SEAL COAT AND PAVEMENT MARKINGSSeq No:3005
Time:135 WORKING DAYSProject ID:STP 2019(091)
Highway:FM 482Contract #:10183005
Length:335.521CCSJ:0016-19-024
Limits: 
From:0.4 MILES SW OF KRUEGER CANYONCheck:$100,000
To:IH 35Misc Cost:$10,500.00
Estimate$16,116,533.97% Over/UnderCompany
Bidder 1$15,797,806.81-1.98%RONALD R. WAGNER & CO., LP
Bidder 2$16,003,367.35-0.70%CLARK CONSTRUCTION OF TEXAS, INC.
Bidder 3$17,706,855.74+9.87%BRANNAN PAVING CO., LTD.
State Let Construction Projects for October, 2018

Text version of this page
County:NAVARROLet Date:10/02/18
Type:REHABILITATE EXISTING PAVEMENT AND ADD SHOULDERSSeq No:3006
Time:486 WORKING DAYSProject ID:STP 2019(137)
Highway:FM 55Contract #:10183006
Length:9.840CCSJ:0121-08-019
Limits: 
From:SH 31Check:$100,000
To:3RD ST IN BLOOMING GROVEMisc Cost:$519,600.00
Estimate$9,513,500.30% Over/UnderCompany
Bidder 1$7,343,202.30-22.81%A. K. GILLIS & SONS, INC.
Bidder 2$8,666,340.70-8.90%KNIFE RIVER CORPORATION - SOUTH
Bidder 3$8,673,698.85-8.83%A. L. HELMCAMP, INC.
Bidder 4$8,936,318.66-6.07%D. L. LENNON INCORPORATED - CONTRACTOR
Bidder 5$9,295,199.49-2.29%ED BELL CONSTRUCTION COMPANY
State Let Construction Projects for October, 2018

Text version of this page
County:LUBBOCKLet Date:10/02/18
Type:ITS EQUIPMENTSeq No:3007
Time:90 WORKING DAYSProject ID:NH 2019(103)
Highway:VAContract #:10183007
Length:0.001CCSJ:0905-00-111
Limits: 
From:VARIOUS ROADWAYS INCheck:$16,000
To:THE LUBBOCK DISTRICTMisc Cost:$159,727.99
Estimate$811,399.25% Over/UnderCompany
Bidder 1$721,754.07-11.05%FLORIDA TRAFFIC CONTROL DEVICES, INC.
Bidder 2$787,020.19-3.00%AMERICAN LIGHTING AND SIGNALIZATION, LLC
Bidder 3$933,042.29+14.99%HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
Bidder 4$1,019,713.75+25.67%MICA CORPORATION
State Let Construction Projects for October, 2018

Text version of this page
County:ATASCOSALet Date:10/02/18
Type:GRADE, BASE, SC, SURF, PAVMT MRKSeq No:3008
Time:358 WORKING DAYSProject ID:STP 2019(110)
Highway:FM 140Contract #:10183008
Length:3.458CCSJ:0748-05-040
Limits: 
From:SH 16Check:$100,000
To:LA PARITA CREEKMisc Cost:$59,296.00
Estimate$5,263,546.20% Over/UnderCompany
Bidder 1$4,730,331.26-10.13%HUNTER INDUSTRIES, LTD.
Bidder 2$4,989,438.25-5.21%SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
Bidder 3$5,224,830.93-0.74%DEAN WORD COMPANY, LTD.
Bidder 4$5,372,846.02+2.08%TIERRA LEASE SERVICE, LLC
Bidder 5$5,870,010.56+11.52%ANGEL BROTHERS HOLDINGS CORP.
Bidder 6$5,929,225.00+12.65%JORDAN FOSTER CONSTRUCTION, LLC
Bidder 7$6,312,668.86+19.93%HARPER BROTHERS CONSTRUCTION LLC
Bidder 8$6,718,404.32+27.64%RAY FARIS, INC.
State Let Construction Projects for October, 2018

Text version of this page
County:BEXARLet Date:10/02/18
Type:REPAIR SLOPE FAILURESeq No:3010
Time:222 WORKING DAYSProject ID:NH 2019(109)
Highway:IH 37Contract #:10183010
Length:0.573CCSJ:0073-08-195
Limits: 
From:HACKBERRYCheck:$55,000
To:IH 10Misc Cost:$44,400.00
Estimate$2,770,759.01% Over/UnderCompany
Bidder 1$2,967,146.61+7.09%RELMCO, INC.
Bidder 2$3,656,202.44+31.96%CAPITAL EXCAVATION COMPANY
Bidder 3$3,863,948.32+39.45%DAN WILLIAMS COMPANY
Bidder 4$4,297,999.33+55.12%J3 COMPANY, LLC
Bidder 5$4,361,012.00+57.39%JORDAN FOSTER CONSTRUCTION, LLC
Bidder 6$4,564,866.68+64.75%CURRAN CONTRACTING COMPANY
Bidder 7$4,858,782.80+75.36%DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC.
Bidder 8$4,862,825.41+75.51%ANGEL BROTHERS HOLDINGS CORP.
State Let Construction Projects for October, 2018

Text version of this page
County:DEWITTLet Date:10/02/18
Type:MILL AND INLAYSeq No:3011
Time:120 WORKING DAYSProject ID:STP 2019(098)
Highway:VAContract #:10183011
Length:5.746CCSJ:0913-00-103
Limits: 
From:VARIOUS LOCATIONSCheck:$60,000
To:VICTORIA AREA OFFICEMisc Cost:$1,500.00
Estimate$3,021,981.05% Over/UnderCompany
Bidder 1$3,289,679.41+8.86%HUNTER INDUSTRIES, LTD.
Bidder 2$3,528,584.55+16.76%ANGEL BROTHERS HOLDINGS CORP.
Bidder 3$3,593,858.96+18.92%LONE STAR PAVING COMPANY
State Let Construction Projects for October, 2018

Text version of this page
County:BRAZOSLet Date:10/02/18
Type:SEAL COATSeq No:3013
Time:128 WORKING DAYSProject ID:NH 2019(100)
Highway:SH 6Contract #:10183013
Length:254.984CCSJ:0049-09-078
Limits: 
From:SH 6 WFR @ OSRCheck:$100,000
To:FM 2818Misc Cost:$37,500.00
Estimate$9,969,859.69% Over/UnderCompany
Bidder 1$10,186,765.85+2.18%F. N. PLOCH CONSTRUCTION COMPANY, INC.
Bidder 2$10,391,142.29+4.23%NEWMAN & KENG PAVING COMPANY, INC.
Bidder 3$11,752,800.64+17.88%RONALD R. WAGNER & CO., LP
State Let Construction Projects for October, 2018

Text version of this page
County:ANGELINALet Date:10/02/18
Type:INSTALL PROFILE PAVEMENT MARKINGSSeq No:3014
Time:118 WORKING DAYSProject ID:C 911-00-78
Highway:VAContract #:10183014
Length:253.682CCSJ:0911-00-078
Limits: 
From:VARIOUS LOCATIONS DISTRICTWIDECheck:$27,000
To:.Misc Cost:$1,000.00
Estimate$1,339,332.60% Over/UnderCompany
Bidder 1$1,368,036.18+2.14%PMI PAVEMENT MARKING, INC.
Bidder 2$1,562,072.76+16.63%STRIPE-A-ZONE, INC.
Bidder 3$1,578,986.50+17.89%INTERSTATE BARRICADES & MARKINGS, INC.
Bidder 4$1,980,862.80+47.90%STRIPING TECHNOLOGY, L.P.
Bidder 5$1,990,935.88+48.65%TRP CONSTRUCTION GROUP, LLC
Bidder 6$2,535,632.44+89.32%TOTAL HIGHWAY MAINTENANCE, LLC
State Let Construction Projects for October, 2018

Text version of this page
County:GRAYSONLet Date:10/02/18
Type:REVERSE EXISTING RAMP CONFIGURATIONSeq No:3015
Time:149 WORKING DAYSProject ID:CC 47-3-89
Highway:US 75Contract #:10183015
Length:1.171CCSJ:0047-03-089
Limits: 
From:FM 1417Check:$41,000
To:1.171 MILES SOUTH OF FM 1417Misc Cost:$10,000.00
Estimate$2,059,519.97% Over/UnderCompany
Bidder 1$2,328,633.32+13.07%ED BELL CONSTRUCTION COMPANY
Bidder 2$2,343,605.58+13.79%OVERLAND CORPORATION
Bidder 3$2,494,536.14+21.12%ACCELERATED CRITICAL PATH, INC.
Bidder 4$2,864,878.91+39.10%EAST TEXAS BRIDGE, INC.
Bidder 5$3,399,427.30+65.06%FNH CONSTRUCTION, LLC
State Let Construction Projects for October, 2018

Text version of this page
County:CAMERONLet Date:10/02/18
Type:OVERLAYSeq No:3016
Time:152 WORKING DAYSProject ID:NH 2019(112)
Highway:IH 2Contract #:10183016
Length:9.276CCSJ:0039-19-061
Limits: 
From:HIDALGO/CAMERON CLCheck:$100,000
To:DIXIELAND RD.Misc Cost:$151,500.00
Estimate$9,358,694.94% Over/UnderCompany
Bidder 1$8,734,018.37-6.67%TEXAS SAI, INC.
Bidder 2$8,935,940.35-4.52%EARTHWORKS ENTERPRISE
Bidder 3$9,905,641.45+5.84%FOREMOST PAVING, INC.
Bidder 4$10,544,518.31+12.67%IOC COMPANY LLC
Bidder 5$11,194,188.71+19.61%ANDERSON COLUMBIA CO., INC.
State Let Construction Projects for October, 2018

Text version of this page
County:AUSTINLet Date:10/02/18
Type:REPLACE BRIDGE AND APPROACHESSeq No:3017
Time:120 WORKING DAYSProject ID:BR 2019(099)
Highway:FM 2429Contract #:10183017
Length:0.445CCSJ:2320-01-011
Limits: 
From:AT MILL CREEKCheck:$36,000
To:STR # 2320-01-002Misc Cost:$1,500.00
Estimate$1,789,448.15% Over/UnderCompany
Bidder 1$1,839,845.51+2.82%ANGEL BROTHERS HOLDINGS CORP.
Bidder 2$2,162,356.81+20.84%ISI CONTRACTING, INC.
Bidder 3$2,188,445.95+22.30%FUQUA CONSTRUCTION CO., INC.
Bidder 4$2,214,216.83+23.74%KNIFE RIVER CORPORATION - SOUTH
Bidder 5$2,291,163.34+28.04%JOHN REED AND COMPANY, LLC
Bidder 6$2,428,140.10+35.69%HODGES AND SON CONSTRUCTION COMPANY, INC.
State Let Construction Projects for October, 2018

Text version of this page
County:MCLENNANLet Date:10/02/18
Type:REHAB & WDN RDWYSeq No:3018
Time:510 WORKING DAYSProject ID:STP 1802(320)
Highway:FM 2114Contract #:10183018
Length:11.931CCSJ:2061-02-030
Limits: 
From:FM 2311Check:$100,000
To:HILL CO LINEMisc Cost:$20,000.00
Estimate$9,350,224.38% Over/UnderCompany
Bidder 1$9,997,468.08+6.92%BIG CREEK CONSTRUCTION, LTD.
Bidder 2$9,997,939.90+6.93%KNIFE RIVER CORPORATION - SOUTH
Bidder 3$10,396,249.37+11.19%OLDCASTLE MATERIALS TEXAS, INC.
Bidder 4$13,309,571.66+42.34%ED BELL CONSTRUCTION COMPANY
State Let Construction Projects for October, 2018

Text version of this page
County:BEXARLet Date:10/02/18
Type:INSTALL RAISED MEDIAN WITH ACTATED PED SYMBOLSSeq No:3019
Time:58 WORKING DAYSProject ID:STP 2019(067)HES
Highway:SS 421Contract #:10183019
Length:0.602CCSJ:0291-11-021
Limits: 
From:0.1 ME WEST OF GOODRICHCheck:$4,000
To:0.1 MI EAST OF HAMILTONMisc Cost:$18,800.00
Estimate$189,782.67% Over/UnderCompany
Bidder 1$320,840.00+69.06%FNH CONSTRUCTION, LLC
State Let Construction Projects for October, 2018

Text version of this page
County:SWISHERLet Date:10/02/18
Type:SCRUB SEALSeq No:3020
Time:49 WORKING DAYSProject ID:STP 2019(102)
Highway:FM 146Contract #:10183020
Length:72.380CCSJ:0357-04-019
Limits: 
From:VARIOUS LOCATIONSCheck:$42,000
To:IN LUBBOCK DISTRICTMisc Cost:$10,000.00
Estimate$2,075,444.00% Over/UnderCompany
Bidder 1$1,899,776.17-8.46%CDM HOLDINGS, LLC
Bidder 2$1,952,339.28-5.93%LIPHAM ASPHALT AND PAVING COMPANY, LLC
Bidder 3$2,394,074.80+15.35%INTERMOUNTAIN SLURRY SEAL, INC.
State Let Construction Projects for October, 2018

Text version of this page
County:BOWIELet Date:10/02/18
Type:SEAL COATSeq No:3021
Time:75 WORKING DAYSProject ID:STP 2019(131)
Highway:US 67Contract #:10183021
Length:15.796CCSJ:0010-11-072
Limits: 
From:ANDERSON CREEKCheck:$100,000
To:CASS C/LMisc Cost:$20,000.00
Estimate$7,798,156.70% Over/UnderCompany
Bidder 1$6,997,654.55-10.27%MISSOURI PETROLEUM PRODUCTS COMPANY LLC
Bidder 2$7,331,298.45-5.99%CDM HOLDINGS, LLC
Bidder 3$9,628,485.54+23.47%RONALD R. WAGNER & CO., LP
State Let Construction Projects for October, 2018

Text version of this page
County:BRAZORIALet Date:10/02/18
Type:REMOVE AND REPLACE EXISTING DRAINAGE STRUCTURESeq No:3022
Time:55 WORKING DAYSProject ID:C 586-1-67
Highway:SH 332Contract #:10183022
Length:0.024CCSJ:0586-01-067
Limits: 
From:0.102 MILES EAST OF LEVEE ROADCheck:$9,000
To:.Misc Cost:$13,900.00
Estimate$455,071.13% Over/UnderCompany
Bidder 1$433,600.50-4.72%EARTH BUILDERS, L.P.
Bidder 2$547,625.40+20.34%MAIN LANE INDUSTRIES LTD.
Bidder 3$581,190.65+27.71%ISI CONTRACTING, INC.
Bidder 4$594,897.00+30.73%TEXCON GENERAL CONTRACTORS
Bidder 5$615,055.90+35.16%FNH CONSTRUCTION, LLC
Bidder 6$705,999.00+55.14%NBG CONSTRUCTORS, INC.
Bidder 7$739,708.00+62.55%L.C. JORDAN & SON
State Let Construction Projects for October, 2018