Last Update: Wednesday, April 24, 2024
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings.
Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and
intended for informational purposes only.
|
|
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 |
|
Text version of this page |
County: | HAMILTON | Let Date: | 04/04/24 |
Type: | INTERSECTION IMPROVEMENT | Seq No: | 3033 |
Time: | 30 WORKING DAYS | Project ID: | STP 2024(857)HES |
Highway: | FM 1602 | Contract #: | 04243033 |
Length: | 0.000 | CCSJ: | 0774-03-015 |
Limits: | |
From: | 0.10 MI N OF SH22 | Check: | $3,000 |
To: | SH22 | Misc Cost: | |
Text version of this page |
County: | VAN ZANDT | Let Date: | 04/04/24 |
Type: | HAZARD ELIMINATION & SAFETY | Seq No: | 3034 |
Time: | 72 WORKING DAYS | Project ID: | STP 2024(855)HES |
Highway: | VA | Contract #: | 04243034 |
Length: | 0.000 | CCSJ: | 0910-12-141 |
Limits: | |
From: | VARIOUS LOCATIONS IN | Check: | $9,000 |
To: | VAN ZANDT CO | Misc Cost: | |
Text version of this page |
County: | ROBERTSON | Let Date: | 04/04/24 |
Type: | BRIDGE MAINTENANCE | Seq No: | 3035 |
Time: | 57 WORKING DAYS | Project ID: | C 917-18-89 |
Highway: | VA | Contract #: | 04243035 |
Length: | 0.000 | CCSJ: | 0917-18-089 |
Limits: | |
From: | VARIOUS LOCATIONS | Check: | $6,000 |
To: | IN ROBERTSON COUNTY | Misc Cost: | |
Text version of this page |
County: | CALDWELL | Let Date: | 04/04/24 |
Type: | LANDSCAPE DEVELOPMENT | Seq No: | 3036 |
Time: | 102 WORKING DAYS | Project ID: | C 152-2-71 |
Highway: | US 183 | Contract #: | 04243036 |
Length: | 0.000 | CCSJ: | 0152-02-071 |
Limits: | |
From: | CEMETERY STREET | Check: | $6,000 |
To: | CITY PARK ROAD | Misc Cost: | |
Text version of this page |
County: | HALE | Let Date: | 04/04/24 |
Type: | REHABILITATE EXISTING ROADWAY | Seq No: | 3037 |
Time: | 146 WORKING DAYS | Project ID: | C 905-12-45 |
Highway: | VA | Contract #: | 04243037 |
Length: | 0.000 | CCSJ: | 0905-12-045 |
Limits: | |
From: | VARIOUS LOCATIONS IN | Check: | $37,000 |
To: | HALE COUNTY | Misc Cost: | $18,001.00 |
Estimate | $1,838,550.00 | % Over/Under | Company |
Bidder 1 | $1,747,472.00 | -4.95% | WINDING ROAD CONSTRUCTION, INC. |
Bidder 2 | $1,813,836.00 | -1.34% | O. TREVINO CONSTRUCTION, LLC |
Bidder 3 | $2,349,600.00 | +27.80% | SCR CIVIL CONSTRUCTION, LLC |
Text version of this page |
County: | ROCKWALL | Let Date: | 04/04/24 |
Type: | BRIDGE MAINTENANCE | Seq No: | 3038 |
Time: | 112 WORKING DAYS | Project ID: | F 2024(948) |
Highway: | SH 66 | Contract #: | 04243038 |
Length: | 1.131 | CCSJ: | 0009-04-077 |
Limits: | |
From: | WEST OF SH 205 | Check: | $82,000 |
To: | WEST OF SH 205 | Misc Cost: | |
Estimate | $4,123,571.00 | % Over/Under | Company |
Bidder 1 | $2,188,896.00 | -46.92% | RAGLE CONSTRUCTION, INC. |
Bidder 2 | $2,781,360.00 | -32.55% | SOUTHERN ROAD & BRIDGE, LLC |
Bidder 3 | $5,445,500.00 | +32.06% | FNH CONSTRUCTION, LLC |
Bidder 4 | $8,469,880.00 | +105.40% | SCR CIVIL CONSTRUCTION, LLC |
Text version of this page |
County: | SMITH | Let Date: | 04/04/24 |
Type: | HAZARD ELIMINATION & SAFETY | Seq No: | 3039 |
Time: | 47 WORKING DAYS | Project ID: | F 2024(958) |
Highway: | VA | Contract #: | 04243039 |
Length: | 1.000 | CCSJ: | 0910-00-123 |
Limits: | |
From: | VARIOUS LOCATIONS IN | Check: | $34,000 |
To: | THE TYLER DISTRICT | Misc Cost: | |
Estimate | $1,721,002.46 | % Over/Under | Company |
Bidder 1 | $1,144,487.99 | -33.50% | STRIPE-A-ZONE, LLC |
Bidder 2 | $1,508,385.85 | -12.35% | STRIPING TECHNOLOGY, L.P. |
Bidder 3 | $1,599,599.99 | -7.05% | BATTERSON, LLP |
Bidder 4 | $1,837,015.13 | +6.74% | INTERSTATE BARRICADES & MARKINGS, INC. |
Text version of this page |
County: | HARRISON | Let Date: | 04/04/24 |
Type: | INSTALL ILLUMINATION | Seq No: | 3040 |
Time: | 170 WORKING DAYS | Project ID: | STP 2B24(045)VRU |
Highway: | US 59 | Contract #: | 04243040 |
Length: | 9.000 | CCSJ: | 0062-07-103 |
Limits: | |
From: | AT FM 1997 | Check: | $27,000 |
To: | . | Misc Cost: | $27,400.00 |
Text version of this page |
County: | DAWSON | Let Date: | 04/04/24 |
Type: | WIDEN ROAD - ADD LANES AND SHOULDERS | Seq No: | 3041 |
Time: | 236 WORKING DAYS | Project ID: | C 68-5-40 |
Highway: | US 87 | Contract #: | 04243041 |
Length: | 0.000 | CCSJ: | 0068-05-040 |
Limits: | |
From: | 0.5 MILES NORTH OF US 349 | Check: | $100,000 |
To: | 0.5 MILES SOUTH OF US 349 | Misc Cost: | |
Estimate | $12,007,909.75 | % Over/Under | Company |
Bidder 1 | $14,793,665.35 | +23.20% | A. L. HELMCAMP, INC. |
Bidder 2 | $14,978,220.25 | +24.74% | JAMES HAMILTON CONSTRUCTION CO. |
Bidder 3 | $18,552,412.53 | +54.50% | KIEWIT INFRASTRUCTURE SOUTH CO. |
Bidder 4 | $21,401,374.85 | +78.23% | WEBBER, LLC |
Text version of this page |
County: | COOKE | Let Date: | 04/05/24 |
Type: | WIDEN ROAD - ADD LANES | Seq No: | 3202 |
Time: | 1588 WORKING DAYS | Project ID: | F 2024(845) |
Highway: | IH 35 | Contract #: | 04243202 |
Length: | 13.951 | CCSJ: | 0194-01-010 |
Limits: | |
From: | ON IH 35 AT THE RED RIVER BRIDGE | Check: | $100,000 |
To: | . | Misc Cost: | |
Text version of this page |
County: | GRAYSON | Let Date: | 04/05/24 |
Type: | PREVENTIVE MAINTENANCE | Seq No: | 3203 |
Time: | 80 WORKING DAYS | Project ID: | C 81-10-52 |
Highway: | US 377 | Contract #: | 04243203 |
Length: | 14.380 | CCSJ: | 0081-10-052 |
Limits: | |
From: | OKLAHOMA STATE LINE | Check: | $100,000 |
To: | US 82 | Misc Cost: | |
Estimate | $7,559,041.75 | % Over/Under | Company |
Bidder 1 | $5,667,808.58 | -25.02% | OVERLAND CORPORATION |
Bidder 2 | $6,962,836.40 | -7.89% | JAGOE-PUBLIC COMPANY |
Bidder 3 | $7,135,620.75 | -5.60% | RK HALL, LLC |
Bidder 4 | $9,156,454.75 | +21.13% | FNH CONSTRUCTION, LLC |
Text version of this page |
County: | HARRIS | Let Date: | 04/05/24 |
Type: | REHAB OF DYNAMIC MESSAGE SIGN | Seq No: | 3204 |
Time: | 180 WORKING DAYS | Project ID: | F 2024(900) |
Highway: | VA | Contract #: | 04243204 |
Length: | 0.000 | CCSJ: | 0912-00-700 |
Limits: | |
From: | VARIOUS LOCATIONS DISTRICTWIDE | Check: | $32,000 |
To: | . | Misc Cost: | |
Estimate | $1,620,463.24 | % Over/Under | Company |
Bidder 1 | $862,600.00 | -46.77% | TRAF-TEX, INC. |
Bidder 2 | $888,681.00 | -45.16% | FLORIDA TRAFFIC CONTROL DEVICES, INC. |
Bidder 3 | $1,064,018.00 | -34.34% | SICE, INC. |
Bidder 4 | $1,229,609.04 | -24.12% | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC |
Text version of this page |
County: | LIVE OAK | Let Date: | 04/05/24 |
Type: | RESURFACE ROADWAY | Seq No: | 3205 |
Time: | 228 WORKING DAYS | Project ID: | C 73-7-71 |
Highway: | IH 37 | Contract #: | 04243205 |
Length: | 0.000 | CCSJ: | 0073-07-071 |
Limits: | |
From: | ATASCOSA COUNTY LINE | Check: | $100,000 |
To: | 3.9 MILES NORTH OF SH 72 | Misc Cost: | |
Text version of this page |
County: | UPSHUR | Let Date: | 04/05/24 |
Type: | SURFACING/ROADWAY RESTORATION | Seq No: | 3206 |
Time: | 0 X | Project ID: | C 248-5-65 |
Highway: | US 271 | Contract #: | 04243206 |
Length: | 4.169 | CCSJ: | 0248-05-065 |
Limits: | |
From: | 0.06 MI N OF FM 726 | Check: | $100,000 |
To: | GREGG C/L | Misc Cost: | |
Estimate | $6,868,830.40 | % Over/Under | Company |
Bidder 1 | $5,280,510.75 | -23.12% | MADDEN CONTRACTING COMPANY, LLC. |
Bidder 2 | $6,340,007.75 | -7.70% | LONGVIEW BRIDGE AND ROAD, LTD. |
Bidder 3 | $6,811,877.10 | -0.83% | EAST TEXAS BRIDGE, INC. |
Text version of this page |
County: | JASPER | Let Date: | 04/05/24 |
Type: | SURFACING/ROADWAY RESTORATION | Seq No: | 3207 |
Time: | 147 WORKING DAYS | Project ID: | BR 2024(854) |
Highway: | FM 777 | Contract #: | 04243207 |
Length: | 0.040 | CCSJ: | 1109-01-026 |
Limits: | |
From: | 4.9 MILES S OF US 190 AT AIRPORT, N | Check: | $100,000 |
To: | US 190 AT AIRPORT | Misc Cost: | |
Text version of this page |
County: | COMAL | Let Date: | 04/05/24 |
Type: | BICYCLE AND PEDESTRIAN IMPROVEMENTS | Seq No: | 3208 |
Time: | 158 WORKING DAYS | Project ID: | STP 2024(925)MM |
Highway: | FM 306 | Contract #: | 04243208 |
Length: | 0.630 | CCSJ: | 1728-02-065 |
Limits: | |
From: | GUADALUPE RIVER- EASTERN CROSSSING | Check: | $100,000 |
To: | GUADALUPE RIVER- WESTERN CROSSING | Misc Cost: | |
Estimate | $7,166,421.67 | % Over/Under | Company |
Bidder 1 | $7,171,215.50 | +0.07% | ENCINO LANDSCAPE, INC. |
Bidder 2 | $7,932,389.00 | +10.69% | CAPITAL EXCAVATION COMPANY |
Bidder 3 | $8,383,708.62 | +16.99% | RELMCO, INC. |
Bidder 4 | $8,914,300.00 | +24.39% | HARPER BROTHERS CONSTRUCTION LLC |
Bidder 5 | $9,356,590.52 | +30.56% | STERLING DELAWARE HOLDING COMPANY |
Bidder 6 | $9,431,457.01 | +31.61% | ALTUS CONSTRUCTION LLC |