Last Update: Friday, September 06, 2024
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings.
Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and
intended for informational purposes only.
|
|
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 |
|
Text version of this page |
County: | TRAVIS | Let Date: | 07/10/24 |
Type: | BRIDGE MAINTENANCE | Seq No: | 3219 |
Time: | 192 WORKING DAYS | Project ID: | C 914-00-533 |
Highway: | VA | Contract #: | 07243219 |
Length: | 0.000 | CCSJ: | 0914-00-533 |
Limits: | |
From: | VARIOUS LOCATIONS IN BASTROP AND | Check: | $71,000 |
To: | TRAVIS COUNTIES | Misc Cost: | |
Text version of this page |
County: | HARRIS | Let Date: | 07/10/24 |
Type: | TRAFFIC SIGNAL IMPROVEMENTS | Seq No: | 3220 |
Time: | 395 WORKING DAYS | Project ID: | F 2B24(233) |
Highway: | VA | Contract #: | 07243220 |
Length: | 0.001 | CCSJ: | 0912-00-613 |
Limits: | |
From: | VARIOUS LOCATIONS DISTRICTWIDE | Check: | $61,000 |
To: | . | Misc Cost: | |
Estimate | $3,044,926.73 | % Over/Under | Company |
Bidder 1 | $3,278,706.50 | +7.68% | STATEWIDE TRAFFIC SIGNAL COMPANY |
Bidder 2 | $3,379,359.94 | +10.98% | THIRD COAST SERVICES LLC |
Bidder 3 | $3,954,015.25 | +29.86% | TRAF-TEX, INC. |
Bidder 4 | $4,255,141.00 | +39.75% | SELECT MAINTENANCE, L.L.C. |
Text version of this page |
County: | JEFFERSON | Let Date: | 07/10/24 |
Type: | BRIDGE MAINTENANCE | Seq No: | 3221 |
Time: | 50 WORKING DAYS | Project ID: | C 920-00-157 |
Highway: | VA | Contract #: | 07243221 |
Length: | 0.000 | CCSJ: | 0920-00-157 |
Limits: | |
From: | DISTRICT WIDE | Check: | $60,000 |
To: | . | Misc Cost: | |
Estimate | $2,997,259.00 | % Over/Under | Company |
Bidder 1 | $2,547,180.00 | -15.02% | ICOS MANAGEMENT, LLC |
Bidder 2 | $2,862,100.00 | -4.51% | MB WESTERN INDUSTRIAL CONTRACTING CO. |
Bidder 3 | $2,993,590.00 | -0.12% | AAD CONTRACTING INC. |
Bidder 4 | $3,529,350.00 | +17.75% | FNH CONSTRUCTION, LLC |
Bidder 5 | $3,597,214.50 | +20.02% | RAGLE CONSTRUCTION, INC. |
Text version of this page |
County: | HARRIS | Let Date: | 07/10/24 |
Type: | REHABILITATE BRIDGE | Seq No: | 3222 |
Time: | 153 WORKING DAYS | Project ID: | F 2B24(235) |
Highway: | VA | Contract #: | 07243222 |
Length: | 0.000 | CCSJ: | 0912-72-771 |
Limits: | |
From: | VARIOUS LOCATIONS IN SOUTH HARRIS A | Check: | $50,000 |
To: | . | Misc Cost: | |
Estimate | $2,495,636.00 | % Over/Under | Company |
Bidder 1 | $2,164,229.93 | -13.28% | ISI CONTRACTING, INC. |
Bidder 2 | $2,604,363.19 | +4.36% | MB WESTERN INDUSTRIAL CONTRACTING CO. |
Bidder 3 | $3,931,992.50 | +57.55% | MC2 CIVIL, LLC |
Bidder 4 | $4,376,881.92 | +75.38% | RAGLE CONSTRUCTION, INC. |
Text version of this page |
County: | MCLENNAN | Let Date: | 07/10/24 |
Type: | HAZARD ELIMINATION & SAFETY | Seq No: | 3223 |
Time: | 60 WORKING DAYS | Project ID: | STP 2B24(285)HES |
Highway: | FM 1695 | Contract #: | 07243223 |
Length: | 0.000 | CCSJ: | 2506-01-045 |
Limits: | |
From: | US 84 | Check: | $10,000 |
To: | FM 2063 | Misc Cost: | |
Estimate | $476,255.27 | % Over/Under | Company |
Bidder 1 | $463,681.00 | -2.64% | GARRET SHIELDS INFRASTRUCTURE |
Bidder 2 | $476,286.65 | +0.01% | RHINO EQUITY, LLC |
Bidder 3 | $532,606.25 | +11.83% | STX CIVIL |
Bidder 4 | $533,861.50 | +12.10% | RISE UP CONSTRUCTION LLC |
Bidder 5 | $614,660.90 | +29.06% | AAD CONTRACTING INC. |
Bidder 6 | $686,507.95 | +44.15% | BEAR CREEK CONTRACTING, LLC |
Bidder 7 | $771,551.08 | +62.00% | TALBERT COMPANIES LLC |
Bidder 8 | $772,725.70 | +62.25% | DIGG COMMERCIAL, LLC |
Bidder 9 | $863,065.50 | +81.22% | ROY JORGENSEN ASSOCIATES, INC. |
Text version of this page |
County: | WHEELER | Let Date: | 07/10/24 |
Type: | BRIDGE REPLACEMENT | Seq No: | 3224 |
Time: | 235 WORKING DAYS | Project ID: | BR 2B24(267) |
Highway: | FM 1547 | Contract #: | 07243224 |
Length: | 0.040 | CCSJ: | 0761-03-021 |
Limits: | |
From: | @ LONG DRY CREEK | Check: | $71,000 |
To: | . | Misc Cost: | |
Estimate | $3,538,438.50 | % Over/Under | Company |
Bidder 1 | $3,197,364.70 | -9.64% | SKYLINE BRIDGE LLC |
Bidder 2 | $3,212,333.93 | -9.22% | TALBERT COMPANIES LLC |
Bidder 3 | $3,768,321.09 | +6.50% | C. E. BARKER, LTD. |
Bidder 4 | $3,858,990.60 | +9.06% | EARTH BUILDERS, L.P. |
Bidder 5 | $4,044,234.25 | +14.29% | L A FULLER & SONS CONSTRUCTION, LTD. |
Bidder 6 | $5,164,150.00 | +45.94% | HODGES AND SON CONSTRUCTION COMPANY, INC. |
Text version of this page |
County: | LEE | Let Date: | 07/10/24 |
Type: | RESURFACE ROADWAY | Seq No: | 3225 |
Time: | 32 WORKING DAYS | Project ID: | C 114-7-87 |
Highway: | US 290 | Contract #: | 07243225 |
Length: | 0.000 | CCSJ: | 0114-07-087 |
Limits: | |
From: | NAVARRO | Check: | $45,000 |
To: | CR 226 | Misc Cost: | |
Estimate | $2,259,300.78 | % Over/Under | Company |
Bidder 1 | $2,209,194.34 | -2.22% | LONE STAR PAVING COMPANY |
Bidder 2 | $2,532,207.84 | +12.08% | TEXAS MATERIALS GROUP, INC. |
Bidder 3 | $2,636,801.61 | +16.71% | KNIFE RIVER CORPORATION - SOUTH |
Bidder 4 | $3,483,991.56 | +54.21% | HUNTER INDUSTRIES, LTD. |
Text version of this page |
County: | TRAVIS | Let Date: | 07/10/24 |
Type: | BRIDGE MAINTENANCE | Seq No: | 3226 |
Time: | 260 WORKING DAYS | Project ID: | C 914-00-507 |
Highway: | VA | Contract #: | 07243226 |
Length: | 0.000 | CCSJ: | 0914-00-507 |
Limits: | |
From: | VARIOUS LOCATIONS DISTRICTWIDE | Check: | $37,000 |
To: | . | Misc Cost: | |
Estimate | $1,841,608.68 | % Over/Under | Company |
Bidder 1 | $2,572,807.00 | +39.70% | TAYLOR CONTRACTING LLC |
Bidder 2 | $3,023,398.00 | +64.17% | SCR CIVIL CONSTRUCTION, LLC |
Bidder 3 | $4,021,840.00 | +118.39% | ROY JORGENSEN ASSOCIATES, INC. |
Text version of this page |
County: | TARRANT | Let Date: | 07/10/24 |
Type: | TRAFFIC SIGNAL IMPROVEMENTS | Seq No: | 3227 |
Time: | 400 WORKING DAYS | Project ID: | C 902-00-290 |
Highway: | VA | Contract #: | 07243227 |
Length: | 0.000 | CCSJ: | 0902-00-290 |
Limits: | |
From: | VARIOUS LOCATIONS | Check: | $39,000 |
To: | DISTRICTWIDE FY 2024 | Misc Cost: | |
Text version of this page |
County: | FANNIN | Let Date: | 07/10/24 |
Type: | BRIDGE REPLACEMENT | Seq No: | 3228 |
Time: | 139 WORKING DAYS | Project ID: | BR 2B24(278) |
Highway: | FM 68 | Contract #: | 07243228 |
Length: | 0.249 | CCSJ: | 0620-01-019 |
Limits: | |
From: | AT NORTH SULPHUR RIVER | Check: | $62,000 |
To: | . | Misc Cost: | |
Estimate | $3,101,166.30 | % Over/Under | Company |
Bidder 1 | $2,823,236.80 | -8.96% | L & N BRIDGE, LLC |
Bidder 2 | $3,071,967.61 | -0.94% | TALBERT COMPANIES LLC |
Bidder 3 | $3,548,109.70 | +14.41% | C. E. BARKER, LTD. |
Bidder 4 | $3,974,756.90 | +28.17% | HODGES AND SON CONSTRUCTION COMPANY, INC. |
Bidder 5 | $4,242,106.10 | +36.79% | EAST TEXAS BRIDGE, INC. |
Bidder 6 | $4,493,861.62 | +44.91% | RAGLE CONSTRUCTION, INC. |
Text version of this page |
County: | SCHLEICHER | Let Date: | 07/10/24 |
Type: | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | Seq No: | 3229 |
Time: | 209 WORKING DAYS | Project ID: | STP 2023(590)TAPS |
Highway: | CS | Contract #: | 07243229 |
Length: | 0.000 | CCSJ: | 0907-26-006 |
Limits: | |
From: | VARIOUS LOCATIONS IN ELDORADO, TEXA | Check: | $22,000 |
To: | - | Misc Cost: | |
Estimate | $1,081,905.25 | % Over/Under | Company |
Bidder 1 | $767,531.16 | -29.06% | TALBERT COMPANIES LLC |
Bidder 2 | $847,794.40 | -21.64% | DORADO CONSTRUCTION GROUP |
Bidder 3 | $886,197.88 | -18.09% | PROJECT ALLIED RESOURCES, LLC |
Bidder 4 | $973,312.00 | -10.04% | LCR TOTAL TRANSPORT LLC |
Bidder 5 | $985,624.00 | -8.90% | DELGADO'S CONTRACTORS, LLC |
Bidder 6 | $989,816.18 | -8.51% | TI-ZACK CONCRETE, LLC |
Bidder 7 | $995,610.00 | -7.98% | DIGG COMMERCIAL, LLC |
Bidder 8 | $1,330,614.00 | +22.99% | FNH CONSTRUCTION, LLC |
Text version of this page |
County: | SMITH | Let Date: | 07/10/24 |
Type: | HAZARD ELIMINATION & SAFETY | Seq No: | 3230 |
Time: | 72 WORKING DAYS | Project ID: | STP 2023(830)HESG |
Highway: | CR | Contract #: | 07243230 |
Length: | 0.000 | CCSJ: | 0910-16-171 |
Limits: | |
From: | @ SAMUEL DR | Check: | $3,000 |
To: | . | Misc Cost: | $2,000.00 |
Text version of this page |
County: | DEWITT | Let Date: | 07/10/24 |
Type: | HIGHWAY IMPROVEMENT | Seq No: | 3231 |
Time: | 48 WORKING DAYS | Project ID: | CC 942-10-20 |
Highway: | FM 240 | Contract #: | 07243231 |
Length: | 0.343 | CCSJ: | 0942-01-020 |
Limits: | |
From: | US 87 | Check: | $14,000 |
To: | .385 MILES SOUTH OF US 87 | Misc Cost: | |
Estimate | $685,862.75 | % Over/Under | Company |
Bidder 1 | $898,096.88 | +30.94% | C. E. BARKER, LTD. |
Bidder 2 | $1,018,779.68 | +48.54% | ACME BRIDGE COMPANY, INC. |
Bidder 3 | $1,054,352.77 | +53.73% | HUNTER INDUSTRIES, LTD. |
Bidder 4 | $1,068,480.89 | +55.79% | CLARK CONSTRUCTION OF TEXAS, INC. |
Bidder 5 | $1,078,751.38 | +57.28% | DEAN WORD COMPANY, LTD. |
Bidder 6 | $1,091,828.10 | +59.19% | CK NEWBERRY, LLC |
Text version of this page |
County: | FRANKLIN | Let Date: | 07/10/24 |
Type: | BRIDGE MAINTENANCE | Seq No: | 3232 |
Time: | 61 WORKING DAYS | Project ID: | F 2B24(422) |
Highway: | IH 30 | Contract #: | 07243232 |
Length: | 0.140 | CCSJ: | 0610-02-065 |
Limits: | |
From: | AT CR 2080 | Check: | $15,000 |
To: | . | Misc Cost: | |
Estimate | $731,922.00 | % Over/Under | Company |
Bidder 1 | $564,885.00 | -22.82% | THK CONSTRUCTION LLC |
Bidder 2 | $624,740.00 | -14.64% | EAST TEXAS BRIDGE, INC. |
Bidder 3 | $699,110.00 | -4.48% | AAD CONTRACTING INC. |
Bidder 4 | $994,830.00 | +35.92% | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC |
Bidder 5 | $1,004,740.00 | +37.27% | RHINO EQUITY, LLC |
Text version of this page |
County: | POTTER | Let Date: | 07/09/24 |
Type: | METAL BEAM GUARD FENCE REPAIR | Seq No: | 4001 |
Time: | 365 CALENDAR DAYS | Project ID: | RMC - 646876001 |
Highway: | IH0040 | Contract #: | 07244001 |
Length: | 0.010 | CCSJ: | 6468-76-001 |
Limits: | |
From: | VARIOUS LOCATIONS- SEE PLAN SHEETS | Check: | $15,000 |
To: | VARIOUS LOCATIONS-SEE PLAN SHEETS | Misc Cost: | |
Text version of this page |
County: | CARSON | Let Date: | 07/09/24 |
Type: | MILL AND INLAY | Seq No: | 4002 |
Time: | 365 CALENDAR DAYS | Project ID: | RMC - 646903001 |
Highway: | IH0040 | Contract #: | 07244002 |
Length: | 0.010 | CCSJ: | 6469-03-001 |
Limits: | |
From: | VARIOUS LOCATIONS- SEE PLAN SHEETS | Check: | $68,000 |
To: | VARIOUS LOCATIONS-SEE PLAN SHEETS | Misc Cost: | |