Bid Totals Page 9 of 31

Last Update: Wednesday, June 29, 2022

Site improvements have arrived.

New interactive dashboards on TxDOT.gov make it simple for you to quickly find relevant and up-to-date information. Access them here

Need help finding something? Check out this information page for more details.

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.


1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31

Text version of this page
County:ARANSASLet Date:05/05/22
Type:INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFTSeq No:3226
Time:85 WORKING DAYSProject ID:C 180-5-65
Highway:BS 35-LContract #:05223226
Length:0.845CCSJ:0180-05-065
Limits: 
From:.88 MI N. OF SH 188Check:$29,000
To:SH 188Misc Cost:
Estimate$1,425,124.75% Over/UnderCompany
Bidder 1$1,836,179.00+28.84%TEXAS STEEL INDUSTRIAL PLACING, LLC
Bidder 2$1,900,603.50+33.36%CK NEWBERRY, LLC
Bidder 3$1,929,822.20+35.41%J E CONSTRUCTION SERVICES, LLC
State Let Construction Projects for May, 2022

Text version of this page
County:AUSTINLet Date:05/05/22
Type:BRIDGE REPLACEMENTSeq No:3227
Time:172 WORKING DAYSProject ID:BR 2020(686)
Highway:CRContract #:05223227
Length:0.300CCSJ:0913-20-093
Limits: 
From:AT DRAWCheck:$26,000
To:STR# AA03-13-002 (KIEMSTEADT RD)Misc Cost:
Estimate$1,314,061.00% Over/UnderCompany
Bidder 1$1,258,243.82-4.25%FUQUA CONSTRUCTION CO., INC.
Bidder 2$1,556,463.54+18.45%MB WESTERN INDUSTRIAL CONTRACTING COMPANY
Bidder 3$1,564,704.45+19.07%SB CONTRACTORS LLC
Bidder 4$1,685,524.80+28.27%KNIFE RIVER CORPORATION - SOUTH
Bidder 5$1,966,075.50+49.62%EARTH BUILDERS, L.P.
State Let Construction Projects for May, 2022

Text version of this page
County:BELLLet Date:05/05/22
Type:HAZARD ELIMINATION & SAFETYSeq No:3228
Time:45 WORKING DAYSProject ID:STP 2022(479)HES
Highway:SH 36Contract #:05223228
Length:4.293CCSJ:0184-04-053
Limits: 
From:SH 53Check:$10,000
To:.5 MI W OF IH 35Misc Cost:
Estimate$487,589.40% Over/UnderCompany
Bidder 1$586,558.01+20.30%ROADWAY SPECIALTIES, INC.
Bidder 2$681,447.00+39.76%MASSANA CONSTRUCTION INC.
Bidder 3$698,435.10+43.24%DAN WILLIAMS COMPANY
Bidder 4$699,456.30+43.45%O. TREVINO CONSTRUCTION, LLC
Bidder 5$703,037.14+44.19%SCR CIVIL CONSTRUCTION, LLC
Bidder 6$773,378.40+58.61%GRATIOT CONSTRUCTION, LTD.
State Let Construction Projects for May, 2022

Text version of this page
County:WICHITALet Date:05/05/22
Type:INSTALL ILLUMINATIONSeq No:3229
Time:78 WORKING DAYSProject ID:F 2022(377)
Highway:VAContract #:05223229
Length:0.000CCSJ:0903-00-120
Limits: 
From:VARIOUS LOCATIONS INCheck:$13,000
To:COOKE AND MONTAGUE COUNTIESMisc Cost:
Estimate$633,165.40% Over/UnderCompany
Bidder 1$833,158.86+31.59%WG ENGINEERING & CONSTRUCTION, LLC
Bidder 2$849,038.21+34.09%HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
Bidder 3$881,898.52+39.28%SIEMENS MOBILITY, INC.
Bidder 4$942,539.33+48.86%MICA CORPORATION
Bidder 5$980,906.95+54.92%SOUTH TEXAS ILLUMINATION, LLC
State Let Construction Projects for May, 2022

Text version of this page
County:TRAVISLet Date:05/05/22
Type:INSTALL TRAFFIC SIGNALSeq No:3232
Time:66 WORKING DAYSProject ID:F 2022(500)
Highway:SH 130Contract #:05223232
Length:0.000CCSJ:0440-06-025
Limits: 
From:AT FM 812Check:$8,000
To:.Misc Cost:
Estimate$400,729.94% Over/UnderCompany
Bidder 1$459,288.60+14.61%AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
Bidder 2$467,113.93+16.57%THE LEVY COMPANY, INC.
Bidder 3$536,218.30+33.81%WG ENGINEERING & CONSTRUCTION, LLC
State Let Construction Projects for May, 2022

Text version of this page
County:HARRISONLet Date:05/05/22
Type:RAILROAD CROSSING UPGRADESSeq No:3233
Time:39 WORKING DAYSProject ID:STP 2021(657)FRS1
Highway:CSContract #:05223233
Length:0.100CCSJ:0919-03-063
Limits: 
From:US 80Check:$6,000
To:0.14 MI. S. OF US 80Misc Cost:$39,500.00
Estimate$300,214.00% Over/UnderCompany
Bidder 1$309,959.60+3.25%RAYFORD'S TRUCK & TRACTOR
Bidder 2$333,333.00+11.03%EAST TEXAS BRIDGE, INC.
State Let Construction Projects for May, 2022

Text version of this page
County:GREGGLet Date:05/05/22
Type:BICYCLE AND PEDESTRIAN IMPROVEMENTSSeq No:3234
Time:53 WORKING DAYSProject ID:STP 2022(532)HES
Highway:SS 502Contract #:05223234
Length:0.000CCSJ:0392-08-023
Limits: 
From:AT EDEN STCheck:$5,000
To:.Misc Cost:$3,000.00
Estimate$260,728.91% Over/UnderCompany
Bidder 1$330,073.00+26.60%REYNOLDS & KAY, LTD.
State Let Construction Projects for May, 2022

Text version of this page
County:EASTLANDLet Date:05/05/22
Type:INSTALL/REPLACE SIGNSSeq No:3236
Time:77 WORKING DAYSProject ID:F 2022(553)
Highway:VAContract #:05223236
Length:39.900CCSJ:0923-09-069
Limits: 
From:ON IH 20 FROM CALLAHAN C/LCheck:$14,000
To:ERATH C/LMisc Cost:
Estimate$708,532.55% Over/UnderCompany
Bidder 1$709,237.96+0.10%COMPLETION DOSZIER LLC
Bidder 2$718,381.35+1.39%BATTERSON, LLP
Bidder 3$756,014.77+6.70%MICA CORPORATION
Bidder 4$828,583.60+16.94%WG ENGINEERING & CONSTRUCTION, LLC
State Let Construction Projects for May, 2022

Text version of this page
County:ARMSTRONGLet Date:05/05/22
Type:TRAFFIC SIGNAL IMPROVEMENTSSeq No:3237
Time:104 WORKING DAYSProject ID:C 42-3-44
Highway:US 287Contract #:05223237
Length:0.029CCSJ:0042-03-044
Limits: 
From:AT SH 207Check:$22,000
To:.Misc Cost:
Estimate$1,095,837.23% Over/UnderCompany
Bidder 1$2,102,432.75+91.86%GILVIN-TERRILL, LTD.
State Let Construction Projects for May, 2022

Text version of this page
County:KERRLet Date:05/05/22
Type:HAZARD ELIMINATION & SAFETYSeq No:3238
Time:137 WORKING DAYSProject ID:STP 2022(403)HES
Highway:SH 16Contract #:05223238
Length:34.481CCSJ:0291-03-076
Limits: 
From:0.1 MI NORTH OF THOMPSON DRCheck:$28,000
To:0.1 MI SOUTH OF THOMPSON DRMisc Cost:
Estimate$1,389,046.85% Over/UnderCompany
Bidder 1$1,294,034.49-6.84%E-Z BEL CONSTRUCTION, LLC
Bidder 2$1,604,261.88+15.49%THE LEVY COMPANY, INC.
State Let Construction Projects for May, 2022

Text version of this page
County:TARRANTLet Date:05/05/22
Type:LANDSCAPE DEVELOPMENTSeq No:3239
Time:58 WORKING DAYSProject ID:F 2022(672)
Highway:IH 820Contract #:05223239
Length:0.000CCSJ:0008-15-059
Limits: 
From:0.05 MILES N. OF CLIFFORD STCheck:$8,000
To:0.05 MILES S. OF CLIFFORD STMisc Cost:
Estimate$413,724.80% Over/UnderCompany
Bidder 1$365,571.75-11.64%CENTRAL NORTH CONSTRUCTION, LLC
Bidder 2$396,336.00-4.20%ENCINO LANDSCAPE, INC.
State Let Construction Projects for May, 2022

Text version of this page
County:HIDALGOLet Date:05/05/22
Type:HAZARD ELIMINATION & SAFETYSeq No:3240
Time:239 WORKING DAYSProject ID:STP 2022(728)HES
Highway:VAContract #:05223240
Length:0.000CCSJ:0921-02-483
Limits: 
From:VARIOUS LOCATIONS IN HIDALGO COUNTYCheck:$32,000
To:.Misc Cost:
Estimate$1,611,443.90% Over/UnderCompany
Bidder 1$1,287,240.20-20.12%AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
Bidder 2$1,571,274.75-2.49%TRAF-TEX, INC.
Bidder 3$1,668,245.06+3.52%THE LEVY COMPANY, INC.
Bidder 4$1,889,706.39+17.27%MALDONADO-BURKETT, LLP
State Let Construction Projects for May, 2022

Text version of this page
County:BROWNLet Date:05/04/22
Type:THERMOPLASTIC PAVEMENT MARKINGSSeq No:4001
Time:100 WProject ID:RMC - 639585001
Highway:US0377Contract #:05224001
Length:0.010CCSJ:6395-85-001
Limits: 
From:DISTRICT-WIDECheck:$31,000
To:DISTRICT-WIDEMisc Cost:
Estimate$1,531,830.00% Over/UnderCompany
Bidder 1$1,610,600.00+5.14%STRIPING TECHNOLOGY, L.P.
Bidder 2$1,621,382.50+5.85%D. I. J. CONSTRUCTION, INC.
Bidder 3$1,748,040.00+14.11%TRP CONSTRUCTION GROUP, LLC
Bidder 4$1,856,142.50+21.17%L&L COMPANY
Bidder 5$1,883,075.00+22.93%DOUBLE A CONTRACTING, L.P.
Bidder 6$2,788,250.00+82.02%STRIPE-A-ZONE, LLC
Bidder 7$2,881,422.50+88.10%TOTAL HIGHWAY MAINTENANCE, LLC
Bidder 8$3,277,995.00+113.99%INTERSTATE BARRICADES & MARKINGS, INC.
State Let Maintenance Projects for May, 2022

Text version of this page
County:WALKERLet Date:05/04/22
Type:MILL AND INLAYSeq No:4002
Time:365 CALENDAR DAYSProject ID:RMC - 640051001
Highway:IH0045Contract #:05224002
Length:0.010CCSJ:6400-51-001
Limits: 
From:VARIOUSCheck:$24,000
To:VARIOUSMisc Cost:
Estimate$1,221,835.00% Over/UnderCompany
Bidder 1$1,656,940.00+35.61%CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
Bidder 2$1,725,650.00+41.23%BIG CREEK CONSTRUCTION, LTD.
Bidder 3$2,291,072.00+87.51%TEXAS MATERIALS GROUP, INC.
Bidder 4$2,694,050.00+120.49%KNIFE RIVER CORPORATION - SOUTH
State Let Construction Projects for May, 2022

Text version of this page
County:BRAZOSLet Date:05/04/22
Type:SPOT BASE REPAIRSeq No:4003
Time:365 CALENDAR DAYSProject ID:RMC - 640070001
Highway:SH0006Contract #:05224003
Length:0.010CCSJ:6400-70-001
Limits: 
From:VARIOUSCheck:$14,000
To:VARIOUSMisc Cost:
Estimate$680,640.00% Over/UnderCompany
Bidder 1$898,531.50+32.01%CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
Bidder 2$1,094,329.00+60.78%KNIFE RIVER CORPORATION - SOUTH
Bidder 3$1,260,930.00+85.26%TEXAS MATERIALS GROUP, INC.
State Let Construction Projects for May, 2022

Text version of this page
County:NUECESLet Date:05/04/22
Type:DRY DOCKING FERRY BOATSSeq No:4004
Time:730 CALENDAR DAYSProject ID:RMC - 639689001
Highway:SH0361Contract #:05224004
Length:0.010CCSJ:6396-89-001
Limits: 
From:SH0361Check:$100,000
To:AT FERRY LANDINGMisc Cost:
Estimate$5,193,117.16% Over/UnderCompany
Bidder 1$4,498,625.00-13.37%PALACIOS SHIPYARD, INC.
Bidder 2$5,833,818.55+12.34%TEXAS GULF CONSTRUCTION COMPANY, INC.
State Let Construction Projects for May, 2022