Bid Totals Page 6 of 31

Last Update: Wednesday, June 29, 2022

Site improvements have arrived.

New interactive dashboards on TxDOT.gov make it simple for you to quickly find relevant and up-to-date information. Access them here

Need help finding something? Check out this information page for more details.

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.


1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31

Text version of this page
County:TOM GREENLet Date:05/04/22
Type:HAZARD ELIMINATION & SAFETYSeq No:3007
Time:282 WORKING DAYSProject ID:STP 2022(508)HES
Highway:BU 67-HContract #:05223007
Length:46.147CCSJ:0077-09-010
Limits: 
From:US 87Check:$34,000
To:SL 306Misc Cost:
Estimate$1,702,267.13% Over/UnderCompany
Bidder 1$1,746,965.98+2.63%3LW CIVIL LLC
Bidder 2$1,874,036.31+10.09%RELMCO, INC.
Bidder 3$1,898,927.90+11.55%ENCINO LANDSCAPE, INC.
Bidder 4$2,360,203.25+38.65%SCR CIVIL CONSTRUCTION, LLC
State Let Construction Projects for May, 2022

Text version of this page
County:MATAGORDALet Date:05/04/22
Type:BICYCLE AND PEDESTRIAN IMPROVEMENTSSeq No:3008
Time:240 WORKING DAYSProject ID:F 2022(490)
Highway:SH 35Contract #:05223008
Length:4.400CCSJ:0179-04-100
Limits: 
From:FM 806Check:$60,000
To:FRONT STREET ,ETC.Misc Cost:
Estimate$2,998,158.50% Over/UnderCompany
Bidder 1$2,857,443.00-4.69%TI-ZACK CONCRETE, INC.
Bidder 2$2,877,405.00-4.03%ENCINO LANDSCAPE, INC.
Bidder 3$3,866,000.00+28.95%FNH CONSTRUCTION, LLC
Bidder 4$4,336,771.40+44.65%ALTUS CONSTRUCTION LLC
State Let Construction Projects for May, 2022

Text version of this page
County:ECTORLet Date:05/04/22
Type:HIGHWAY IMPROVEMENTSeq No:3009
Time:186 WORKING DAYSProject ID:STP 2022(497)HES
Highway:SH 302Contract #:05223009
Length:0.000CCSJ:0572-01-072
Limits: 
From:0.4 MI EAST OF SH 158/FM 181Check:$50,000
To:SL 338Misc Cost:
Estimate$2,490,485.29% Over/UnderCompany
Bidder 1$2,334,519.40-6.26%L&L COMPANY
Bidder 2$2,352,186.76-5.55%MIJELUM, L.L.C.
Bidder 3$2,397,732.22-3.72%GRATIOT CONSTRUCTION, LTD.
Bidder 4$2,425,564.16-2.61%SCR CIVIL CONSTRUCTION, LLC
Bidder 5$2,802,268.31+12.52%DAN WILLIAMS COMPANY
Bidder 6$2,977,749.31+19.57%ALTUS CONSTRUCTION LLC
Bidder 7$3,082,809.91+23.78%O. TREVINO CONSTRUCTION, LLC
State Let Construction Projects for May, 2022

Text version of this page
County:DALLASLet Date:05/04/22
Type:INSTALLATION OF WIRELESS ITS SYSTEMSeq No:3010
Time:200 WORKING DAYSProject ID:CM 2022(485)
Highway:US 175Contract #:05223010
Length:21.922CCSJ:0197-02-133
Limits: 
From:IH 635Check:$46,000
To:SH 34Misc Cost:
Estimate$2,293,618.55% Over/UnderCompany
Bidder 1$2,097,982.43-8.53%FLORIDA TRAFFIC CONTROL DEVICES, INC.
Bidder 2$2,625,368.65+14.46%MICA CORPORATION
Bidder 3$2,860,300.37+24.71%SICE, INC.
Bidder 4$3,558,608.70+55.15%HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
State Let Construction Projects for May, 2022

Text version of this page
County:KAUFMANLet Date:05/04/22
Type:INSTALL/REPLACE SIGNSSeq No:3012
Time:320 WORKING DAYSProject ID:F 2022(483)
Highway:US 80Contract #:05223012
Length:4.098CCSJ:0095-04-072
Limits: 
From:EAST OF FM 548Check:$45,000
To:SP 557Misc Cost:
Estimate$2,258,908.36% Over/UnderCompany
Bidder 1$2,575,586.67+14.02%MICA CORPORATION
Bidder 2$2,754,024.22+21.92%CREATIVE DESIGN CONCEPTS, INC.
Bidder 3$3,353,923.25+48.48%HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
State Let Construction Projects for May, 2022

Text version of this page
County:ORANGELet Date:05/04/22
Type:SURFACING/ROADWAY RESTORATIONSeq No:3013
Time:92 WORKING DAYSProject ID:C 28-14-120
Highway:IH 10Contract #:05223013
Length:0.000CCSJ:0028-14-120
Limits: 
From:BOB HALL ROAD, EASTCheck:$52,000
To:BU 90YMisc Cost:
Estimate$2,609,891.42% Over/UnderCompany
Bidder 1$2,592,503.75-0.67%O. TREVINO CONSTRUCTION, LLC
Bidder 2$2,699,750.76+3.44%WINDING ROAD CONSTRUCTION, INC.
Bidder 3$2,796,028.75+7.13%SELECT MAINTENANCE, L.L.C.
Bidder 4$2,986,459.15+14.43%MAIN LANE INDUSTRIES LTD.
State Let Construction Projects for May, 2022

Text version of this page
County:MCLENNANLet Date:05/04/22
Type:HAZARD ELIMINATION & SAFETYSeq No:3014
Time:75 WORKING DAYSProject ID:STP 2022(478)HES
Highway:US 84Contract #:05223014
Length:8.512CCSJ:0055-07-064
Limits: 
From:.4 MI E OF SH 317Check:$31,000
To:OAK CREEK CIRCLEMisc Cost:
Estimate$1,548,265.00% Over/UnderCompany
Bidder 1$1,815,348.44+17.25%ROADWAY SPECIALTIES, INC.
Bidder 2$1,823,846.00+17.80%SCR CIVIL CONSTRUCTION, LLC
Bidder 3$1,830,269.00+18.21%MASSANA CONSTRUCTION INC.
Bidder 4$2,225,520.90+43.74%ALTUS CONSTRUCTION LLC
Bidder 5$2,392,038.70+54.50%O. TREVINO CONSTRUCTION, LLC
State Let Construction Projects for May, 2022

Text version of this page
County:GONZALESLet Date:05/04/22
Type:BRIDGE REPLACEMENTSeq No:3015
Time:184 WORKING DAYSProject ID:BR 2022(492)
Highway:FM 2067Contract #:05223015
Length:0.100CCSJ:0942-02-011
Limits: 
From:AT DENTON CREEKCheck:$50,000
To:STR # 0942-02-003Misc Cost:
Estimate$2,507,357.50% Over/UnderCompany
Bidder 1$2,478,717.66-1.14%HILL COUNTRY BRIDGE, INC.
Bidder 2$2,563,471.48+2.24%SB CONTRACTORS LLC
Bidder 3$3,048,162.85+21.57%CAPITAL EXCAVATION COMPANY
Bidder 4$3,082,241.25+22.93%TEXAS STEEL INDUSTRIAL PLACING, LLC
Bidder 5$3,148,346.30+25.56%STATELINE CONSTRUCTION, LLC
Bidder 6$3,330,695.52+32.84%ACME BRIDGE COMPANY, INC.
Bidder 7$3,615,775.99+44.21%AUSTIN BRIDGE & ROAD SERVICES, LP
Bidder 8$3,836,300.25+53.00%R CONSTRUCTION CIVIL, LLC
Bidder 9$5,335,116.73+112.78%FUQUA CONSTRUCTION CO., INC.
State Let Construction Projects for May, 2022

Text version of this page
County:BEXARLet Date:05/04/22
Type:TRAFFIC SIGNAL IMPROVEMENTSSeq No:3016
Time:260 WORKING DAYSProject ID:C 915-00-237
Highway:VAContract #:05223016
Length:0.001CCSJ:0915-00-237
Limits: 
From:DISTRICTWIDE TRAFFIC CONTROL FY 202Check:$30,000
To:PROJECT 2Misc Cost:
Estimate$1,488,684.57% Over/UnderCompany
Bidder 1$1,606,331.22+7.90%E-Z BEL CONSTRUCTION, LLC
Bidder 2$1,703,277.00+14.41%D&G ENERGY CORPORATION
Bidder 3$2,027,860.47+36.22%THE LEVY COMPANY, INC.
State Let Construction Projects for May, 2022

Text version of this page
County:ANDERSONLet Date:05/04/22
Type:HAZARD ELIMINATION & SAFETYSeq No:3017
Time:47 WORKING DAYSProject ID:STP 2022(533)HES
Highway:VAContract #:05223017
Length:0.001CCSJ:0910-08-081
Limits: 
From:VARIOUS LOCATIONS INCheck:$15,000
To:ANDERSON COMisc Cost:
Estimate$748,230.00% Over/UnderCompany
Bidder 1$757,095.00+1.18%MARCOM'S MOWING SERVICE, LLC
Bidder 2$946,370.00+26.48%STRIPING TECHNOLOGY, L.P.
State Let Construction Projects for May, 2022

Text version of this page
County:SHELBYLet Date:05/04/22
Type:BRIDGE REPLACEMENTSeq No:3018
Time:48 WORKING DAYSProject ID:BR 2B20(125)
Highway:CRContract #:05223018
Length:0.000CCSJ:0911-39-063
Limits: 
From:CR 4123 AT BEAR BAYOUCheck:$8,000
To:CR 4123 AT BEAR BAYOUMisc Cost:
Estimate$421,440.75% Over/UnderCompany
Bidder 1$425,319.60+0.92%L. S. EQUIPMENT CO., INC.
Bidder 2$444,459.52+5.46%THK CONSTRUCTION LLC
Bidder 3$499,923.90+18.62%ENCINO LANDSCAPE, INC.
Bidder 4$500,942.25+18.86%STATELINE CONSTRUCTION, LLC
Bidder 5$546,351.00+29.64%HODGES AND SON CONSTRUCTION COMPANY, INC.
Bidder 6$566,628.30+34.45%CROSS PLUS CONSTRUCTION, LLC
Bidder 7$599,727.95+42.30%EAST TEXAS BRIDGE, INC.
Bidder 8$678,947.15+61.10%DREWERY CONSTRUCTION COMPANY, INCORPORATED
State Let Construction Projects for May, 2022

Text version of this page
County:LIMESTONELet Date:05/04/22
Type:FULL DEPTH BASE REPAIR AND RESURFACESeq No:3019
Time:75 WORKING DAYSProject ID:F 2022(481)
Highway:FM 39Contract #:05223019
Length:2.477CCSJ:0643-03-030
Limits: 
From:SH 14Check:$33,000
To:MEXIA CITY LIMITSMisc Cost:$4,500.00
Estimate$1,650,496.00% Over/UnderCompany
Bidder 1$1,576,056.00-4.51%BIG CREEK CONSTRUCTION, LTD.
Bidder 2$1,628,788.40-1.32%KNIFE RIVER CORPORATION - SOUTH
Bidder 3$1,885,783.41+14.26%TEXAS MATERIALS GROUP, INC.
State Let Construction Projects for May, 2022

Text version of this page
County:POLKLet Date:05/04/22
Type:BRIDGE REPLACEMENTSeq No:3020
Time:52 WORKING DAYSProject ID:BR 2B20(098)
Highway:CRContract #:05223020
Length:0.000CCSJ:0911-04-089
Limits: 
From:KELLEY RD AT BLUFF CREEKCheck:$9,000
To:KELLEY RD AT BLUFF CREEKMisc Cost:
Estimate$436,693.10% Over/UnderCompany
Bidder 1$458,032.40+4.89%CROSS PLUS CONSTRUCTION, LLC
Bidder 2$484,426.00+10.93%STATELINE CONSTRUCTION, LLC
Bidder 3$499,998.10+14.50%ENCINO LANDSCAPE, INC.
Bidder 4$521,693.21+19.46%JOHN REED AND COMPANY, LLC
Bidder 5$583,270.00+33.57%HODGES AND SON CONSTRUCTION COMPANY, INC.
Bidder 6$676,655.65+54.95%DREWERY CONSTRUCTION COMPANY, INCORPORATED
State Let Construction Projects for May, 2022

Text version of this page
County:KARNESLet Date:05/04/22
Type:TRAFFIC SIGNAL IMPROVEMENTSSeq No:3021
Time:88 WORKING DAYSProject ID:STP 2022(543)HES
Highway:US 181Contract #:05223021
Length:2.742CCSJ:0100-05-187
Limits: 
From:ON US181 FROM .5 MI N OF FM81Check:$12,000
To:.5 MI S OF FM81Misc Cost:
Estimate$589,627.65% Over/UnderCompany
Bidder 1$642,568.81+8.98%MALDONADO-BURKETT, LLP
Bidder 2$704,642.82+19.51%F & W ELECTRICAL CONTRACTORS, INC.
Bidder 3$706,754.70+19.86%AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
Bidder 4$760,639.96+29.00%TRAF-TEX, INC.
Bidder 5$810,763.45+37.50%THE LEVY COMPANY, INC.
State Let Construction Projects for May, 2022

Text version of this page
County:HOPKINSLet Date:05/04/22
Type:BRIDGE REPLACEMENTSeq No:3022
Time:128 WORKING DAYSProject ID:BR 2021(759)
Highway:CRContract #:05223022
Length:0.133CCSJ:0901-28-093
Limits: 
From:CR 4714Check:$12,000
To:AT CROOKS CREEKMisc Cost:
Estimate$576,853.43% Over/UnderCompany
Bidder 1$608,037.35+5.41%STATELINE CONSTRUCTION, LLC
Bidder 2$623,991.35+8.17%L. S. EQUIPMENT CO., INC.
Bidder 3$647,856.45+12.31%HIGHWAY 19 CONSTRUCTION LLC
Bidder 4$688,335.75+19.33%HODGES AND SON CONSTRUCTION COMPANY, INC.
Bidder 5$737,773.70+27.90%PIERCE R & B LLC
Bidder 6$774,177.05+34.21%EAST TEXAS BRIDGE, INC.
State Let Construction Projects for May, 2022

Text version of this page
County:EASTLANDLet Date:05/04/22
Type:INSTALL TRAFFIC SIGNALSeq No:3023
Time:109 WORKING DAYSProject ID:F 2022(486)
Highway:SH 112Contract #:05223023
Length:0.000CCSJ:0007-04-134
Limits: 
From:AT IH 20 NORTH FRONTAGE ROADCheck:$20,000
To:.Misc Cost:
Estimate$1,003,312.49% Over/UnderCompany
Bidder 1$1,693,302.70+68.77%O. TREVINO CONSTRUCTION, LLC
Bidder 2$1,773,162.20+76.73%NOBLES ROAD CONSTRUCTION, INC.
Bidder 3$2,364,136.90+135.63%PRATER DIRT WORK LLC
State Let Construction Projects for May, 2022