Bid Totals Page 43 of 47

Last Update: Thursday, December 01, 2022

Bid Tabulations Dashboard

Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.


1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | 41 | 42 | 43 | 44 | 45 | 46 | 47

Text version of this page
County:FREESTONELet Date:12/01/22
Type:ONE-WAY FRONTAGE ROAD CONVERSIONSeq No:3002
Time:794 WORKING DAYSProject ID:F 2023(277)
Highway:IH 45Contract #:12223002
Length:0.000CCSJ:0675-01-069
Limits: 
From:US 84Check:$100,000
To:1.6 MILES NORTH OF FM 27Misc Cost:
Estimate$28,008,368.27% Over/UnderCompany
Bidder 1$35,901,732.19+28.18%A. L. HELMCAMP, INC.
Bidder 2$40,873,565.95+45.93%BIG CREEK CONSTRUCTION, LTD.
State Let Construction Projects for December, 2022

Text version of this page
County:RED RIVERLet Date:12/01/22
Type:PREVENTIVE MAINTENANCESeq No:3003
Time:140 WORKING DAYSProject ID:F 2023(231)
Highway:US 82Contract #:12223003
Length:0.000CCSJ:0045-12-091
Limits: 
From:SH 37Check:$100,000
To:BU 37Misc Cost:
Estimate$14,276,865.48% Over/UnderCompany
Bidder 1$19,399,613.07+35.88%BRANNAN PAVING CO., LTD.
State Let Construction Projects for December, 2022

Text version of this page
County:DENTONLet Date:12/01/22
Type:HIGHWAY OPERATIONS PROGRAMSeq No:3004
Time:378 WORKING DAYSProject ID:F 2022(043)
Highway:IH 35EContract #:12223004
Length:2.727CCSJ:0196-02-132
Limits: 
From:FRANKFORD RDCheck:$100,000
To:CORPORATE DRMisc Cost:$280,000.00
Estimate$16,115,260.77% Over/UnderCompany
Bidder 1$17,598,674.69+9.21%COPASA INC
Bidder 2$19,429,297.72+20.56%SEMA CONSTRUCTION, INC.
Bidder 3$21,884,434.67+35.80%ALTUS CONSTRUCTION LLC
Bidder 4$21,991,999.16+36.47%JAGOE-PUBLIC COMPANY
Bidder 5$23,445,977.44+45.49%RAGLE CONSTRUCTION, INC.
State Let Construction Projects for December, 2022

Text version of this page
County:KENTLet Date:12/01/22
Type:SEAL COATSeq No:3005
Time:103 WORKING DAYSProject ID:F 2023(256)
Highway:US 380Contract #:12223005
Length:7.734CCSJ:0263-01-021
Limits: 
From:SH 70Check:$100,000
To:SH 70Misc Cost:
Estimate$11,058,873.37% Over/UnderCompany
Bidder 1$10,460,911.96-5.41%RONALD R. WAGNER & CO., LP
Bidder 2$11,256,028.77+1.78%LIPHAM ASPHALT AND PAVING COMPANY, LLC
Bidder 3$11,645,808.49+5.31%NORTHEASTERN PAVERS, LLC
Bidder 4$13,749,892.35+24.33%CK NEWBERRY, LLC
State Let Construction Projects for December, 2022

Text version of this page
County:ECTORLet Date:12/01/22
Type:HIGHWAY IMPROVEMENTSeq No:3006
Time:255 WORKING DAYSProject ID:F 2022(586)
Highway:SL 338Contract #:12223006
Length:0.000CCSJ:2224-01-118
Limits: 
From:US385NCheck:$100,000
To:SH 191Misc Cost:
Estimate$17,010,312.97% Over/UnderCompany
Bidder 1$18,181,464.70+6.88%RK HALL, LLC
Bidder 2$21,994,180.60+29.30%FNF CONSTRUCTION, INC.
Bidder 3$24,843,752.17+46.05%JONES BROS. DIRT & PAVING CONTRACTORS, INC.
State Let Construction Projects for December, 2022

Text version of this page
County:DALLASLet Date:12/01/22
Type:BRIDGE MAINTENANCESeq No:3008
Time:365 WORKING DAYSProject ID:BR 2023(096)
Highway:IH 45Contract #:12223008
Length:1.346CCSJ:0092-14-098
Limits: 
From:IH 30Check:$100,000
To:PENNSYLVANIA AVEMisc Cost:
Estimate$5,998,532.97% Over/UnderCompany
Bidder 1$5,125,904.79-14.55%GIBSON & ASSOCIATES, INC.
Bidder 2$6,303,110.25+5.08%RAGLE CONSTRUCTION, INC.
State Let Construction Projects for December, 2022

Text version of this page
County:CULBERSONLet Date:12/01/22
Type:REHABILITATE EXISTING ROADWAYSeq No:3009
Time:110 WORKING DAYSProject ID:C 20-1-22
Highway:US 90Contract #:12223009
Length:0.000CCSJ:0020-01-022
Limits: 
From:BI 10-D (BROADWAY ST)Check:$100,000
To:3.95 MI N OF FM 1523Misc Cost:
Estimate$5,718,574.44% Over/UnderCompany
Bidder 1$6,496,447.39+13.60%DAN WILLIAMS COMPANY
Bidder 2$6,611,504.50+15.61%INTERNATIONAL EAGLE ENTERPRISES, INC.
State Let Construction Projects for December, 2022

Text version of this page
County:WEBBLet Date:12/01/22
Type:BRIDGE REPLACEMENTSeq No:3010
Time:437 WORKING DAYSProject ID:BR 2021(892)
Highway:CRContract #:12223010
Length:0.329CCSJ:0922-33-159
Limits: 
From:WORMSER RD AT DOLORES CREEK RELIEFCheck:$67,000
To:.Misc Cost:$86,000.00
Estimate$3,374,329.75% Over/UnderCompany
Bidder 1$4,871,880.84+44.38%RELMCO, INC.
Bidder 2$4,917,131.20+45.72%CK NEWBERRY, LLC
State Let Construction Projects for December, 2022

Text version of this page
County:BREWSTERLet Date:12/01/22
Type:PREVENTIVE MAINTENANCESeq No:3011
Time:40 WORKING DAYSProject ID:F 2023(268)
Highway:SH 118Contract #:12223011
Length:0.000CCSJ:0358-05-018
Limits: 
From:17.35 MI N FM 170Check:$99,000
To:2.75 MI S FM 170Misc Cost:
Estimate$4,933,492.18% Over/UnderCompany
Bidder 1$5,327,450.03+7.99%COX PAVING OF TEXAS, INC.
Bidder 2$5,776,887.64+17.10%BRANNAN PAVING CO., LTD.
State Let Construction Projects for December, 2022

Text version of this page
County:FAYETTELet Date:12/01/22
Type:REHABILITATE EXISTING ROADWAYSeq No:3012
Time:120 WORKING DAYSProject ID:F 2022(658)
Highway:US 77Contract #:12223012
Length:1.500CCSJ:0268-01-056
Limits: 
From:FM 155Check:$76,000
To:1.50 MI SOUTH OF FM 155Misc Cost:
Estimate$3,824,673.10% Over/UnderCompany
Bidder 1$3,760,967.65-1.67%BIG CREEK CONSTRUCTION, LTD.
Bidder 2$4,051,320.09+5.93%HUNTER INDUSTRIES, LTD.
Bidder 3$4,426,087.51+15.72%DUNN SERVICES, INC.
Bidder 4$4,431,914.04+15.88%TEXAS MATERIALS GROUP, INC.
Bidder 5$4,842,785.76+26.62%KNIFE RIVER CORPORATION - SOUTH
Bidder 6$5,245,831.07+37.16%ACME BRIDGE COMPANY, INC.
State Let Construction Projects for December, 2022

Text version of this page
County:BANDERALet Date:12/01/22
Type:BRIDGE REPLACEMENTSeq No:3013
Time:206 WORKING DAYSProject ID:BR 2021(338)
Highway:CRContract #:12223013
Length:0.125CCSJ:0915-47-039
Limits: 
From:ENGLISH CROSSING RDCheck:$55,000
To:AT MEDINA RIVERMisc Cost:
Estimate$2,766,308.36% Over/UnderCompany
Bidder 1$2,422,534.82-12.43%RELMCO, INC.
Bidder 2$2,498,043.16-9.70%E-Z BEL CONSTRUCTION, LLC
Bidder 3$2,498,999.98-9.66%HARPER BROTHERS CONSTRUCTION LLC
Bidder 4$2,892,195.10+4.55%CAPITAL EXCAVATION COMPANY
Bidder 5$3,140,000.00+13.51%MILLING SERVICES
Bidder 6$3,255,553.54+17.69%ACME BRIDGE COMPANY, INC.
State Let Construction Projects for December, 2022

Text version of this page
County:TRAVISLet Date:12/01/22
Type:RESURFACE ROADWAYSeq No:3014
Time:54 WORKING DAYSProject ID:F 2023(265)
Highway:RM 2222Contract #:12223014
Length:0.000CCSJ:2100-01-069
Limits: 
From:RIBELIN RANCH DRIVECheck:$52,000
To:SL 360Misc Cost:
Estimate$2,584,954.63% Over/UnderCompany
Bidder 1$2,999,888.08+16.05%TEXAS MATERIALS GROUP, INC.
Bidder 2$3,220,310.74+24.58%HUNTER INDUSTRIES, LTD.
Bidder 3$3,565,591.40+37.94%LONE STAR PAVING COMPANY
State Let Construction Projects for December, 2022

Text version of this page
County:DONLEYLet Date:12/01/22
Type:BRIDGE REPLACEMENTSeq No:3015
Time:210 WORKING DAYSProject ID:BR 2023(281)
Highway:FM 291Contract #:12223015
Length:0.000CCSJ:0795-05-010
Limits: 
From:@ WHITEFISH CREEKCheck:$72,000
To:.Misc Cost:
Estimate$3,586,776.30% Over/UnderCompany
Bidder 1$3,892,082.00+8.51%EARTH BUILDERS, L.P.
Bidder 2$4,034,270.79+12.48%COPPELL CONSTRUCTION CO., INC.
Bidder 3$4,464,646.75+24.48%GILVIN-TERRILL, LTD.
Bidder 4$4,675,665.20+30.36%J. LEE MILLIGAN, INC.
State Let Construction Projects for December, 2022

Text version of this page
County:LUBBOCKLet Date:12/01/22
Type:TRAFFIC SIGNAL IMPROVEMENTSSeq No:3016
Time:260 WORKING DAYSProject ID:C 905-00-112
Highway:VAContract #:12223016
Length:0.001CCSJ:0905-00-112
Limits: 
From:VARIOUS LOCATIONS INCheck:$51,000
To:THE LUBBOCK DISTRICTMisc Cost:
Estimate$2,548,575.63% Over/UnderCompany
Bidder 1$2,731,558.50+7.18%VACA UNDERGROUND UTILITIES INC
Bidder 2$2,815,704.40+10.48%WILLIS ELECTRIC CO., LP
State Let Construction Projects for December, 2022

Text version of this page
County:STERLINGLet Date:12/01/22
Type:REPLACE BRIDGE AND APPROACHESSeq No:3017
Time:187 WORKING DAYSProject ID:BR 2023(234)
Highway:SH 163Contract #:12223017
Length:0.000CCSJ:0333-02-013
Limits: 
From:AT WILLOW CREEKCheck:$42,000
To:.Misc Cost:
Estimate$2,121,104.30% Over/UnderCompany
Bidder 1$2,615,605.00+23.31%DELGADO'S CONTRACTORS, LLC
Bidder 2$3,234,186.15+52.48%ACME BRIDGE COMPANY, INC.
Bidder 3$3,255,589.66+53.49%COPPELL CONSTRUCTION CO., INC.
Bidder 4$4,056,441.08+91.24%RAGLE CONSTRUCTION, INC.
State Let Construction Projects for December, 2022

Text version of this page
County:HARRISLet Date:12/01/22
Type:SURFACING/ROADWAY RESTORATIONSeq No:3018
Time:109 WORKING DAYSProject ID:C 177-7-118
Highway:IH 69Contract #:12223018
Length:0.000CCSJ:0177-07-118
Limits: 
From:SL 8 EASTCheck:$34,000
To:FM 1960Misc Cost:
Estimate$1,694,149.85% Over/UnderCompany
Bidder 1$975,659.05-42.41%STRIPE LINES, INC.
Bidder 2$1,202,421.02-29.03%PROFESSIONAL TRAFFIC CONTROL LLC
Bidder 3$1,217,147.45-28.16%BATTERSON, LLP
State Let Construction Projects for December, 2022