Bid Totals Page 46 of 48

Last Update: Friday, September 29, 2023

Bid Tabulations Dashboard

Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.


1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | 41 | 42 | 43 | 44 | 45 | 46 | 47 | 48

Text version of this page
County:LAMARLet Date:09/21/23
Type:JANITORIAL MAINTENANCESeq No:0109
Time:365 CALENDAR DAYSProject ID:RMC - 645493001
Highway:BU0271BContract #:09230109
Length:0.000CCSJ:6454-93-001
Limits: 
From:JANITORIAL MAINTENANCECheck:$1,000
To:AT PARIS DISTRICT HEADQUARTERSMisc Cost:
Estimate$51,450.00% Over/UnderCompany
Bidder 1$44,200.00-14.09%RWCS JANITORIAL LLC
Bidder 2$44,971.00-12.59%KLEEN SWEEP SERVICES
State Let Construction Projects for September, 2023

Text version of this page
County:PALO PINTOLet Date:09/21/23
Type:CRACK SEALSeq No:0201
Time:90 WProject ID:RMC - 644569001
Highway:US0180Contract #:09230201
Length:0.000CCSJ:6445-69-001
Limits: 
From:VARIOUS LOCATIONS WITHINCheck:$3,000
To:PALO PINTO COUNTYMisc Cost:
Estimate$150,708.01% Over/UnderCompany
Bidder 1$224,930.65+49.25%CRACKSEAL OF TEXAS, LLC
Bidder 2$258,533.00+71.55%D & M CONTRACTORS, LLC
State Let Construction Projects for September, 2023

Text version of this page
County:JOHNSONLet Date:09/21/23
Type:CRACK SEALSeq No:0203
Time:33 WProject ID:RMC - 644244001
Highway:FM2331Contract #:09230203
Length:0.000CCSJ:6442-44-001
Limits: 
From:JOHNSON COUNTYCheck:$3,000
To:VARIOUS LIMITSMisc Cost:
Estimate$164,598.16% Over/UnderCompany
Bidder 1$285,232.09+73.29%CRACKSEAL OF TEXAS, LLC
Bidder 2$391,320.00+137.74%D & M CONTRACTORS, LLC
State Let Construction Projects for September, 2023

Text version of this page
County:TARRANTLet Date:09/21/23
Type:CRACK SEALSeq No:0204
Time:90 WProject ID:RMC - 637919001
Highway:IH0820Contract #:09230204
Length:0.000CCSJ:6379-19-001
Limits: 
From:VARIOUS LOCATIONS INCheck:$2,000
To:TARRANTMisc Cost:
Estimate$98,324.11% Over/UnderCompany
Bidder 1$247,320.00+151.54%CRACKSEAL OF TEXAS, LLC
Bidder 2$299,700.00+204.81%D & M CONTRACTORS, LLC
State Let Construction Projects for September, 2023

Text version of this page
County:PALO PINTOLet Date:09/21/23
Type:HOT MIXSeq No:0205
Time:180 CALENDAR DAYSProject ID:MMC - 645008001
Highway:SH0016Contract #:09230205
Length:0.000CCSJ:6450-08-001
Limits: 
From:VARIOUS LOCATIONS WITHINCheck:$6,000
To:PALO PINTO COUNTYMisc Cost:
Estimate$289,967.50% Over/UnderCompany
Bidder 1$380,000.00+31.05%TOUCHSTONE RESOURCES, LLC
State Let Construction Projects for September, 2023

Text version of this page
County:WISELet Date:09/21/23
Type:REFLECTORIZED PAVEMENT MARKINGS & MARKERSSeq No:0207
Time:365 CALENDAR DAYSProject ID:RMC - 644867001
Highway:US0380Contract #:09230207
Length:0.000CCSJ:6448-67-001
Limits: 
From:VARIOUS LOCATIONS INCheck:$4,000
To:WISE & JACK COUNTIESMisc Cost:
Estimate$202,212.00% Over/UnderCompany
Bidder 1$272,370.00+34.70%TRP CONSTRUCTION GROUP, LLC
State Let Construction Projects for September, 2023

Text version of this page
County:SAN JACINTOLet Date:09/21/23
Type:HOT MIX/SP, TY C & HMCL/SAN JACINTOSeq No:1160
Time:120 CALENDAR DAYSProject ID:MMC - 645307001
Highway:SH0150Contract #:09231160
Length:0.000CCSJ:6453-07-001
Limits: 
From:SAN JACINTO COUNTY MAINTENANCE YARDCheck:$5,000
To:SAN JACINTO COUNTY MAINTENANCE YARDMisc Cost:
Estimate$248,171.50% Over/UnderCompany
Bidder 1$234,454.00-5.53%TEXAS MATERIALS GROUP, INC.
State Let Construction Projects for September, 2023

Text version of this page
County:TRINITYLet Date:09/21/23
Type:HOT MIX/SP & TY D/TRINITYSeq No:1161
Time:120 CALENDAR DAYSProject ID:MMC - 645334001
Highway:SH0094Contract #:09231161
Length:0.000CCSJ:6453-34-001
Limits: 
From:TRINITY COUNTY MAINTENANCE YARDCheck:$5,000
To:TRINITY COUNTY MAINTENANCE YARDMisc Cost:
Estimate$263,590.00% Over/UnderCompany
Bidder 1$244,450.00-7.26%VULCAN CONSTRUCTION MATERIALS, LLC
Bidder 2$263,233.50-0.14%TEXAS MATERIALS GROUP, INC.
State Let Construction Projects for September, 2023

Text version of this page
County:DIMMITLet Date:09/21/23
Type:LIMESTONE ROCK ASPHALTSeq No:2202
Time:182 CALENDAR DAYSProject ID:MMC - 645455001
Highway:US0277Contract #:09232202
Length:0.000CCSJ:6454-55-001
Limits: 
From:VARIOUSCheck:$6,000
To:VARIOUSMisc Cost:
Estimate$298,273.00% Over/UnderCompany
Bidder 1$330,275.00+10.73%MARTIN MARIETTA MATERIALS, INC.
Bidder 2$338,485.00+13.48%VULCAN CONSTRUCTION MATERIALS, LLC
State Let Construction Projects for September, 2023

Text version of this page
County:LASALLELet Date:09/21/23
Type:DE-ICING SALTSeq No:2203
Time:182 CALENDAR DAYSProject ID:MMC - 645471001
Highway:IH0035Contract #:09232203
Length:0.000CCSJ:6454-71-001
Limits: 
From:VARIOUSCheck:$1,000
To:VARIOUSMisc Cost:
Estimate$29,000.00% Over/UnderCompany
Bidder 1$29,600.00+2.07%SOUTHWEST ENVIROTX PARTNERS, LLC
State Let Construction Projects for September, 2023

Text version of this page
County:LASALLELet Date:09/21/23
Type:EMULSIONSeq No:2204
Time:182 CALENDAR DAYSProject ID:MMC - 645485001
Highway:IH0035Contract #:09232204
Length:0.000CCSJ:6454-85-001
Limits: 
From:VARIOUSCheck:$3,000
To:VARIOUSMisc Cost:
Estimate$140,800.00% Over/UnderCompany
Bidder 1$146,960.00+4.38%ERGON ASPHALT & EMULSIONS, INC.
State Let Construction Projects for September, 2023

Text version of this page
County:TYLERLet Date:09/26/23
Type:ASPHALTIC PATCHING MATERIALSeq No:2055
Time:365 CALENDAR DAYSProject ID:MMC - 645413001
Highway:FM0256Contract #:09232055
Length:0.000CCSJ:6454-13-001
Limits: 
From:DISTRICTWIDECheck:$6,000
To:DISTRICTWIDEMisc Cost:
Estimate$288,000.00% Over/UnderCompany
Bidder 1$283,691.00-1.50%TEXAS MATERIALS GROUP, INC.
Bidder 2$292,468.00+1.55%WALLER COUNTY ASPHALT INC.
Bidder 3$345,200.00+19.86%TOUCHSTONE RESOURCES, LLC
State Let Construction Projects for September, 2023

Text version of this page
County:JEFFERSONLet Date:09/26/23
Type:HOT-MIX COLD-LAIDSeq No:2056
Time:365 CALENDAR DAYSProject ID:MMC - 645558001
Highway:US0069Contract #:09232056
Length:0.000CCSJ:6455-58-001
Limits: 
From:DISTRICTWIDECheck:$5,000
To:DISTRICTWIDEMisc Cost:
Estimate$267,780.00% Over/UnderCompany
Bidder 1$307,200.00+14.72%TEXAS MATERIALS GROUP, INC.
State Let Construction Projects for September, 2023

Text version of this page
County:LIBERTYLet Date:09/26/23
Type:HOT-MIX COLD-LAIDSeq No:2057
Time:365 CALENDAR DAYSProject ID:MMC - 645573001
Highway:US0090Contract #:09232057
Length:0.000CCSJ:6455-73-001
Limits: 
From:DISTRICTWIDECheck:$4,000
To:DISTRICTWIDEMisc Cost:
Estimate$179,000.00% Over/UnderCompany
Bidder 1$215,000.00+20.11%TEXAS MATERIALS GROUP, INC.
State Let Construction Projects for September, 2023

Text version of this page
County:ORANGELet Date:09/26/23
Type:HOT-MIX COLD-LAIDSeq No:2058
Time:365 CALENDAR DAYSProject ID:MMC - 645571001
Highway:SH0062Contract #:09232058
Length:0.000CCSJ:6455-71-001
Limits: 
From:DISTRICTWIDECheck:$2,000
To:DISTRICTWIDEMisc Cost:
Estimate$98,550.00% Over/UnderCompany
Bidder 1$116,250.00+17.96%TEXAS MATERIALS GROUP, INC.
State Let Construction Projects for September, 2023

Text version of this page
County:WEBBLet Date:09/26/23
Type:LIMESTONE ROCK ASPHALTSeq No:2205
Time:182 CALENDAR DAYSProject ID:MMC - 645429001
Highway:IH0035Contract #:09232205
Length:0.000CCSJ:6454-29-001
Limits: 
From:VARIOUSCheck:$6,000
To:VARIOUSMisc Cost:
Estimate$299,600.00% Over/UnderCompany
Bidder 1$345,020.00+15.16%VULCAN CONSTRUCTION MATERIALS, LLC
Bidder 2$357,990.00+19.49%MARTIN MARIETTA MATERIALS, INC.
State Let Construction Projects for September, 2023